Green v. Ziegelman

767 N.W.2d 660, 282 Mich. App. 292
CourtMichigan Court of Appeals
DecidedFebruary 3, 2009
DocketDocket 280624
StatusPublished
Cited by77 cases

This text of 767 N.W.2d 660 (Green v. Ziegelman) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Green v. Ziegelman, 767 N.W.2d 660, 282 Mich. App. 292 (Mich. Ct. App. 2009).

Opinion

MURPHY, EJ.

Defendants appeal as of right a $156,313 judgment entered by the circuit court in favor of plaintiffs and against defendant Norman H. Ziegelman (Ziegelman), individually, on plaintiffs’ claim of breach of an agreement for architectural services. Ziegelman’s *294 liability for the breach was determined postjudgment through proceedings supplementary to the initial judgment, and liability was predicated on an alter ego theory, with the court piercing the corporate veil of a corporation owned by Ziegelman. The initial judgment on the claim for breach of the architectural agreement, which judgment was founded on an arbitration award, was entered solely against defendant Norman H. Ziegelman Architects, Inc. (NZA). We vacate the judgment at issue.

Plaintiffs Sanford Green, Jack R. Hendrickson, and Thomas Esper, along with defendant Ziegelman, were all members of plaintiff Libwag, LLC, which was formed to undertake a real estate development project. The Libwag operating agreement contained an arbitration provision for purposes of settling disputes arising out of the agreement. Shortly after the development project commenced, Libwag entered into architectural and construction contracts with, respectively, NZA and defendant Continental Construction Company (Continental). Ziegelman was the sole shareholder of both NZA and Continental.

A dispute arose concerning the development project and the operating agreement, and Ziegelman demanded arbitration for an alleged breach of the operating agreement, which plaintiffs denied, making their own claim that Ziegelman breached the operating agreement. The parties also disagreed regarding the proper composition of the arbitration panel and the scope of the arbitration provision. Given the dispute, plaintiffs, except for Lib-wag, filed a declaratory judgment action in the circuit court against Ziegelman, seeking the proper interpretation of the arbitration provision contained in the operating agreement with respect to its scope and the number of arbitrators to sit in judgment. Ziegelman *295 then filed a motion for summary disposition and to compel arbitration. The circuit court, pursuant to MCR 2.116(I)(2), granted summary disposition in favor of plaintiffs, ruling that it had the authority to address the issue concerning the number of arbitrators to be selected and that the dispute must be arbitrated by four arbitrators, as argued by plaintiffs, and not one, as argued by Ziegelman. The circuit court ordered the case to arbitration.

Pursuant to an arbitration agreement thereafter executed by all plaintiffs and all defendants, the parties agreed to arbitrate: (1) all issues by and between Libwag and NZA arising under the architectural agreement, with the arbitration award being final and binding upon the parties to that agreement, (2) all issues by and between Libwag and Continental arising under the construction contract, with the arbitration award being final and binding upon the parties to that agreement, and (3) all issues by and between NZA and Libwag and Hendrickson that were currently pending in a federal district court lawsuit involving copyright infringement claims. 1 The agreement expressly superseded the arbitration provisions found in the architectural and construction contracts. Pursuant to the Libwag operating agreement, the alleged breaches of the agreement were also set to be arbitrated under the agreement’s arbitration provision. It is abundantly clear that the parties had decided to resolve all their disputes in arbitration. No mention was made regarding a claim against Ziegelman individually for breach of the architectural agreement, let alone a claim that he was liable for a breach of *296 the architectural agreement predicated on a liability theory of piercing the corporate veil.

The issues and disputes were arbitrated, and the arbitration panel rendered an award concluding that NZA had breached the architectural agreement and that plaintiffs were entitled to a damages award of $156,313 against NZA for the breach. 2 The arbitration panel also found that Ziegelman himself had breached the operating agreement and that his membership interest in Libwag had to be reduced to 7V2 percent because of the breach. 3 Further, the arbitration panel ruled that neither side had demonstrated a breach of the construction contract. Finally, the arbitration panel concluded that NZA had failed to establish its copyright infringement claims, which had been the subject of the federal lawsuit.

Plaintiffs then proceeded to file a motion in the circuit court to reopen the case, to add Libwag, NZA, and Continental as parties, given that they were not named in the complaint seeking declaratory relief, and to enter judgment upon the arbitration award. Plaintiffs made no attempt at this point to pursue a claim against Ziegelman personally for breach of the architectural agreement, nor was any theory posited regarding the need to pierce the corporate veil. Subsequently, the circuit court entered an order granting plaintiffs’ motion. The order provided that judgment was to be entered pursuant to the arbitration award. A judgment, entered the same day that the order granting plaintiffs’ motion was granted, provided, in relevant part, that NZA had breached the architectural agreement. The judgment also stated:

*297 IT IS FURTHER ORDERED AND ADJUDGED that Libwag and Green and Hendrickson and Esper shall have Judgment in favor of them and against [NZA] in the amount of $156,313.00, plus statutory interest from and after April 27, 2006, and execution shall so issue therefore.

Nowhere in the judgment is it provided that Ziegelman was liable for breach of the architectural agreement.

Approximately three months later, plaintiffs filed an ex parte motion under the proceedings supplementary to judgment act (PSJA), which is found at MCL 600.6101 et seq., and MCR 2.621. In the motion, plaintiffs requested an order requiring NZA to produce a laundry list of financial records and documents, requiring Ziegelman, as president of NZA, to appear for a discoveiy hearing in order to testify regarding NZA assets, and requiring NZA to produce certain documents at the discovery hearing. Plaintiffs also sought an order restraining NZA from transferring assets. Plaintiffs further requested that, “if it appears on hearing hereof that other parties hold in their names property beneficially or equitably belonging to [NZA], such parties may be joined in this proceeding.” An order granting the motion was subsequently entered, but it said nothing about any other party being joined in the supplementary proceedings. Ziegelman then submitted to a discovery deposition as president of NZA. The deposition revealed that NZA had no assets and only $400 in accounts receivable. It also revealed evidence that arguably could serve as a basis for piercing NZA’s corporate veil and holding Ziegelman personally liable, suggesting that NZA was nothing more than Ziegelman’s alter ego. 4 On the strength of the deposition, plaintiffs filed a motion to

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Simone Mauro v. Anthony Marrocco
Michigan Court of Appeals, 2025
Michelle Busuito v. Dte Energy Company
Michigan Court of Appeals, 2025
Trg Advisory Ltd v. Mg Realty LLC
Michigan Court of Appeals, 2025
People of Michigan v. James Edward Matthews
Michigan Court of Appeals, 2025
Deborah Moorehead v. Van Buren Public Schools
Michigan Court of Appeals, 2025
In Re Thomas Lis Trust
Michigan Court of Appeals, 2025
In Re P Garner Minor
Michigan Court of Appeals, 2025
Lockwood v. Professional Neurological Services, Ltd.
2025 IL App (1st) 231705 (Appellate Court of Illinois, 2025)
20250122_C368569_50_368569.Opn.Pdf
Michigan Court of Appeals, 2025
20250115_C365154_66_365154.Opn.Pdf
Michigan Court of Appeals, 2025
20241206_C363572_41_363572.Opn.Pdf
Michigan Court of Appeals, 2024
Home Title Connect LLC v. Mill Creek LLC
Michigan Court of Appeals, 2024
Susan Jaber v. Jacob E Randall
Michigan Court of Appeals, 2024
Nossonal Kleinfeldt v. Nicole Stern
Michigan Court of Appeals, 2024

Cite This Page — Counsel Stack

Bluebook (online)
767 N.W.2d 660, 282 Mich. App. 292, Counsel Stack Legal Research, https://law.counselstack.com/opinion/green-v-ziegelman-michctapp-2009.