Gulf States Utilities Company v. Federal Power Commission, Southwest Louisiana Electric Membership Corporation, Intervenor

518 F.2d 450, 171 U.S. App. D.C. 57, 1975 U.S. App. LEXIS 13028
CourtCourt of Appeals for the D.C. Circuit
DecidedAugust 22, 1975
Docket74-1160
StatusPublished
Cited by32 cases

This text of 518 F.2d 450 (Gulf States Utilities Company v. Federal Power Commission, Southwest Louisiana Electric Membership Corporation, Intervenor) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gulf States Utilities Company v. Federal Power Commission, Southwest Louisiana Electric Membership Corporation, Intervenor, 518 F.2d 450, 171 U.S. App. D.C. 57, 1975 U.S. App. LEXIS 13028 (D.C. Cir. 1975).

Opinions

Opinion for the Court filed by Circuit Judge LEVENTHAL.

LEVENTHAL, Circuit Judge:

In July of 1950 Gulf States Utilities Company (Gulf States) and the Southwest Louisiana Electric Membership Cooperative (SLEMCO) entered into a contract for the supply of electrical energy by Gulf States to SLEMCO. That agreement, which set a maximum demand ceiling of some 8,000 kilowatts,1 was held by the Federal Power Commission, on June 14, 1973, to be a fixed-rate contract that barred unilateral rate increases by the supplier for deliveries of electricity.2

In its order of October 19, 1973, denying SLEMCO’s application for rehearing of the June 14th order, the Commission interpreted an August 1970 letter agreement modifying the 1950 contract as removing the demand ceiling, thus making all energy supplied by Gulf States to SLEMCO subject to the contract and to the fixed contract rates.3 We are asked to review this interpretation of the 1970 agreement. We affirm the conclusion of the Commission.

I. LEGAL BACKGROUND

The Federal Power Act, 16 U.S.C. §§ 824 et seq. (1970), requires, in § 205(c),4 that every public utility file schedules of its rates and charges for sales subject to the Commission’s jurisdiction. Section 205(d)5 prohibits any change in previously filed rates from taking effect except by filing with the Commission, after thirty days’ notice upheld FPC’s determination and § 205(e)6 [452]*452authorizes the Commission to suspend the new rates for up to five months pending a hearing on whether the change is just and reasonable. Section 206(a)7 allows the Commission, upon its own motion or upon complaint, to hold a hearing on whether a rate is “unjust, unreasonable, unduly discriminatory or preferential” and to fix a new rate if the filed rate is found to be unlawful.

The Supreme Court has held that these provisions do not authorize the Commission to approve unilateral rate increases that are inconsistent with a seller’s contractual obligations. See United Gas Pipe Line Co. v. Mobile Gas Service Corp., 350 U.S. 332, 76 S.Ct. 373, 100 L.Ed. 373 (1956); FPC v. Sierra Pacific Power Co., 350 U.S. 348, 76 S.Ct. 368, 100 L.Ed. 388 (1956). Rather, they provide “only for notice to the Commission of the rates established by the natural gas companies” — either ex parte or through negotiation, as the particular contract provides — “and for review by the Commission of those rates.” United Gas Pipe Line Co. v. Mobile Gas Service Corp., supra, 350 U.S. at 343, 76 S.Ct. at 380. The Commission has the power, under § 206(a), to require a rate change not agreed to by the parties, but its sole concern in such a proceeding is “whether the rate is so low as to adversely affect the public interest ... as distinguished from the private interests of the utilities.” FPC v. Sierra Pacific Power Co., supra, 350 U.S. at 355, 76 S.Ct. at 372. If the contract between the parties reserves to the seller the privilege to change the rate unilaterally, there is no bar to Commission acceptance, subject to its review powers under §§ 205(e) and 206(a). United Gas Pipe Line Co. v. Memphis Light, Gas & Water Division, 358 U.S. 103, 79 S.Ct. 194 (1958).

We have said:

The rule of Sierra, Mobile and Memphis is refreshingly simple: The contract between the parties governs the legality of the filing. Rate filings consistent with contractual obligations are valid; rate filings inconsistent with contractual obligations are invalid.

Richmond Power & Light v. FPC, 156 U.S.App.D.C. 315, 318, 481 F.2d 490, 493, cert. denied sub nom. Indiana & Michigan Electric Co. v. FPC, 414 U.S. 1068, 94 S.Ct. 578, 38 L.Ed.2d 472 (1973). Thus, in deciding whether to accept a filing of a rate increase made unilaterally by the seller the Commission must decide whether the parties intended to allow such unilateral changes or whether the contract established a fixed rate that can be changed only through mutual negotiation.

II. THE FACTUAL SETTING

The original contract between Gulf States and SLEMCO for the furnishing of electricity was framed in 1950. Article III, paragraph B of that contract set an initial maximum commitment of 5,700 kilowatts, which could be increased up to 8,000 kilowatts. In article I, five points of delivery were established, with a “maximum capacity” in terms of kilowatts specified for each point. The contract provided that, “[u]pon written application by Customer and if agreeable to Company, additional points of delivery may be established . . ..” Article V provided that SLEMCO should pay “for all electric energy furnished hereunder at the rates . . . set forth in Rate Schedule REA, attached. . . . ” and that, [it is further agreed that] should SLEMCO sell to any consumer “other than those specified in the availability clause of Schedule REA, such schedule shall no longer apply.” In that case a new rate shall be negotiated, and if “parties fail to agree on a proper applicable rate, then said agreement shall be cancelled.”

Between March of 1951 and July of 1963, the 1950 contract was amended six times by letter agreements that made changes and additions in delivery points but made no increase in the maximum [453]*453commitment. However, Gulf States routinely delivered electricity to SLEMCO far in excess of the contract maximum. In 1962, 35,579 kilowatts were delivered; in 1963, 45,090 kilowatts; and in 1970, 99,437 kilowatts.

In April of 1973, Gulf States filed new rate schedules with the FPC that would increase all its wholesale rates effective June 15, 1973. These schedules were to affect Gulf States’ contract with SLEMCO, as well as its contracts with other customers. In its filing Gulf States said that most of its contracts expressly contemplated unilateral rate increases and that, where the contract did not provide for unilateral increases, the new rates were to apply to deliveries in excess of the maximum contractual commitment.

In a separate docket, on May 4, 1973, Gulf States filed the letter agreement of August 1970 that modified and extended the 1950 contract with SLEMCO, as amended through July of 1963. That agreement specified inter alia that “Company will interpret language of the [contract] to be no less favorable than would be the case if Exhibit A . were incorporated . . ., .” Exhibit A contained four paragraphs. The first specified that Gulf States “will provide additional capacity ... as [SLEMCO’s] Normal Load Growth warrants ..” The second provided for the supply of “additional capacity, over and above Normal Load Growth” in certain circumstances.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Shell Energy North America (US), L.P. v. FERC
107 F.4th 981 (D.C. Circuit, 2024)
Southern California Edison Co. v. United States
43 Fed. Cl. 107 (Federal Claims, 1999)
Garkane Power Ass'n v. Public Service Commission of Utah
681 P.2d 1196 (Utah Supreme Court, 1984)
Philadelphia Electric Co. v. Borough of Lansdale
424 A.2d 514 (Superior Court of Pennsylvania, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
518 F.2d 450, 171 U.S. App. D.C. 57, 1975 U.S. App. LEXIS 13028, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gulf-states-utilities-company-v-federal-power-commission-southwest-cadc-1975.