Assemblers, Inc. v. American Manufacturers Mutual Insurance

761 N.W.2d 399, 281 Mich. App. 599
CourtMichigan Court of Appeals
DecidedDecember 9, 2008
DocketDocket 281728
StatusPublished

This text of 761 N.W.2d 399 (Assemblers, Inc. v. American Manufacturers Mutual Insurance) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Assemblers, Inc. v. American Manufacturers Mutual Insurance, 761 N.W.2d 399, 281 Mich. App. 599 (Mich. Ct. App. 2008).

Opinion

*601 Davis, J.

Plaintiff appeals as of right orders of summary disposition entered in favor of defendants American Manufacturers Mutual Insurance Company (American Manufacturers) and United States Fidelity & Guaranty Company (USF&G). We affirm in part, reverse in part, and remand for further proceedings consistent with this opinion.

This case arises out of the Howe Elementary School demolition and reconstruction project begun by the Detroit Public Schools in 2001. The Detroit Public Schools contracted with American International, Inc., to be the general contractor for the project. American International obtained a payment bond from USF&G, and it subcontracted part of the construction project to defendant Metro Steel Fabricators, Inc. (Metro Steel). Metro Steel obtained its own payment bond from American Manufacturers. Metro Steel then subcontracted part of the construction work to plaintiff.

On May 8, 2003, plaintiff “stopped working on the Howe Elementary School project” without completing it. Plaintiff contends that its work on the project was nearly complete at that time, but that it was not receiving its expected payments and it perceived that it would continue not receiving its payments. Plaintiff therefore ceased work “to avoid further losses.” It is undisputed that plaintiff was not, in fact, paid all that it was owed on the Howe Elementary School project. On March 25, 2004, the Detroit Public Schools formally terminated the construction contract with American International for failure “to properly make payments to Subcontractors or for labor, materials and equipment” pursuant to that contract. 1 On May 6, 2004, Metro Steel explicitly acknowledged in a letter to plaintiff that *602 $124,666 remained owing on the Howe Elementary School project. Plaintiff seeks the same amount in the instant action. Nevertheless, the Detroit Public Schools thereafter persuaded plaintiff to complete its work on the project, giving plaintiff “assurances of payment.” On August 19, 2004, plaintiff returned to the work site and completed its work on the Howe Elementary School project.

On August 27, 2004, plaintiff sent notices to both sureties that it was making a claim on each of the payment bonds. Plaintiff then commenced the instant action against them. All parties filed motions for summary disposition. USF&G argued that the last day plaintiff worked as a subcontractor to a subcontractor on the original contract was May 8, 2003, and that it failed to provide notice of its claim within 90 days thereof, as required by the contractor’s bond for public buildings or works act, MCL 129.201 et seq. 2 USF&G also argued that it could not be held liable on the bond because it was a secondary surety to American Manufacturers’s bond and because plaintiff was responsible for delays in the project. American Manufacturers argued that its bond contained a contractual limitations period that required claimants to file suit within one year of giving notice under the bond or of the last day on which work was performed and that plaintiff exceeded this date by more than three months under any possible interpretation of the facts. Plaintiff argued that the work it performed on August 19, 2004, was merely a completion of its work on its subcontract with a subcontractor and that American Manufacturers’s bond was a statutory bond and it was required to afford the *603 longer limitations period available under the public works bond statute. The trial court granted summary disposition in favor of the sureties; the parties later agreed to a consent judgment and final order resolving the remaining claims. 3

A grant or denial of summary disposition is reviewed de novo on the basis of the entire record to determine if the moving party is entitled to judgment as a matter of law. Maiden v Rozwood, 461 Mich 109, 118; 597 NW2d 817 (1999). When reviewing a motion under MCR 2.116(0(10), which tests the factual sufficiency of the complaint, this Court considers all evidence submitted by the parties in the light most favorable to the non-moving party. Where the evidence fails to establish a genuine issue regarding any material fact, the moving party is entitled to judgment as a matter of law. Maiden, supra at 120. A motion brought under MCR 2.116(C)(8) should be granted only where the complaint is so legally deficient that recovery would be impossible even if all well-pleaded facts were true and construed in the light most favorable to the nonmoving party. Maiden, supra at 119. This Court also reviews de novo as a question of law the proper interpretation of both contracts and statutes. Detroit Fire Fighters Ass’n, IAFF Local 344 v Detroit, 482 Mich 18, 28; 753 NW2d 579 (2008).

MCL 129.201 et seq. was created by the Legislature in order to protect “principal contractors” from the void left by the “long-standing mechanics’ lien law” that prohibited mechanics’ liens on public buildings. Adamo Equip Rental Co v Mack Dev Co, Inc, 122 Mich App 233, 236; 333 NW2d 40 (1982). Although intended “to safeguard and protect contractors and materialmen in the public sector,” it significantly distinguishes between “rights and duties of the primary contractor and the *604 rights and duties of the secondary contractors ....” Id. at 236-237. This Court has explained that “the principal contractor” means “the contractor who has the primary responsibility for performing the terms of the contract” and might or might not be the first contractor. Id. at 237. The plain language of MCL 129.201 imposes the requirement of providing a bond under the statute only on the principal contractor.

It is undisputed that Metro Steel was not the principal contractor, so Metro Steel was not required by statute to provide a bond pursuant to MCL 129.201 et seq. Plaintiff contends, however, that the bond issued by American Manufacturers is a statutory bond because it incorporates by reference Metro Steel’s subcontract with American International, which in turn allegedly required Metro Steel to obtain a statutory bond because the subcontract between Metro Steel and American International incorporated by reference the prime contract between American International and the Detroit Public Schools that required American International to provide a statutory bond. 4 The prime contract appears to require the general contractor to obtain a payment bond using a form explicitly specifying that the bond is statutory and in conformance with the public works bond act. However, Metro Steel is not the general contractor, the reference to “bidders” appears to be in the context of dealings directly with the project owner, and the American Manufacturers bond did not include that particular language.

*605 Indeed, there is no

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Detroit Fire Fighters Ass'n v. City of Detroit
753 N.W.2d 579 (Michigan Supreme Court, 2008)
Gloucester City v. AM. ARBITRATION ASS'N.
755 A.2d 1256 (New Jersey Superior Court App Division, 2000)
WT ANDREW COMPANY v. Mid-State Surety Corp.
545 N.W.2d 351 (Michigan Supreme Court, 1996)
Maiden v. Rozwood
597 N.W.2d 817 (Michigan Supreme Court, 1999)
DETROIT FIRE FIGHTERS ASS'N IAFF LOCAL 344 v. City of Detroit
753 N.W.2d 579 (Michigan Supreme Court, 2008)
Adamo Equipment Rental Co. v. MacK Development Co.
333 N.W.2d 40 (Michigan Court of Appeals, 1982)
Kammer Asphalt Paving Co. v. East China Township Schools
504 N.W.2d 635 (Michigan Supreme Court, 1993)
Kirkpatrick v. Phillips
127 N.W. 340 (Michigan Supreme Court, 1910)
Grand Blanc Cement Products, Inc. v. Insurance Co. of North America
571 N.W.2d 221 (Michigan Court of Appeals, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
761 N.W.2d 399, 281 Mich. App. 599, Counsel Stack Legal Research, https://law.counselstack.com/opinion/assemblers-inc-v-american-manufacturers-mutual-insurance-michctapp-2008.