Michelle Busuito v. Dte Energy Company

CourtMichigan Court of Appeals
DecidedAugust 21, 2025
Docket367095
StatusUnpublished

This text of Michelle Busuito v. Dte Energy Company (Michelle Busuito v. Dte Energy Company) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Michelle Busuito v. Dte Energy Company, (Mich. Ct. App. 2025).

Opinion

If this opinion indicates that it is “FOR PUBLICATION,” it is subject to revision until final publication in the Michigan Appeals Reports.

STATE OF MICHIGAN

COURT OF APPEALS

JEROME DUBRULLE, JENNIFER DUBRULLE, UNPUBLISHED EDWARD KERFOOT, ELLEN KERFOOT, August 21, 2025 NICOLE NORRIS, MATTHEW NORRIS, CHAD 10:54 AM HAURANI, MONA HAURANI, MARCY TAYLER, ABBY PAULSON, ANDREW HASTINGS, MARGUERITE KAISER, ROBERT KAISER, MOLLY MCCLANAGHAN, RYAN MORRIS, PATRICK SHANLEY, KELLY SHANLEY, RHONDA FENDERSON, SARAH FELDMAN, JOSHUA TUCKER, DANIELLE TUCKER, and all others similarly situated,

Plaintiffs-Appellants,

and

MICHELLE BUSUITO and MATTHEW HOWE,

Plaintiffs,

v No. 367095 Wayne Circuit Court DTE ENERGY COMPANY, MILLER PIPELINE- LC No. 21-009198-NZ MICHIGAN LLC, UTILITY RESOURCE GROUP LLC, and TMC ALLIANCE LLC,

Defendants-Appellees.

Before: PATEL, P.J., and RIORDAN and SWARTZLE, JJ.

PER CURIAM.

Plaintiffs sued defendants, alleging that defendants’ actions caused power outages in the Freud Pump Station, resulting in the flooding of plaintiffs’ properties. The trial court denied plaintiffs’ motion to amend their complaint to add DTE Electric Company as a defendant. Ultimately, the trial court granted defendants’ motions for summary disposition under MCR

-1- 2.116(C)(8) and denied plaintiffs’ motion to strike exhibits that DTE Energy Company and Utility Resource Group LLC (URG) filed with their motions. We reverse and remand for further proceedings.

I. BACKGROUND

According to plaintiffs’ third amended complaint (TAC), on June 22, 2021, defendant Miller Pipeline–Michigan LLC, acting as a contractor for DTE Energy or one of its subsidiaries, was engaged in excavation and damaged an underground cable. As a result, power could not be transmitted from the Ludden Substation to the Freud Pump Station, and five of the eight pumps at the pump station became inoperable. On June 25 and 26, 2021, a “rain event” occurred. Plaintiffs purportedly experienced property damage as a result of sewage backups and flooding. The parties dispute the comparative impact of the rain and disabled pumps on plaintiffs’ alleged damages, and the admissibility of information about the extent of the rain at this stage of the proceedings, but no parties dispute that there was a damaged cable or power outage, or that it rained on June 25 and 26, 2021.

Plaintiffs originally sued DTE Energy and “John Does 1-5.” DTE Energy first moved for summary disposition under MCR 2.116(C)(8) in December 2021, arguing that plaintiffs failed to plead how DTE Energy “fit[] into this picture” or owed plaintiffs a duty. The trial court denied DTE Energy’s motion, concluding that plaintiffs’ complaint sufficiently alleged the facts and elements of plaintiffs’ claims. The case was ultimately reassigned to a different trial court judge.

In June 2022, plaintiffs moved for leave to file the TAC. Plaintiffs sought to add Miller Pipeline, URG, TMC Alliance LLC (TMCA), and DTE Electric as defendants, and to remove reference to John Does 1-5. DTE Energy opposed the request, arguing that amending plaintiffs’ complaint would be futile. DTE Energy further argued that plaintiffs “improperly conflate[d] DTE Energy and DTE Electric,” that neither DTE Energy nor DTE Electric had a contractor relationship with Miller Pipeline or TMCA, and, even if a DTE entity had contracted with one of the subcontractors, any negligence could not imputed to DTE. Following a hearing, the trial court granted plaintiffs’ motion to add the proposed defendants, except for DTE Electric. The trial court stated during the hearing that adding DTE Electric would be futile.

The TAC alleged that defendants “were collectively responsible” for either damaging the cable or failing to take reasonable steps to repair the power instrumentalities servicing Freud Pump Station, and, as a result, Freud Pump Station was not fully operational during the “rain event,” and plaintiffs suffered property damage from the resulting sewage backups. Specifically, plaintiffs alleged that URG had been responsible for marking the power cables and had a duty to mark the infrastructure as URG had indicated that it had. Miller Pipeline, acting as a contractor for DTE Energy or one of its subsidiaries, had damaged the cable, failed to act with reasonable care, locate the cables, or engage in soft-excavation techniques.1 According to plaintiffs, DTE Energy and

1 Under the MISS DIG Underground Facility Damage Prevention and Safety Act, MCL 460.721 et seq., “soft excavation” is “a method and technique designed to prevent contact damage to underground facilities, including, but not limited to, hand-digging, cautious digging with

-2- Miller Pipeline had a duty to conduct a reasonable investigation to locate the underground power cables near the planned excavation project. Further, DTE Energy and TMCA had a duty to maintain and repair the power infrastructure that serviced the sewage-disposal system, but they had failed to do so. Plaintiff explained that a 2014 agreement, the Energy Delivery Services Agreement (EDSA), provided for a gradual system conversion of Detroit Public Lighting Department’s (DPLD) assets, services, and customers to DTE. Under the EDSA, the city of Detroit had contracted with TMCA to perform maintenance repairs on the DPLD system, but TMCA was required to submit proposed work to DTE for review and approval, and DTE made payments to TMCA. Plaintiffs alleged that DTE Energy failed to supervise its contractors, despite being “functionally responsible” for the operation and maintenance of the DPLD system, including the Ludden Substation and its instrumentalities.

Defendants each moved for summary disposition under MCR 2.116(C)(8), each describing the June 25 and 26, 2021 rain as severe, historic, or a “1,000-year storm.” Specifically, Miller Pipeline argued that it did not owe a legal duty to plaintiffs and that its actions were not a proximate cause of plaintiffs’ damages. In its motion, TMCA also argued that it was entitled to summary disposition because plaintiffs could not demonstrate that TMCA owed them a duty or that TMCA’s actions were the cause in fact or a proximate cause of plaintiff’s damages. Next, DTE Energy denied that it owed a duty to plaintiffs. In support of its motion, DTE Energy submitted various exhibits, including Great Lakes Water Authority (GLWA) “Talking Points”; slides from a presentation to GLWA by AECOM, an engineering consulting firm; an executive order of Governor Whitmer declaring a state of emergency as a result of the “heavy rainfall”; and a contract purportedly between Miller Pipeline and DTE Gas to demonstrate that DTE Energy had not contracted with Miller Pipeline. Finally, URG argued that it was entitled to summary disposition on the basis of a lack of proximate cause. URG attached exhibits that included the AECOM presentation and the executive order.

Plaintiffs opposed the motions, and they also moved the trial court to strike or exclude the AECOM presentation, GLWA Talking Points, and executive order on the basis that the trial court was not permitted to consider evidence outside the pleadings when deciding defendants’ motions made under MCR 2.116(C)(8). Further, the exhibits were “inadmissible, unreliable, and contain[ed] hearsay not subject to any exception.” The trial court denied plaintiffs’ motion.

After a hearing, the trial court granted defendants’ motions for summary disposition. In its opinion, the trial court referred to the June 25 and 26, 2021 rain as an “extraordinary 1000-year rainfall event.” The trial court stated that it would treat DTE Energy “as encompassing all of its subsidiaries,” which included DTE Electric and DTE Gas. Next, the trial court determined that any duty that DTE Energy owed to plaintiffs arose from the common law.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hill v. Sears, Roebuck and Co
492 Mich. 651 (Michigan Supreme Court, 2012)
Loweke v. Ann Arbor Ceiling & Partition Co, LLC
809 N.W.2d 553 (Michigan Supreme Court, 2011)
Gerling Konzern Allgemeine Versicherungs AG v. Lawson
693 N.W.2d 149 (Michigan Supreme Court, 2005)
Phillips v. Deihm
541 N.W.2d 566 (Michigan Court of Appeals, 1995)
McMillian v. Vliet
374 N.W.2d 679 (Michigan Supreme Court, 1985)
Prawdzik v. Heidema Brothers, Inc.
89 N.W.2d 523 (Michigan Supreme Court, 1958)
Freed v. Salas
780 N.W.2d 844 (Michigan Court of Appeals, 2009)
Howe v. Detroit Free Press, Inc
555 N.W.2d 738 (Michigan Court of Appeals, 1996)
Clark v. Dalman
150 N.W.2d 755 (Michigan Supreme Court, 1967)
Green v. Ziegelman
767 N.W.2d 660 (Michigan Court of Appeals, 2009)
Skinner v. Square D Co.
516 N.W.2d 475 (Michigan Supreme Court, 1994)
Weymers v. Khera
563 N.W.2d 647 (Michigan Supreme Court, 1997)
Dalley v. Dykema Gossett PLLC
788 N.W.2d 679 (Michigan Court of Appeals, 2010)
Leahy v. Orion Township
711 N.W.2d 438 (Michigan Court of Appeals, 2006)
DeShambo v. Anderson
684 N.W.2d 332 (Michigan Supreme Court, 2004)
Smith v. Stolberg
586 N.W.2d 103 (Michigan Court of Appeals, 1998)
Babula v. Robertson
536 N.W.2d 834 (Michigan Court of Appeals, 1995)
Bailey v. Schaaf
835 N.W.2d 413 (Michigan Supreme Court, 2013)
Roberts v. Salmi
866 N.W.2d 460 (Michigan Court of Appeals, 2014)
Dawe v. Dr Reuven Bar-Levav & Associates, PC
808 N.W.2d 240 (Michigan Court of Appeals, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
Michelle Busuito v. Dte Energy Company, Counsel Stack Legal Research, https://law.counselstack.com/opinion/michelle-busuito-v-dte-energy-company-michctapp-2025.