Grand Blanc Cement Products, Inc. v. Insurance Co. of North America

571 N.W.2d 221, 225 Mich. App. 138
CourtMichigan Court of Appeals
DecidedAugust 19, 1997
DocketDocket No. 186152
StatusPublished
Cited by6 cases

This text of 571 N.W.2d 221 (Grand Blanc Cement Products, Inc. v. Insurance Co. of North America) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Grand Blanc Cement Products, Inc. v. Insurance Co. of North America, 571 N.W.2d 221, 225 Mich. App. 138 (Mich. Ct. App. 1997).

Opinion

Griffin, J.

Defendant Insurance Company of North America (ina) appeals as of right a circuit court’s order granting summary disposition in favor of plaintiff with respect to plaintiff’s claim for recovery under a payment bond issued by ina pursuant to the public works bond act, MCL 129.201 et seq.; MSA 5.2321(1) et seq. (bond act). Plaintiff cross appeals the measure of damages and the trial court’s order granting summary disposition in favor of defendant Artco Contracting, Inc. We affirm in part and reverse in part. We hold, inter alia, that subcontractors or materialmen that have failed to comply with MCL 129.207; MSA 5.2321(7) regarding a prior contract are not barred from protection under the bond act for labor and materials supplied pursuant to a second and indepen[141]*141dent contract for the same project if the general contractor is notified in accordance with the statute within thirty days of the claimant supplying labor or materials under the new contract.

i

Pursuant to the bond act, ina issued a payment bond to Artco, the general contractor on a construction project at Detroit Metropolitan Airport. On December 9, 1992, plaintiff began supplying masonry materials to defendant J. Moye Masonry, one of Artco’s subcontractors. Because of nonpayment, plaintiff terminated its contract and stopped supplying Moye on March 1, 1993. After negotiations and an agreement for payment of the past due amount, a new supply contract was entered into on March 30, 1993. In what plaintiff has characterized as a “three-way contract,”1 plaintiff agreed to supply materials in exchange for payment by Artco in the form of checks issued jointly to plaintiff and Moye. Artco made payment for materials supplied by plaintiff by joint checks dated June 14 and July 2, 1993.

Earlier, on April 8, 1993, plaintiff notified Artco, Moye, and ina’s local agent that it was relying on the payment bond as security for materials supplied under the second contract.2 In August 1993, plaintiff terminated the second contract for nonpayment. Plaintiff notified defendants of the payment lapse in a letter dated August 13, 1993.

[142]*142Plaintiff filed suit against ina under the payment bond. Plaintiff also sued Moye and Artco, alleging contract-related claims as well as claims against Artco of negligence, promissory estoppel, and quantum meruit. The trial court entered a default judgment against Moye. The trial court also granted plaintiffs motion for summary disposition pursuant to MCR 2.116(C)(10) with respect to plaintiffs claim against ina under the payment bond. The trial court ruled that plaintiff had satisfied MCL 129.207; MSA 5.2321(7) and perfected its claim under the bond act by notifying defendants within thirty days of when it began supplying materials under the second contract. The trial court also granted summary disposition in favor of Artco pursuant to MCR 2.116(C)(10) on the basis that plaintiff’s judgment against ina fully satisfied plaintiff’s claims against Artco.

n

On appeal, defendant INA contends that the trial court erred in granting summary disposition for plaintiff with respect to its payment bond claim. We disagree. We review the trial court’s ruling on a motion for summary disposition pursuant to MCR 2.116(C)(10) de novo to determine whether the pleadings or the uncontroverted documentary evidence establish that defendant is entitled to judgment as a matter of law. MCR 2.116(I)(1); Kennedy v Auto Club of Michigan, 215 Mich App 264, 266; 544 NW2d 750 (1996); Porter v Royal Oak, 214 Mich App 478, 484; 542 NW2d 905 (1995). The existence of either circumstance merits summary disposition. Kennedy, supra at 266; Porter, supra at 484.

[143]*143A

The issue on appeal is whether a claimant that had failed to satisfy MCL 129.207; MSA 5.2321(7) regarding an earlier contract to provide materials for a public construction project is afforded bond act protection for materials supplied pursuant to a second and independent contract regarding the same project when proper notification to the general contractor is given within thirty days of supplying materials under the new contract. In addressing this question of first impression, we are mindful that “ ‘[t]he fundamental purpose of any rule of statutory construction, of course, is to assist the court in discovering and giving effect to the intent of the Legislature.’ ” Terzano v Wayne Co, 216 Mich App 522, 526-527; 549 NW2d 606 (1996), quoting In re Certified Question, 433 Mich 710, 722; 449 NW2d 660 (1989). Once discovered, the Legislature’s intent must prevail over any existing rule of construction to the contrary. Ansell v Dep’t of Commerce (On Remand), 222 Mich App 347, 355; 564 NW2d 519 (1997); Terzano, supra at 527. Where reasonable minds may differ about the meaning of a statute, we look to the objective of the statute and the harm it is designed to remedy and apply a reasonable construction that best accomplishes the Legislature’s purpose. Ansell, supra at 355; Terzano, supra at 527; People v Ward, 211 Mich App 489, 492; 536 NW2d 270 (1995). “[Lateral constructions that produce unreasonable and unjust results that are inconsistent with the purpose of the act should be avoided.” Rowell v Security Steel Processing Co, 445 Mich 347, 354; 518 NW2d 409 (1994); Salas v Clements, 399 Mich 103, 109; 247 NW2d 889 (1976).

[144]*144B

The bond act requires principal contractors to provide performance bonds assuring payment to subcontractors and materialmen furnishing supplies, labor, or equipment for public construction projects. W T Andrew Co, Inc v Mid-State Surety Corp, 450 Mich 655, 658; 545 NW2d 351 (1996); Thomas Industries, Inc v C & L Electric, Inc, 216 Mich App 603, 606; 550 NW2d 558 (1996). To qualify for this statutory protection, MCL 129.207; MSA 5.2321(7) provides:

A claimant not having a direct contractual relationship with the principal contractor shall not have a right of action upon the payment bond unless (a) he has within 30 days after furnishing the first of such material. . . served on the principal contractor a written notice, which shall inform the principal of the nature of the material being furnished or to be furnished, . . . and identifying the party contracting for such . . . materials and the site for the . . . delivery of such materials ....

Although this notice requirement is strictly enforced, Tempco Heating & Cooling, Inc v A Rea Constr, Inc, 178 Mich App 181, 190; 443 NW2d 486 (1989); Charles W Anderson Co v Argonaut Ins Co, 62 Mich App 650, 651-654; 233 NW2d 691 (1975), the remedial bond act is “liberally construed” to “protect contractors and materialmen in the public sector.” W T Andrew Co, supra at 659; see also Adamo Equipment Rental Co v Mack Development Co, Inc, 122 Mich App 233, 236; 333 NW2d 40 (1982).

In drafting MCL 129.207; MSA 5.2321(7), the Legislature did not specify whether the thirty-day period is particular to each individual contract or whether it commences once and for all when the claimant begins performing its first contract to work for the [145]*145public project.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Doug Dysert Poured Walls LLC v. Del Charbonier
Michigan Court of Appeals, 2023
Michigan Pipe & Valve-Lansing, Inc. v. Hebeler Enterprises, Inc.
808 N.W.2d 323 (Michigan Court of Appeals, 2011)
Assemblers, Inc. v. American Manufacturers Mutual Insurance
761 N.W.2d 399 (Michigan Court of Appeals, 2008)
Hanley v. Mazda Motor Corp.
609 N.W.2d 203 (Michigan Court of Appeals, 2000)
People v. Fetterley
583 N.W.2d 199 (Michigan Court of Appeals, 1998)
Grand Blanc Cement v. INA
571 N.W.2d 221 (Michigan Court of Appeals, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
571 N.W.2d 221, 225 Mich. App. 138, Counsel Stack Legal Research, https://law.counselstack.com/opinion/grand-blanc-cement-products-inc-v-insurance-co-of-north-america-michctapp-1997.