Grand Blanc Cement v. INA

571 N.W.2d 221, 225 Mich. App. 132
CourtMichigan Court of Appeals
DecidedNovember 6, 1997
Docket186152
StatusPublished

This text of 571 N.W.2d 221 (Grand Blanc Cement v. INA) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Grand Blanc Cement v. INA, 571 N.W.2d 221, 225 Mich. App. 132 (Mich. Ct. App. 1997).

Opinion

571 N.W.2d 221 (1997)
225 Mich. App. 132

GRAND BLANC CEMENT PRODUCTS, INC., Plaintiff-Appellee/Cross-Appellant,
v.
INSURANCE COMPANY OF NORTH AMERICA, Defendant-Appellant/Cross-Appellee, and
Artco Contracting, Inc., Defendant-Cross-Appellee, and
J. Moye Masonry, Inc., Defendant.

Docket No. 186152.

Court of Appeals of Michigan.

Submitted June 3, 1997, at Detroit.
Decided August 19, 1997, at 9:15 a.m.
Released for Publication November 6, 1997.

*223 Winegarden, Shedd, Haley, Lindholm & Robertson, P.L.C. by Alan F. Himelhoch, Flint, for Plaintiff-Appellee/Cross-Appellant.

Harvey, Kruse, Westen & Milan, P.C. by John F. Milan and Maurice A. Borden, Troy, for Insurance Company of North America and Artco, Contracting, Inc.

Before TAYLOR, P.J., and RICHARD ALLEN GRIFFIN and SAAD, JJ.

*222 RICHARD ALLEN GRIFFIN, Judge.

Defendant Insurance Company of North America (INA) appeals as of right a circuit court's order granting summary disposition in favor of plaintiff with respect to plaintiff's claim for recovery under a payment bond issued by INA pursuant to the public works bond act, M.C.L. § 129.201 et seq.; M.S.A. § 5.2321(1) et seq. (bond act). Plaintiff cross appeals the measure of damages and the trial court's order granting summary disposition in favor of defendant Artco Contracting, Inc. We affirm in part and reverse in part. We hold, inter alia, that subcontractors or materialmen that have failed to comply with M.C.L. § 129.207; M.S.A. § 5.2321(7) regarding a prior contract are not barred from protection under the bond act for labor and materials supplied pursuant to a second and independent contract for the same project if the general contractor is notified in accordance with the statute within thirty days of the claimant supplying labor or materials under the new contract.

I

Pursuant to the bond act, INA issued a payment bond to Artco, the general contractor on a construction project at Detroit Metropolitan Airport. On December 9, 1992, plaintiff began supplying masonry materials to defendant J. Moye Masonry, one of Artco's subcontractors. Because of nonpayment, plaintiff terminated its contract and stopped supplying Moye on March 1, 1993. After negotiations and an agreement for payment of the past due amount, a new supply contract was entered into on March 30, 1993. In what plaintiff has characterized as a "three-way contract,"[1] plaintiff agreed to supply materials in exchange for payment by *224 Artco in the form of checks issued jointly to plaintiff and Moye. Artco made payment for materials supplied by plaintiff by joint checks dated June 14 and July 2, 1993.

Earlier, on April 8, 1993, plaintiff notified Artco, Moye, and INA's local agent that it was relying on the payment bond as security for materials supplied under the second contract.[2] In August 1993, plaintiff terminated the second contract for nonpayment. Plaintiff notified defendants of the payment lapse in a letter dated August 13, 1993.

Plaintiff filed suit against INA under the payment bond. Plaintiff also sued Moye and Artco alleging contract-related claims as well as claims against Artco of negligence, promissory estoppel, and quantum meruit. The trial court entered a default judgment against Moye. The trial court also granted plaintiff's motion for summary disposition pursuant to MCR 2.116(C)(10) with respect to plaintiff's claim against INA under the payment bond. The trial court ruled that plaintiff had satisfied M.C.L. § 129.207; M.S.A. § 5.2321(7) and perfected its claim under the bond act by notifying defendants within thirty days of when it began supplying materials under the second contract. The trial court also granted summary disposition in favor of Artco pursuant to MCR 2.116(C)(10) on the basis that plaintiff's judgment against INA fully satisfied plaintiff's claims against Artco.

II

On appeal, defendant INA contends that the trial court erred in granting summary disposition for plaintiff with respect to its payment bond claim. We disagree. We review the trial court's ruling on a motion for summary disposition pursuant to MCR 2.116(C)(10) de novo to determine whether the pleadings or the uncontroverted documentary evidence establish that defendant is entitled to judgment as a matter of law. MCR 2.116(I)(1); Kennedy v. Auto Club of Michigan, 215 Mich.App. 264, 266, 544 N.W.2d 750 (1996); Porter v. Royal Oak, 214 Mich.App. 478, 484, 542 N.W.2d 905 (1995). The existence of either circumstance merits summary disposition. Kennedy, supra at 266, 544 N.W.2d 750; Porter, supra at 484, 542 N.W.2d 905.

A

The issue on appeal is whether a claimant that had failed to satisfy M.C.L. § 129.207; M.S.A. § 5.2321(7) regarding an earlier contract to provide materials for a public construction project is afforded bond act protection for materials supplied pursuant to a second and independent contract regarding the same project when proper notification to the general contractor is given within thirty days of supplying materials under the new contract. In addressing this question of first impression, we are mindful that "`[t]he fundamental purpose of any rule of statutory construction, of course, is to assist the court in discovering and giving effect to the intent of the Legislature.'" Terzano v. Wayne Co., 216 Mich.App. 522, 526-527, 549 N.W.2d 606 (1996), quoting In re Certified Question, 433 Mich. 710, 722, 449 N.W.2d 660 (1989). Once discovered, the Legislature's intent must prevail over any existing rule of construction to the contrary. Ansell v. Dep't of Commerce (On Remand), 222 Mich.App. 347, 355, 564 N.W.2d 519 (1997); Terzano, supra at 527, 549 N.W.2d 606. Where reasonable minds may differ about the meaning of a statute, we look to the objective of the statute and the harm it is designed to remedy and apply a reasonable construction that best accomplishes the Legislature's purpose. Ansell, supra at 355, 564 N.W.2d 519; Terzano, supra at 527, 549 N.W.2d 606; People v. Ward, 211 Mich.App. 489, 492, 536 N.W.2d 270 (1995). "[L]iteral constructions that produce unreasonable and unjust results that are inconsistent with the purpose of the act should be avoided." Rowell v. Security Steel Processing Co., 445 Mich. 347, 354, 518 N.W.2d 409 (1994); Salas v. Clements, 399 Mich. 103, 109, 247 N.W.2d 889 (1976).

B

The bond act requires principal contractors to provide performance bonds assuring payment to subcontractors and materialmen *225 furnishing supplies, labor, or equipment for public construction projects. W T Andrew Co., Inc. v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Porter v. City of Royal Oak
542 N.W.2d 905 (Michigan Court of Appeals, 1995)
In Re MacDonald Estate
67 N.W.2d 227 (Michigan Supreme Court, 1954)
Milbrand Co. v. Department of Social Services
324 N.W.2d 41 (Michigan Court of Appeals, 1982)
Silver v. International Paper Co.
192 N.W.2d 535 (Michigan Court of Appeals, 1971)
Ackron Contracting Co. v. Oakland County
310 N.W.2d 874 (Michigan Court of Appeals, 1981)
Ansell v. Department of Commerce (On Remand)
564 N.W.2d 519 (Michigan Court of Appeals, 1997)
WT ANDREW COMPANY v. Mid-State Surety Corp.
545 N.W.2d 351 (Michigan Supreme Court, 1996)
Napier v. Jacobs
414 N.W.2d 862 (Michigan Supreme Court, 1987)
Thomas Industries, Inc v. C & L Electric, Inc
550 N.W.2d 558 (Michigan Court of Appeals, 1996)
Kaminski v. Newton
438 N.W.2d 915 (Michigan Court of Appeals, 1989)
Price Bros. Co. v. Olin Const. Co., Inc.
528 F. Supp. 716 (W.D. New York, 1981)
Erb Lumber Co. v. Homeowner Construction Lien Recovery Fund
522 N.W.2d 917 (Michigan Court of Appeals, 1994)
Adamo Equipment Rental Co. v. MacK Development Co.
333 N.W.2d 40 (Michigan Court of Appeals, 1982)
In Re Certified Question
449 N.W.2d 660 (Michigan Supreme Court, 1989)
Kennedy v. Auto Club
544 N.W.2d 750 (Michigan Court of Appeals, 1996)
Swickard v. Wayne County Medical Examiner
475 N.W.2d 304 (Michigan Supreme Court, 1991)
Terzano v. Wayne County
549 N.W.2d 606 (Michigan Court of Appeals, 1996)
Price Bros. v. Charles J. Rogers Construction Co.
304 N.W.2d 584 (Michigan Court of Appeals, 1981)
Pi-Con, Inc. v. a J Anderson Construction Co.
458 N.W.2d 639 (Michigan Supreme Court, 1990)
Tempco Heating & Cooling, Inc v. a Rea Construction, Inc
443 N.W.2d 486 (Michigan Court of Appeals, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
571 N.W.2d 221, 225 Mich. App. 132, Counsel Stack Legal Research, https://law.counselstack.com/opinion/grand-blanc-cement-v-ina-michctapp-1997.