Community School District of Eldora v. Employers Mutual Casualty Co. of Des Moines

194 F. Supp. 733, 7 A.F.T.R.2d (RIA) 1519, 1961 U.S. Dist. LEXIS 5111
CourtDistrict Court, N.D. Iowa
DecidedJune 2, 1961
DocketCiv. No. 670
StatusPublished
Cited by2 cases

This text of 194 F. Supp. 733 (Community School District of Eldora v. Employers Mutual Casualty Co. of Des Moines) is published on Counsel Stack Legal Research, covering District Court, N.D. Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Community School District of Eldora v. Employers Mutual Casualty Co. of Des Moines, 194 F. Supp. 733, 7 A.F.T.R.2d (RIA) 1519, 1961 U.S. Dist. LEXIS 5111 (N.D. Iowa 1961).

Opinion

GRAVEN, District Judge.

This is a case involving priority among unpaid materialmen of a contractor, a Federal tax lien, and the claim of the-owner of the improved property for attorney fees. The trial was to the Court.

On March 3, 1958, the Community School District of Eldora, an Iowa public school corporation, entered into a contract with Sid Smith & Co., an Iowa corporation. The first corporation will be hereinafter referred to as the Owner and the latter corporation as the Contractor. Under the contract, the Contractor was to furnish all of the materials and perform all of the work in connection with the plumbing, heating and ventilation of an auditorium in a gymnasium addition to be erected for the Owner. The contract price was $53,-500. The work was to be completed on or before November 1, 1958. The contract provided for supervision by an architect. The contract was a standard printed form of contract with blanks-provided to be filled in by typewriter. The filled-in words are indicated by underscoring in the paragraphs next set forth. Article 4 of the contract provided' as follows:

“Article 4. Progress Payments— The Owner shall make payments on. [736]*736account of the Contract as provided therein, as follows:
“On or about the 15th day of each month Ninety (90%) per cent of the value, based on the Contract prices of labor and materials incorporated in the work and of materials suitably stored at the site thereof up to the first day of that month, as estimated by the Architect, less the aggregate of previous payments; and upon substantial completion of the entire work, a sum sufficient to increase the total payments to 90% per cent of the Contract price”

Article 5 of the contract provided, in part, as follows:

“Article 5. Acceptance and Final Payment — Final payment shall be due forty (40) days after substantial completion of the work provided the work be then fully completed and the contract fully performed.
“Upon receipt of written notice that the work is ready for final inspection and acceptance, the Architect shall promptly make such inspection, and when he finds the work acceptable under the Contract and the Contract fully performed he shall promptly issue a final certificate, over his own signature, stating that the work provided for in this Contract has been completed and is accepted by him under the terms and conditions thereof, and that the entire balance found to be due the Contractor, and noted in said final certificate, is due and payable.
“Before issuance of final certificate the Contractor shall submit evidence satisfactory to the Architect that all payrolls, material bills, and other indebtedness connected with the work have been paid.”

Chapter 573, Code of Iowa 1958,1.C.A., requires that in connection with contracts for public improvements a contractor shall furnish a bond for the protection of those furnishing materials or labor for the improvement which shall be in an amount not less than seventy-five percent of the contract price. In accord with the provisions of that Chapter, the Contractor furnished a combination performance and labor and material payment bond with the defendant, Employers Mutual Casualty' Company of Des Moines, as surety in the principal sum of $53,500. That defendant will hereinafter be referred to as the Bonding Company. Section 573.6 of Chapter 573 provides, in part, as follows:

“The following provisions shall be held to be a part of every bond given for the performance of a contract for the construction of a public improvement * * *:
“1. The principal and sureties on this bond hereby agree to pay to all persons, firms, or corporations having contracts directly with the principal * * * all just claims due them for labor performed or materials furnished, in the performance of the contract on account of which this bond is given, when the same are not satisfied out of the portion of the contract price which the public corporation is required to retain until completion of the public improvement * * *.”

Chapter 573 provides for the filing of claims with the board of the public corporation by those whose claims for material or labor have not been paid. Section 573.10 of that Chapter provides, in part:

“Claims may be filed * * *
“1. At any time before the expiration of thirty days immediately following the completion and final acceptance of the improvement. * *

On February 21, 1958, prior to the time the Contractor entered into the contract herein involved, the Government had made an assessment against the Contractor for unpaid withholding taxes in a substantial amount. At different times thereafter during the year of 1958 and the forepart, of the year of [737]*7371959, the Government made additional assessments against the Contractor for unpaid withholding taxes. Those assessments became tax liens upon their assessment. The total amount of those liens is much greater than any amounts here in controversy. For convenience in reference, the Government’s tax liens will hereinafter be referred to in the singular.

The Contractor proceeded with the performance under his contract with the Owner. Upon approval of and certification by the architect, the Owner paid the Contractor progress payments in the sum of $47,254.57, the last payment of which was made on or about January 22, 1959. The architect has never certified that the improvement has been completed in accord with the provisions of the contract.

On March 4, 1959, the defendant, Johnson Service Company, filed a claim with the Owner for the amount due it for labor and materials furnished for the improvement. During the next few months several other parties who had furnished labor and materials for the improvement, for which they had not been paid, also filed claims with the Owner. The amount of those claims was established at an earlier hearing before this Court. The amounts so established and the dates of the filing of them are as follows:

3/ 4/59 Johnson Service Company $4,026.00

4/16/59 Titus Manufacturing Corporation 872.47

4/28/59 A. Y. McDonald Mfg. Co. 3,452.55

4/29/59 Eldora Heating & Supply Co. 181.51

5/18/59 The Trane Company 2,203.45

These claims were all filed within the time prescribed by Section 573.10 heretofore referred to.

Sections 573.12, 573.13 and 573.14 of Chapter 573 provide as follows:

“573.12 Retention from payments on contracts. Payments made under contracts for the construction of public improvements, unless provided otherwise by law, shall be made on the basis of monthly estimates of labor performed and material delivered ; said payments to be made for not more than ninety percent of said estimates and to be so made that at least ten percent of the contract price will remain unpaid at the date of the completion of the contract, anything in the contract to the contrary notwithstanding.”
“573.13 Inviolability and disposition of fund.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Spahn & Rose Lumber Co. v. Iowa Steel & Construction Co.
131 N.W.2d 791 (Supreme Court of Iowa, 1964)

Cite This Page — Counsel Stack

Bluebook (online)
194 F. Supp. 733, 7 A.F.T.R.2d (RIA) 1519, 1961 U.S. Dist. LEXIS 5111, Counsel Stack Legal Research, https://law.counselstack.com/opinion/community-school-district-of-eldora-v-employers-mutual-casualty-co-of-des-iand-1961.