Hanna v. Huer, Johns, Neel, Rivers & Webb

662 P.2d 243, 233 Kan. 206, 1983 Kan. LEXIS 296
CourtSupreme Court of Kansas
DecidedApril 20, 1983
Docket54,238
StatusPublished
Cited by39 cases

This text of 662 P.2d 243 (Hanna v. Huer, Johns, Neel, Rivers & Webb) is published on Counsel Stack Legal Research, covering Supreme Court of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hanna v. Huer, Johns, Neel, Rivers & Webb, 662 P.2d 243, 233 Kan. 206, 1983 Kan. LEXIS 296 (kan 1983).

Opinion

The opinion of the court was delivered by

Holmes, J.:

This is an appeal by the defendant, Huer, Johns, Neel, Rivers and Webb, a professional corporation and formerly a partnership, (hereafter Huer, Johns, or the architect) from two judgments entered upon jury verdicts in favor of two construction workmen for personal injuries received on the construction jobsite. The injured workmen, O. D. Pearman and Duone Hanna, filed separate suits which were consolidated for trial in the district court. Huer, Johns appeals from each judgment and the cases remain consolidated on appeal.

The plaintiffs were ironworkers employed by American Construction Erection Services Company, Inc., of Wichita (ACE-SCO). ACESCO was hired as a subcontractor to erect the structural steel in the construction of a Dillard’s department store building in Wichita’s Towne East Shopping Center. ACESCO was hired by The Law Company of Wichita. The Law Company was technically a subcontractor itself under the general contractor, Pickens & Bond Construction Company of Little Rock, Arkansas. The Law Company, however, functioned in the manner of a general contractor on the project site and will be considered as such for the purposes of this appeal, and will be-referred to as the general contractor. Huer, Johns, under a contract with the project owner Dillard’s, was responsible for drafting the documents for the owner-builder contract, including the plans, specifications and general conditions and was also responsible for the general administration of the construction contract.

The accident which injured Hanna and Pearman occurred about 3:00 p.m. on October 18, 1974. At that time Hanna was the foreman of the detail gang for ACESCO. Pearman was a welder on Hanna’s crew. The detail gang was responsible for permanently securing the structural steel once it had been put into place by the company’s raising gang. The unfortunate accident which resulted in serious injuries to each plaintiff occurred when a steel tie joist that Pearman was sitting on at an upper level of the building’s steel skeleton fell, hitting Hanna, knock *208 ing him to a lower level floor and then into an elevator shaft. The tie joist that Pearman was sitting on should have been secured by the raising gang to the steel structure at one end by either bolting or tack welding, but was not. In addition the joist was not the proper length and was fabricated for use in another part of the building. The combination of the tie joist being too short and the failure to secure it at one end to the steel beam resulted in the joist being dislodged from its position and the injuries to the plaintiffs. Plaintiffs assumed the joist was properly secured at one end when, in fact, it was kept aloft merely because each end was resting upon beams which were already in place. Pearman made no inspection of the length of the joist nor determined if it was securely fastened to the beam and Hanna could not see the ends of the joist from his position below.

Plaintiffs originally filed suit against their employer, the general contractors on the job, the steel fabricator, the owner and the architect. At the time of trial, Huer, Johns was the only viable defendant remaining in the action for the purpose of liability although the jury was instructed to apportion the comparative fault for the accident in each case among each plaintiff, the general contractors, the employer, the owner and the defendant Huer, Johns.

Plaintiffs’ action was based upon two theories of liability, both based upon negligence. First, they contend that the employment contract between Huer, Johns and Dillard’s included the responsibility for safety precautions upon the project. It is contended that ACESCO was notoriously derelict in providing safe working conditions and that if defendant had not been negligent in the performance of its contractual duties in administering the construction of the project the accident would not have happened. Second, it is contended that if Huer, Johns did not breach its contractual duties it was at least guilty of negligence which was the proximate cause of plaintiffs’ injuries. Defendant, on the other hand, asserted there was no contractual duty to supervise or maintain safety standards on the project and that there was no professional negligence on its part. Huer, Johns had been the architects for Dillard’s on several construction projects and did not have a written contract of employment apart from the contract between Dillard’s and the general contractor.

Clyde Webb, a principal in Huer, Johns, testified that it was *209 his firm’s responsibility under its oral contract with Dillard’s to design the building, develop the contracts, plans and specifications and “get it built.” The contract documents prepared by Huer, Johns included the plans, drawings, specifications and American Institute of Architects Document A201. A201, along with the plans, etc., described therein and collectively called the contract documents, constituted the construction contract between the owner and the general contractor. Although Huer, Johns was not a party signatory to that contract, in addition to setting out the agreements between the owner and the general contractor, it also specifies the duties of the architect and contains certain provisions pertaining to the subcontractors. All parties rely on certain provisions of A201 and there is no serious contention that A201 is not a part of the oral agreement between Huer, Johns and Dillard’s. Plaintiffs contend that under the oral employment agreement, including A201, Huer, Johns was responsible for safety conditions on the project; that ACESCO was notorious for its failure to follow safety procedures; that defendant knew or should have known ACESCO was sloppy and careless in its work and therefore Huer, Johns was liable for plaintiffs’ injuries.

There was considerable testimony about the careless procedures followed by ACESCO and such unsafe practices were well known to The Law Company’s safety man on the project, to its superintendents and to plaintiffs who had been employees of ACESCO for some time. However, it is also clear that no one ever advised Huer, Johns of the numerous problems being experienced with ACESCO.

Mr. Webb said he visited the construction site on occasion and others from his firm visited the site periodically for the purpose of fulfilling Huer, Johns’ obligation to the project owner to make certain that the construction was progressing satisfactorily and conformed to the plans and specifications. It was Huer, Johns’ obligation to require that the contractor lived up to its agreement with the owner. Huer, Johns periodically approved completed work in order for the builders to be paid. Webb testified that he never made any inquiries about jobsite safety and that safety was not part of Huer, Johns’ responsibility. He knew The Law Company, which was acting as . the general contractor on the project, had a safety program and a safety man on the project, and *210 he was satisfied with that knowledge. He also testified he was not aware of any safety problems with ACESCO and had been advised of none.

Steven Harrell, an employee of The Law Company, was its safety inspector and responsible for safety conditions on the construction project. He testified that his function was to make inspections and review the subcontractors’ work.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

George Waltman v. Engineering Plus, Inc.
264 So. 3d 758 (Mississippi Supreme Court, 2019)
David McKean v. Yates Engineering Corporation
200 So. 3d 431 (Mississippi Supreme Court, 2016)
David McKean v. Yates Engineering Corporation
210 So. 3d 1037 (Court of Appeals of Mississippi, 2015)
Evergreen Engineering, Inc. v. Green Energy Team LLC
884 F. Supp. 2d 1049 (D. Hawaii, 2012)
Edwards v. Anderson Engineering, Inc.
166 P.3d 1047 (Supreme Court of Kansas, 2007)
Roe Ex Rel. Roe v. Department of Social & Rehabilitation Services
80 P.3d 1162 (Court of Appeals of Kansas, 2003)
Hobson v. Waggoner Engineering, Inc.
878 So. 2d 68 (Court of Appeals of Mississippi, 2003)
Estate of Beckner v. Jensen
24 P.3d 169 (Court of Appeals of Kansas, 2001)
Glaser Ex Rel. Glaser v. Emporia Unified School District No. 253
21 P.3d 573 (Supreme Court of Kansas, 2001)
Herczeg v. Hampton Township Municipal Authority
766 A.2d 866 (Superior Court of Pennsylvania, 2001)
Fisher v. M. Spinelli & Sons Co.
9 Mass. L. Rptr. 638 (Massachusetts Superior Court, 1999)
Jones v. James Reeves Contractors, Inc.
701 So. 2d 774 (Mississippi Supreme Court, 1997)
McAninch v. Robinson
942 S.W.2d 452 (Missouri Court of Appeals, 1997)
Peck v. Horrocks Engineering
Tenth Circuit, 1997
Calwell v. Hassan
925 P.2d 422 (Supreme Court of Kansas, 1996)
Stewart v. NationaLease of Kansas City, Inc.
920 F. Supp. 1188 (D. Kansas, 1996)
Nicholson v. turner/cargile
669 N.E.2d 529 (Ohio Court of Appeals, 1995)
Calwell v. Hassan
908 P.2d 184 (Court of Appeals of Kansas, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
662 P.2d 243, 233 Kan. 206, 1983 Kan. LEXIS 296, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hanna-v-huer-johns-neel-rivers-webb-kan-1983.