Granger Northern, Inc. v. Cianchette

572 A.2d 136
CourtSupreme Judicial Court of Maine
DecidedMarch 23, 1990
StatusPublished
Cited by19 cases

This text of 572 A.2d 136 (Granger Northern, Inc. v. Cianchette) is published on Counsel Stack Legal Research, covering Supreme Judicial Court of Maine primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Granger Northern, Inc. v. Cianchette, 572 A.2d 136 (Me. 1990).

Opinion

CLIFFORD, Justice.

The four defendants, Eric Cianchette, Kenneth Cianchette, A. Earl Brown and William Brown, appeal from a judgment of the Superior Court (Cumberland County, Fritzsche, J.) affirming an arbitrator’s award in favor of the plaintiff, Granger Northern, Inc. We reject the defendants’ contentions that the dispute was not arbi-trable and that the arbitrator exceeded his authority and affirm the judgment.

In 1985, Granger Northern, Inc. (“Gran-ger”) contracted with Armory Hotel Associates (“Associates”) 1 for the design and construction of a luxury hotel in Portland, to be called the Old Port Regency Hotel. The construction contract provided that Granger would complete the project for a guaranteed maximum price of $4,388,350. The contract could be varied during the course of construction through the use of change orders. Article 9 of the contract defined a change order as

a written order to the Contractor signed by the Owner or his authorized agent and issued after the execution of this Agreement, authorizing a Change in the Project and/or an adjustment in the Guaranteed Maximum Price....

The contract further required that Associates designate a representative with the authority to approve such orders and entitled the contractor to rely upon the decisions made by that representative. 2

*138 Eleven change orders amounting to $246,705 were prepared by Granger before the project was completed. All the change orders were evidenced by standard American Institute of Architects change order forms. Of the eleven, five were approved in writing by Robert Welch as “agent for” Iyanough Management, 3 while the remaining six were not signed. 4

Granger instituted an action against Associates and its seven partners to recover $1,008,614, of which $246,705 was for work performed pursuant to the eleven change orders. The Maine partners sought a stay of Granger’s demand for arbitration. The Superior Court refused to stay the arbitration. After seven days of hearings, the arbitrator found against Associates and ordered that Granger be paid $1,008,614, plus interest. The Superior Court denied the motion of the Maine partners to vacate the arbitrator’s award and granted Granger's motion for entry of judgment on the record. The Maine partners then brought this appeal.

Under the Uniform Arbitration Act, 14 M.R.S.A. §§ 5927-5949 (1980), the Superior Court reviews both the substantive determination of arbitrability and the power exercised in granting an award. Westbrook School Comm. v. Westbrook Teachers Ass’n, 404 A.2d 204, 206-07 (Me.1979) (construing 14 M.R.S.A. §§ 5928, 5938 (Supp.1978-79)). Our review is limited to errors of law made by the Superior Court. Id. at 206 n. 3.

On appeal, the Maine partners contest the validity of that portion of the arbitrator’s award entitling Granger to recover $246,705 for the work performed pursuant-to the change orders. They first contend that the arbitrator did not have proper jurisdiction to decide the dispute over the change orders and that the Superior Court erred in not granting their motion to stay the arbitration proceedings.

When parties enter an agreement providing that disputes will be submitted to arbitration, 5 a particular dispute is arbitrable “ ‘unless it may be said with positive assurance that the arbitration clause is not susceptible of an interpretation that covers the asserted dispute. Doubts should be resolved in favor of coverage.’ ” Westbrook School Comm., 404 A.2d at 208 (quoting United Steelworkers v. Warrior & Gulf Navigation Co., 363 U.S. 574, 582-83, 80 S.Ct. 1347, 1353, 4 L.Ed.2d 1409 (1960)). The question of substantive arbitrability, reserved to the trial court, depends upon the intent of the parties and may be determined by reference to principles of contract interpretation. Id. at 207; Hartford Fin. Sys., Inc. v. Florida Software Serv., Inc., 550 F.Supp. 1079, 1086-87 (D.Me.1982). The arbitration clause in article 9 of the contract between Granger and Associates provides that,

[a]ll claims, disputes and other matters in question arising out of, or relating to, this Agreement or the breach thereof, except with respect to the Architect/Engineer’s decision on matters relating to artistic effect, and except for claims which have been waived by the making or acceptance of Final Payment shall be decided by arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association then obtaining unless the parties mutually agree otherwise.

*139 Although they do not contest the validity of the arbitration clause, the Maine partners contend that it is not applicable to the change orders that they maintain constitute separate contracts. We disagree. An “all disputes” arbitration clause like the one at issue gives authority to the arbitrator to decide all “contract-generated or contract-related disputes between the parties however labelled_” Acevedo Maldonado v. PPG Indus., Inc., 514 F.2d 614, 616 (1st Cir.1975). Since disputes over change orders were not specifically excluded from the ambit of the arbitration clause, and the work completed by Granger pursuant to the change orders was performed on and directly related to the construction of the Old Port Regency Hotel, the subject of the contract, those disputes were arbitrable under the “all disputes” arbitration clause. Acevedo Maldonado, 514 F.2d at 616; Bel Pre Medical Ctr., Inc. v. Frederick Contractors, Inc., 21 Md.App. 307, 320 A.2d 558, 566 (1974), rev’d on other grounds, 274 Md. 307, 334 A.2d 526 (1975). The change orders are not so unrelated and separate from the construction contract that we can say “ ‘with positive assurance that the arbitration clause is not susceptible of an interpretation that covers the asserted dispute.’ ” Westbrook School Comm., 404 A.2d at 208 (quoting United Steelworkers, 363 U.S. at 582-83, 80 S.Ct. at 1353).

The Maine partners also contend that the arbitrator exceeded his authority in awarding Granger recovery for the change order work. Their contention is based on the fact that the change orders were not executed in accordance with the contract. 6

The standard for review of whether an arbitrator exceeds his authority is a narrow one. Bureau of the Maine State Police v. Pratt, 568 A.2d 501

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cianchette v. Cianchette
Maine Superior, 2019
Dallaire v. Murphy
Maine Superior, 2015
Regional School Unit No. 5 v. The Coastal Education Association
2015 ME 98 (Supreme Judicial Court of Maine, 2015)
James G. Stanley Jr. v. Michael A. Liberty
2015 ME 21 (Supreme Judicial Court of Maine, 2015)
CMCC Lot 14 v. CPI Augusta DOR
Maine Superior, 2012
JAY CASHMAN, INC. v. Portland Pipe Line Corp.
559 F. Supp. 2d 85 (D. Maine, 2008)
Runnells v. Quinn
2006 ME 7 (Supreme Judicial Court of Maine, 2006)
Barrett v. McDonald Investments, Inc.
2005 ME 43 (Supreme Judicial Court of Maine, 2005)
Widewaters Aroostook Centre Co. v. Noah's of Copley Place, Inc.
267 A.D.2d 995 (Appellate Division of the Supreme Court of New York, 1999)
Scinto v. Sosin, No. Cv 97057620 (May 23, 1997)
1997 Conn. Super. Ct. 4791 (Connecticut Superior Court, 1997)
Pelletier & Flanagan, Inc. v. Maine Court Facilities Authority
673 A.2d 213 (Supreme Judicial Court of Maine, 1996)
City of Lewiston v. Lewiston Firefighters Ass'n, IAG, Local No. 785
629 A.2d 50 (Supreme Judicial Court of Maine, 1993)
Orthopedic Physical Therapy Center, P.A. v. Sports Therapy Centers, Ltd.
621 A.2d 402 (Supreme Judicial Court of Maine, 1993)
Augusta Uniformed Firefighters Ass'n, Local 1650 v. City of Augusta
600 A.2d 403 (Supreme Judicial Court of Maine, 1991)
City of Westbrook v. Teamsters Local No. 48
578 A.2d 716 (Supreme Judicial Court of Maine, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
572 A.2d 136, Counsel Stack Legal Research, https://law.counselstack.com/opinion/granger-northern-inc-v-cianchette-me-1990.