George Waltman v. Engineering Plus, Inc.

264 So. 3d 758
CourtMississippi Supreme Court
DecidedMarch 7, 2019
DocketNO. 2017-CA-01747-SCT
StatusPublished
Cited by3 cases

This text of 264 So. 3d 758 (George Waltman v. Engineering Plus, Inc.) is published on Counsel Stack Legal Research, covering Mississippi Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
George Waltman v. Engineering Plus, Inc., 264 So. 3d 758 (Mich. 2019).

Opinion

KITCHENS, PRESIDING JUSTICE, FOR THE COURT:

¶1. In 2013, Lauderdale County contracted with Norman Enterprises, Inc., a roofing company, to repair the roof of the Ulmer Building in Meridian, Mississippi. George Waltman, an employee of Norman Enterprises, fell through the roof while performing work. Waltman sued Engineering Plus, Inc., the project engineer, claiming it should have warned him of the dangerous condition of the roof. Engineering Plus moved for summary judgment, arguing it had no duty to warn Waltman. The Lauderdale County Circuit Court agreed and granted summary judgment to Engineering Plus. We affirm.

FACTS AND PROCEDURAL HISTORY

¶2. In the summer of 2012, the Lauderdale County Board of Supervisors sought to replace the roofs of several county-owned buildings. A representative of the Board contacted Terrell Temple, an engineer and the president of Engineering Plus, to hire Temple's company as the project engineer for the Ulmer Building and Mount Barton School roof-repair projects in Meridian, Mississippi. Engineering Plus prepared the project details, the contract documents, and the bid paperwork to facilitate the Board's hiring a general contractor. Those documents set forth the scope of the projects and the responsibilities of the general contractor.

¶3. In February 2013, Lauderdale County advertised for bids using the documents prepared by Engineering Plus. Norman Enterprises submitted a bid, which the county accepted. On March 18, 2013, Lauderdale County entered into a contract that incorporated the bid details, with Norman Enterprises as the general contractor for the Ulmer Building project.

¶4. George Waltman, an employee of Norman Enterprises, worked on the Ulmer Building project. After Norman Enterprises had received the notice to proceed with the project, Waltman went to the Ulmer Building on July 23, 2013, to begin removing debris from the roof in preparation for the repairs. Within minutes of arriving at the site, Waltman stepped onto a deteriorated area of the roof and fell through, suffering injuries.

¶5. Waltman sued the project engineer, Engineering Plus, claiming that it knew of the dangerous condition of the roof and should have warned him. Engineering Plus filed a motion for summary judgment on the basis that it had no contractual or common law duty to warn Norman Enterprises's employees of the condition of the roof. The circuit court agreed with Engineering Plus.

¶6. On November 16, 2017, the circuit court entered a memorandum opinion and order in which it granted Engineering Plus's motion for summary judgment and dismissed the cause. Waltman appealed.

STANDARD OF REVIEW

¶7. When parties appeal a grant or denial of summary judgment, this Court employs a de novo standard of review. Bullock v. Life Ins. Co. of Miss. , 872 So.2d 658 , 660 (¶ 6) (Miss. 2004). On de novo review, no deference is given to a lower court's decision.

McArthur v. Ingalls Shipbuilding, Inc. , 879 So.2d 500 , 502 (Miss. Ct. App. 2004). This Court reviews all the evidence in the light most favorable to the non-moving party. Id.

ANALYSIS

¶8. "When the proof regarding only one element of a plaintiff's claim fails, the defendant is entitled to summary judgment, despite any factual disputes regarding the remaining elements of the claim." Hernandez v. Vickery Chevrolet-Oldsmobile Co. , 652 So.2d 179 , 183 (Miss. 1995) (citing Grisham v. John Q. Long V.F.W. Post , 519 So.2d 413 , 416 (Miss. 1988) ). The issue in this case involves only one element of George Waltman's claim: whether Engineering Plus had a duty to warn him of the dangerous condition of the roof. For an engineer to have an affirmative duty to warn of dangerous conditions, the engineer must have taken on, either by contract or conduct, the responsibility of maintaining the safety of the construction project. McKean v. Yates Eng'g Corp. , 200 So.3d 431 , 435 (Miss. 2016). 1

I. Engineering Plus did not assume a duty by contract.

¶9. George Waltman argues that Engineering Plus assumed a contractual duty to supervise the Ulmer Building project based on the following language in the contract between Lauderdale County and Norman Enterprises: "It is further agreed that the work[ ] shall be done under the direct supervision and to the complete satisfaction of the County Engineer or his authorized representatives." 2 The contract as a whole, however, indicates that the parties did not intend for Engineering Plus to be responsible for the safety of Waltman.

¶10. The contract specifies that Norman Enterprises was

responsible for all loss or damage arising out of the nature of the work aforesaid, or from the action of the elements, and unforeseen obstruction or difficulties which may be encountered in the prosecution of the same and for all risks of every description connected with the work for faithfully completing the whole work[.]

The contract further provides that Norman Enterprises "shall satisfy [itself] of the existing size and conditions of the project area." Other provisions of the contract reinforce the proposition that Norman Enterprises was the only party responsible for safety at the project's work site.

¶11. American Jurisprudence, Second Edition, sets out the following general rules of contract interpretation when two or more provisions are arguably in conflict:

Where there is an apparent repugnancy or conflict between two clauses or provisions of a contract, it is the province and duty of the court to find harmony between them and to reconcile them if possible.... No contract provision should be construed as being in conflict with another unless no other reasonable interpretation or construction is possible.... Where a repugnancy is found between clauses, ... [t]he clause contributing most essentially to the contract is entitled to the greater consideration, and a subsidiary provision should be so interpreted as not to be in conflict with what clearly appears to be the dominant purpose of the contract.... [T]his rule is tempered by the corollary that the more specific clause controls the more general.

17A Am. Jur. 2d Contracts § 374 (citations omitted).

¶12.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
264 So. 3d 758, Counsel Stack Legal Research, https://law.counselstack.com/opinion/george-waltman-v-engineering-plus-inc-miss-2019.