Ackron Contracting Co. v. Oakland County

310 N.W.2d 874, 108 Mich. App. 767
CourtMichigan Court of Appeals
DecidedAugust 19, 1981
DocketDocket 50058
StatusPublished
Cited by11 cases

This text of 310 N.W.2d 874 (Ackron Contracting Co. v. Oakland County) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ackron Contracting Co. v. Oakland County, 310 N.W.2d 874, 108 Mich. App. 767 (Mich. Ct. App. 1981).

Opinion

Per Curiam.

On April 18, 1972, Oakland County entered into two contracts with Ackron Contracting Company for the construction of portions of the Clinton-Oakland Sewage Disposal System. The contracts called for installation of sewer mains as well as for the restoration of areas disturbed as a result of construction. The drawings and specifications for the contracts were set out in two separate booklets specifically incorporated into the contract. At the same time, Argonaut Insurance Company, appellant herein, executed performance bonds as surety for Ackron’s performance of the contracts.

Ackron commenced construction under the terms of the contract and substantially completed all underground structures, the sewers and their appurtenances before ceasing operations in June of 1974. At the time of abandonment, Oakland County had disbursed monthly progress payments in the amount of $1,265,714.29 for contract T-3 and $698,005.26 for contract T-6. The final contract prices which would have been due to Ackron, had it completed the work, were stated by Oakland County to be $1,348,255.49 for contract T-3 and $750,133.77 for contract T-6. 1 _

*770 On February 26, 1976, Ackron filed a complaint against Oakland County, alleging that the county failed to pay certain amounts due Ackron for sodding in connection with the contracts, for additional work by Ackron that was not within the scope of the contracts, and for the balance due under the contracts. Oakland County’s answer alleged that Ackron had failed to perform its obligations under the contracts and counterclaimed for an amount in excess of $300,000 to cover expenses incurred in completing the project. On July 19, 1976, Oakland County successfully moved to add Argonaut as a counter-defendant.

On September 14, 1977, Oakland County filed a motion to dismiss Ackron’s complaint and for entry of a default judgment against Argonaut. On September 28, 1977, an order was entered, granting the county’s motion for a default judgment against Argonaut for failure to comply with discovery orders. The entry of default was affirmed by this Court in Ackron Contracting Co, Inc v Oakland County, 87 Mich App 294; 274 NW2d 44 (1978), lv den 406 Mich 915 (1979).

Pursuant to GCR 1963, 520.2(2), 2 evidentiary hearings were held on May 23, July 26, and July 27, 1979, to determine the amount of damages recoverable against Argonaut for costs incurred in completing the project. Oakland County’s project *771 engineer was the only witness called. He testified concerning the scope of the contracts and the procedures for payment of individual contractors during completion. He stated that, although Ackron had substantially completed the construction of the sewer system, it had failed to complete surface restoration and had failed to make necessary repairs on the sewer system. As a result, the county was forced to hire other contractors to complete the project.

In an attempt to establish the cost of completion, detailed accounts and summaries of amounts paid to individual contractors were presented in evidence. Oakland County contended that it was entitled to recover $516,890.01 for amounts expended in completing the project, less $123,754.25, which it had retained.

Argonaut’s trial counsel attempted to cross-examine the county’s project engineer regarding certain amounts paid to the contractors to complete the project. It was Argonaut’s theory that some of Oakland County’s expenditures were either uncalled for by the contracts or were items which Ackron had not been directed to complete before it abandoned the project. Following a discussion held oif the record, cross-examination was not permitted. 3

*772 On April 2, 1980, the trial judge entered an order awarding the county damages in the amount of $313,705.44. The principal action between Ackron and Oakland County has not as yet been heard. Argonaut brings this appeal as a matter of right, challenging the April 2, 1980, order.

Argonaut’s first contention on appeal is that the court’s restrictions on the scope of the damage hearing were inconsistent with the requirements of GCR 1963, 520.2(2) and Michigan case law and that the court’s decision to preclude Argonaut from challenging Oakland County’s claim for damages on the ground that certain costs were not within the terms of the contract constituted error requiring reversal.

The procedural history of this case compels us to decide this matter on a ground not raised by the parties. Argonaut, the defaulted party, is surety for Ackron Construction Company, and the extent of its liability is, therefore, coextensive with that of Ackron. 23 Mich Civil Jurisprudence, Surety-ship, § 35, p 84. Generally, a surety may plead any defense available to its principal and if no action can be maintained by the obligee against the principal, none can be maintained against the surety. 23 Mich Civil Jurisprudence, Suretyship, § 47, p 100. Since the primary action between Ackron and Oakland County has not yet been tried, it is unclear what Ackron’s ultimate liability will be._

*773 Oakland County’s counterclaim against counter-defendants Ackron and appellant Argonaut seeks recovery for damages caused by Ackron’s alleged breach of contract. When the case between Oakland County and Ackron is ultimately resolved, however, it may be determined that Ackron did not breach the contracts and that Ackron has a right of recovery against Oakland County, as Ackron asserts in its complaint. In such a case, Argonaut, as Ackron’s surety, should not be liable to Oakland County in any amount.

As the matter currently stands, Argonaut, as the defaulted party, stands in the anomalous position of having to admit its principal’s liability for breach of the contracts and to compensate Oakland County for the costs which the county incurred in completing them before that issue has been ultimately determined in the principal action between Oakland County and Ackron.

The present issue before this Court, as we see it, was stated in 6 Moore’s Federal Practice (2d ed),. § 55.06, p 55-81:

"Where there are several defendants a question may arise as to whether, after entry of a default against one, a default judgment can be entered immediately against the defaulting defendant or whether entry must be postponed until all the defendants are in default or the case is tried as to the defendants not in default.”

The authors of that treatise, citing the leading case of Frow v De La Vega, 82 US (15 Wall) 552, 554; 21 L Ed 60 (1872), state that the "latter alternative is the correct procedure where the liability of the defendants is joint”. Moore’s, supra, p 55-81.

The problem with the posture of the present *774 case was stated by Justice Bradley in Frow, supra, 554:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
310 N.W.2d 874, 108 Mich. App. 767, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ackron-contracting-co-v-oakland-county-michctapp-1981.