New England Power Company v. Federal Energy Regulatory Commission, Central Maine Power Company, Intervenor

571 F.2d 1213, 187 U.S. App. D.C. 264, 1977 U.S. App. LEXIS 5542, 1977 WL 365237
CourtCourt of Appeals for the D.C. Circuit
DecidedDecember 21, 1977
Docket75-1945
StatusPublished
Cited by8 cases

This text of 571 F.2d 1213 (New England Power Company v. Federal Energy Regulatory Commission, Central Maine Power Company, Intervenor) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
New England Power Company v. Federal Energy Regulatory Commission, Central Maine Power Company, Intervenor, 571 F.2d 1213, 187 U.S. App. D.C. 264, 1977 U.S. App. LEXIS 5542, 1977 WL 365237 (D.C. Cir. 1977).

Opinions

LEVENTHAL, Circuit Judge:

This case arises out of a dispute among the New England utilities which built and own the Maine Yankee nuclear power plant over the allocation of transmission costs among them. Unable to agree on the financial arrangements, Central Maine Power Co. (Central Maine) unilaterally filed with the Federal Power Commission (FPC) a rate modification relieving itself of the obligation to make certain payments. The FPC found that the resulting rates were not unreasonable, a ruling not challenged here. The New England Power Co. (NEPCO) claims that the filing, even if reasonable, was a unilateral filing not permitted under the utilities’ Transmission Agreement, and hence impermissible under United Gas Pipe Line Co. v. Memphis Light, Gas & Water Division, 358 U.S. 103, 79 S.Ct. 194, 3 L.Ed.2d 153 (1958). The FPC rejected NEPCO’s position. We affirm the FPC ruling as a reasonable contract interpretation, consistent with the record of the negotiations leading to the Transmission Agreement.

I. BACKGROUND

In 1966, eleven New England utilities (“sponsors”) agreed to build and operate the Maine Yankee nuclear generating plant in Wiscasset, Maine. The three Maine sponsors use about half of the power from Maine Yankee. To secure the participation of the non-Maine sponsors in the joint venture, the Maine utilities apparently agreed in principle to bear the costs of transmitting the power to the Maine-New Hampshire border to permit further transmission to the southern New England power grid. The exact terms were left to be worked out later.

The Transmission Agreement was signed by the twelve transmitting utilities on April 1, 1971. It was negotiated under the pressure of a deadline established by the SEC in the settlement of an antitrust claim by municipal utilities.1 The provisions critical for this case are in sections 4, 5, and 10, excerpted in the appendix. The municipals were allowed to purchase some of the Maine Yankee power, and to become parties to the agreement by executing a supplement. To complete the settlement, a provision for allocating transmission costs, acceptable to the municipals, had to be worked out. Section 4 of the Transmission Agreement (“Payment for Transmission [1215]*1215Services Received”) provided that the parties pay into a fund the percentage of transmission costs equal to the percentage of Maine Yankee’s power that they take, an allocation technique known as the “postage stamp” method.2 The fund is then distributed to the utilities providing the transmission services in reimbursement of the costs of transmission. In place of its obligation to provide the transmission facilities to the New Hampshire border, Central Maine agreed to pay into the fund for the power it took, even though it did not receive transmission services from any other utility, since Maine Yankee is located within its service area.3

Subsequent to the original undertaking, it turned out that Central Maine had to build two 345 kilovolt transmission lines rather than the single line originally anticipated. Central Maine sought financial support for this extra undertaking from the other utilities. At various times, most of them responded favorably to Central Maine’s position. However, at the time of completion of the Transmission Agreement, no arrangement for financial relief of Central Maine had been agreed upon.

Since the matter could not be settled in the hectic negotiations carried out to produce the purchase and transmission agreements to meet the SEC settlement deadline, Central Maine proposed that each transmitting party be allowed to file modified rates with the FPC, unilaterally, subject to acceptance by the FPC. Being on notice that Central Maine intended to use the right to file a modified rate structure as a “final last straw”4 in its efforts to obtain transmission support, petitioner New England Power Co. (NEPCO), sought to require unanimous action by the transmitting parties to file modified rates with the FPC. NEPCO failed in this. The disputed § 10 of the Transmission Agreement permits unilateral filing, restricted however by a parenthetical provision which is the focus of this case. Section 10 provides in pertinent part:

Each transmitting party reserves the right to submit for filing without the concurrence of any other party a New England power pool agreement and from time to time other rate schedules (with an annual rate determined in accordance with the method set forth in Section 4 hereof) modifying or superseding this Agreement and each party reserves the right to object to any such New England power pool agreement and other rate schedules in accordance with Federal Power Commission rules and regulations.

R. 392-93 (emphasis added).

Unable to reach agreement on relief from its transmission costs, Central Maine unilaterally filed a modification of the rate schedule on February 14, 1973, shortly after Maine Yankee began commercial operation.5 The modification amended § 4 of the [1216]*1216Transmission Agreement to require payments only from utilities receiving transmission service from others. This had the sole effect of removing Central Maine’s obligation to pay into the pooled transmission account. On April 10, 1973, the FPC accepted Central Maine’s proposed modification to be effective thirty days after its filing and instituted an investigation into the lawfulness of the modification pursuant to § 206(a) of the Federal Power Act, 16 U.S.C. § 824e(a). Hearings were held before the Presiding Administrative Law Judge (ALJ) on August 22-24, 1973. In his initial decision of September 3, 1974, the ALJ found that the proposed modification was not contractually barred and that the resulting rates were not unjust or unreasonable. Exceptions were taken to this decision by NEPCO and four other parties to the Transmission Agreement. On July 3, 1975, the FPC issued an order affirming the ALJ’s initial decision and on August 25, 1975 an order denying NEPCO’s motion for rehearing.6

NEPCO alone appeals the FPC’s decision. The appeal is solely on the basis that the unilateral filing is not permitted under the Sierra-Mobile-Memphis doctrine.7

The modification relieves Central Maine of payments of about $1.2 million annually. Central Maine maintained that the annual carrying charges for the two 345 kilovolt transmission lines is about $3.8 million, so that it has recouped less than half of its transmission costs by the modification.8 Furthermore, Central Maine testified to its intent to withdraw the modification in 1986, by which time it projects that its load will have increased to the point that “two lines would have been necessary for the use of the Central Maine system alone and that they would have been built by then regardless of Maine Yankee.” 9 The modification must be taken as just and reasonable in amount. The only question is whether it is permissible under the Sierra-Mobile-Memphis doctrine.

II. LEGALITY OF THE FILING

A. The Sierra-Mobile-Memphis Doctrine

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
571 F.2d 1213, 187 U.S. App. D.C. 264, 1977 U.S. App. LEXIS 5542, 1977 WL 365237, Counsel Stack Legal Research, https://law.counselstack.com/opinion/new-england-power-company-v-federal-energy-regulatory-commission-central-cadc-1977.