Sinclair Refining Co. v. Burch

16 N.W.2d 359, 235 Iowa 594, 1944 Iowa Sup. LEXIS 505
CourtSupreme Court of Iowa
DecidedNovember 14, 1944
DocketNo. 46466.
StatusPublished
Cited by22 cases

This text of 16 N.W.2d 359 (Sinclair Refining Co. v. Burch) is published on Counsel Stack Legal Research, covering Supreme Court of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sinclair Refining Co. v. Burch, 16 N.W.2d 359, 235 Iowa 594, 1944 Iowa Sup. LEXIS 505 (iowa 1944).

Opinions

*595 Garfield, J.

This is a companion case to Hercules Mfg. Co. v. Burch, No. 46485, 235 Iowa 568. The principal distinction between the two cases is that in the Hercules ease Burch completed the work but here he defaulted.

The contract here, made May 3, 1940, was for grading on a primary-road project in Yan Burén county. On May 15th the contractor assigned to Iowa State Bank and Trust Company of Fairfield all sums to become due under the contract. The assignment secured indebtedness which Burch subsequently incurred to the bank upon which there was owing more than the amount still in the hands of the highway commission. On September 16, 1940, at Burch’s request, the highway commission declared the contract in default. The balance of the work was relet by the commission to Booth and Olson. .

Following Burch’s default, Maryland Casualty Company, surety on the contractor’s bond in the sum of $22,500, paid claims for labor and material furnished Burch totaling $4,393.25. These' claims were then assigned to the surety. During June and July the highway commission paid the Fairfield bank on the Burch contract $17,294.24, ninety per cent of three estimates totaling $19,215.82. Ten per cent of this last figure, $1,921.58, was retained by the commission in accordance with the contract. There was also $1,347.53 unpaid on the-Burch contract at the time of his default, in addition to the ten per cent previously retained. The total in the hands of the commission at the time suit was brought was $3,269.11, of which $2,056.33 was ten per cent of the full amount earned by Burch. It was conceded the surety, as subrogee of laborers and materialmen paid by it, was entitled to this $2,056.33. The contest is over the balance of $1,212.78 in the commission’s hands. The trial court awarded .this amount to the assignee bank. The surety has appealed.

All contentions appellant makes here are disposed of by our opinion in Hercules Mfg. Co. v. Burch, except the claim that since Burch defaulted in performing his contract the entire unpaid amount, not merely the ten per cent retention fund, is made available by section 10320, Code, 1939, for the payment of claimants for labor and material and appellant as their subrogee. In the Hercules case it was not necessary to decide this contention because there Burch fully performed his eon- *596 tract. ¥e there held that the only fund available to claimants for labor and material on a completed contract is the percentage of the contract price which the highway commission is required to retain. The question now before us is whether by reason of section 10320 a different rule prevails where the contractor abandons the work. We think section 10320 does not have the effect appellant claims for it.

The primary rule in interpreting a statute is to ascertain and give effect to the intention of the legislature. Smith v. Thompson, 219 Iowa 888, 896, 258 N. W. 190; Keokuk Waterworks Co. v. Keokuk, 224 Iowa 718, 723, 277 N. W. 291; 50 Am. Jur. 200, 201, section 223; 59 C. J. 948, section 568. Tu determining the meaning of section 10320 it should be considered in the light of the whole chapter (452) and every other section therein. Wood Bros. Thresher Co. v. Eicher, 231 Iowa 550, 560,1 N. W. 2d 655, 660; Ahrweiler v. Board of Supervisors, 226 Iowa 229, 231, 283 N. W. 889; 59 C. J. 1042, 1046, section 620. All provisions of the chapter should be considered as parts of a connected whole and .harmonized if possible. Brutsche v. Incorporated Town of Coon Rapids, 218 Iowa 1073, 1081, 256 N. W. 914; In re Estate of Van Vechten, 218 Iowa 229, 234, 251 N. W. 729; Smith v. Thompson, supra; 50 Am. Jur. 367, 368, section 363; 59 C. J. 1051, section 621. The purpose or aim of the legislation is also to be considered. Wood Bros. Thresher Co. v. Eicher, supra; 50 Am. Jur. 283, 284, section 303; 59 C. J. 961, section 571.

It is a familiar rule that the manifest intent of the legislature will prevail over the literal import of the words used; that a thing which is within the intention of the lawmakers is as much within the statute as if it were within the letter; and a thing within the letter of the statute" is not within the statute unless it is within the intention of the legislature. 50 Am. Jur. 232, 234, 235, section 240; 59 C. J. 96A-967, section 573 ; Sexton v. Sexton, 129 Iowa 487, 488, 489, 105 N. W. 314, 2 L. R. A., N. S., 708; Oliphant v. Hawkinson, 192 Iowa 1259, 1263, 183 N. W. 805, 33 A. L. R. 1433; McGraw v. Seigel, 221 Iowa 127, 132, 263 N. W. 553, 106 A. L. R.1035.

Section 10320 states:

“Abandonment of public work — effect. When a contractor *597 abandons the work on a public improvement or is legally excluded therefrom, the improvement shall be deemed completed for the purpose of filing claims as herein provided, from the date of the official cancellation of the contract. The only fund available for the payment of the claims of persons for labor performed or material furnished shall be the amount then due the contractor, if any, and if said amount be insufficient to satisfy said claims, the claimants shall have a right of action on the bond given for the performance of the contract.”

Detaching the second sentence of this section, upon which appellant relies, from chapter 452 as a whole, the words “said amount,” italicized by us, refer back to “the amount then due the contractor,” and purport to give claimants a right of action on the bond only if such amount is insufficient to pay their claims. Considering the chapter as a whole, however, the legislative intent is plain that there is a right, of action on the bond if the percentage of the contract price which the public corporation is required to retain (here ten per cent) is insufficient to satisfy claims.

Section 10304 directs that such a bond as appellant signed must provide:

“The principal and sureties on this bond hereby agree to pay * * * all just claims * * * for labor performed or materials furnished, in the performance of the contract * * * when the same are not satisfied out of the portion of the contract price which the public corporation is required to retain until completion of the public improvement * * *.”

The bond signed by appellant here contains this identical provision.

Section 10319 provides:

“Unpaid claimants — judgment on bond. If, after the said retained percentage has been applied to the payment of duly filed and established claims, there remain any such claims unpaid in whole or in part, judgment shall be entered for the amount thereof against the principal and sureties on the bond. In case the said percentage has been paid over as herein provided, *598 judgment shall be entered against the principal and sureties on all such claims.”

If we are to harmonize sections 10304, 10319, and 10320, the terms “the amount .then due the contractor” and “said amount” found in the later section must be construed to refer to the percentage fund required to be retained.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Employers Mutual Casualty Co. v. City of Marion
577 N.W.2d 657 (Supreme Court of Iowa, 1998)
Farmers Cooperative Co. v. DeCoster
528 N.W.2d 536 (Supreme Court of Iowa, 1995)
Saemisch v. Ley Motor Co.
387 N.W.2d 357 (Supreme Court of Iowa, 1986)
State v. Paschal
300 N.W.2d 115 (Supreme Court of Iowa, 1981)
First Federal State Bank v. Town of Malvern
270 N.W.2d 818 (Supreme Court of Iowa, 1978)
Hedges v. Conder
166 N.W.2d 844 (Supreme Court of Iowa, 1969)
Janson v. Fulton
162 N.W.2d 438 (Supreme Court of Iowa, 1968)
Consolidated Freightways Corp. of Del. v. Nicholas
137 N.W.2d 900 (Supreme Court of Iowa, 1965)
State Ex Rel. Board of Pharmacy Examiners v. McEwen
96 N.W.2d 189 (Supreme Court of Iowa, 1959)
Spencer Publishing Company v. City of Spencer
92 N.W.2d 633 (Supreme Court of Iowa, 1958)
Selken v. Northland Insurance Company
90 N.W.2d 29 (Supreme Court of Iowa, 1958)
Grant v. Norris
85 N.W.2d 261 (Supreme Court of Iowa, 1957)
Ferguson v. Brick
82 N.W.2d 849 (Supreme Court of Iowa, 1957)
State Ex Rel. Pieper v. Patterson
70 N.W.2d 838 (Supreme Court of Iowa, 1955)
Jones v. Thompson
38 N.W.2d 672 (Supreme Court of Iowa, 1949)

Cite This Page — Counsel Stack

Bluebook (online)
16 N.W.2d 359, 235 Iowa 594, 1944 Iowa Sup. LEXIS 505, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sinclair-refining-co-v-burch-iowa-1944.