Gateway Foam Insulators, Inc. v. Jokerst Paving & Contracting, Inc.

279 S.W.3d 179, 2009 Mo. LEXIS 38, 2009 WL 837698
CourtSupreme Court of Missouri
DecidedMarch 31, 2009
DocketSC 89576
StatusPublished
Cited by28 cases

This text of 279 S.W.3d 179 (Gateway Foam Insulators, Inc. v. Jokerst Paving & Contracting, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gateway Foam Insulators, Inc. v. Jokerst Paving & Contracting, Inc., 279 S.W.3d 179, 2009 Mo. LEXIS 38, 2009 WL 837698 (Mo. 2009).

Opinions

MARY R. RUSSELL, Judge.

The question before this Court is whether a claimant whose specially-fitted commercial vehicle was rendered useless may recover both the replacement costs for the vehicle and the lost profits suffered from loss of use of the vehicle. The trial court correctly found that the claimant in this case was entitled to both replacement costs and lost-profits damages. The trial court incorrectly awarded the claimant damages for loan interest paid. The judgment is affirmed in part and reversed in part.1

I. Background

This case arose after an employee of Jokerst Paving & Contracting, Inc. (Defendant) caused a traffic accident between Defendant’s vehicle and a specialized foam insulation installation truck, known as a “foam rig,” owned by Gateway Foam Insulators, Inc. (Plaintiff).

At the time of the accident, Plaintiff owned two foam rigs, which it used together on job sites to expedite completion of its work. The foam rigs included a generator, installation equipment, foam insulation chemicals, and other tools and equipment [183]*183that might be needed at insulation installation jobsites. The accident destroyed the newer of Plaintiffs foam rigs, along with most of its tools and equipment on that rig. Plaintiff also was billed for the environmental cleanup of the hazardous chemicals that spilled from its rig at the time of the accident.2

Plaintiff investigated purchasing a replacement for the damaged foam rig, but it was unable to afford payments on a new vehicle.3 Instead, Plaintiff borrowed money to purchase a used truck and to buy the necessary equipment to make that used truck into a foam rig. Plaintiffs owner testified that he could have worked full-time for two and a half weeks to make the replacement foam rig operational, but he stated that he did not have the money available to put the rig together in two and a half weeks.

Plaintiff sued Defendant seeking money damages for replacement of the foam rig, lost profits for loss of use, and payment for other costs associated with destruction of the foam rig. It argued that its position in the foam insulation installation market was negatively impacted after the accident with Defendant’s vehicle.4 It maintained the loss of the rig affected its ability to complete jobs timely, thereby diminishing its client base and allowing competitors to enter the market.

Plaintiffs owners and accountant testified at trial about lost profits suffered because of loss of use of the foam rig. The accountant testified that she had reviewed Plaintiffs business records and its construction market to determine estimated lost profits at a minimum of $120,000. She testified that $130,000 to $135,000 would be the maximum lost profits due to the loss of Plaintiffs foam rig.

Defendant complained at trial that Plaintiffs exhibits relating to lost profits were based on speculation. It suggested that Plaintiff could have avoided lost profits by more quickly replacing its foam rig, and it argued that Plaintiff overstated the value of its damaged rig and equipment. While Plaintiffs accountant agreed that a new truck would have prevented its lost profits, she also testified that Plaintiff lacked the financial resources to purchase a new truck at the time of the collision. The accountant explained that, at the time of the collision, Plaintiffs owners already were mortgaging rental property to keep the business running.

Defendant, however, presented contrary evidence about Plaintiffs lost profits. Its retained accountant testified that he had reviewed Plaintiffs tax returns to estimate daily revenues and calculated lost profits of approximately $450 per day until the rig was operational. He highlighted that lost profits could not be calculated “to a reasonable degree of certainty” because there were too many variables to consider. He indicated that “it would be hard to arrive at something that is real specific and two [184]*184people would agree that that is the exact number.”

After hearing evidence from both parties, the trial court awarded Plaintiff lost profits based on its accountant’s estimation of $120,000. The trial court found that Plaintiffs accountant “was credible” and that her estimations were “reasonable under the circumstances” as she was “intimately familiar with Plaintiffs business ... and factors affecting the loss of business and profits as a direct result of’ loss of the foam rig.

In addition to the lost profits, Plaintiff also was awarded $68,500 for replacement damages for its destroyed foam rig and equipment and tools.5 In addition, Defendant was ordered to pay $11,723.83 for the interest on the loan Plaintiff was required to take out to replace the damaged rig and $12,746.72 for the cost of environmental cleanup associated with the collision. Defendant appeals.

II. Standard of Review

A judgment in a court-tried case will be affirmed if there is substantial evidence to support it, it is not against the weight of the evidence, and it does not erroneously declare or apply the law. Murphy v. Carrón, 536 S.W.2d 30, 32 (Mo. banc 1976). Because the trial court, rather than this Court, weighs the evidence, this Court’s review of the damages awarded is limited to a determination of whether the verdict reflects the substantial evidence presented. See Collier v. City of Oak Grove, 246 S.W.3d 923, 925 (Mo. banc 2008). “The evidence will be considered in the light most favorable to respondent, giving him the benefit of all reasonable inferences and disregarding appellant’s evidence except as it may support the verdict.” Emerick v. Mutual Benefit Life Ins. Co., 756 S.W.2d 513, 523 (Mo. banc 1988).

III. Arguments

A. Plaintiff was rightly awarded lost-profits damages

1. Lost profits were available to Plaintiff

“The goal of awarding damages is to compensate a party for a legally recognized loss ... [and a] party should be fully compensated for its loss, but not recover a windfall.” Ameristar Jet Charter, Inc. v. Dodson Int’l Parts, Inc., 155 5.W.3d 50, 54 (Mo. banc 2005). Where a property owner is the victim of a tort that destroys his property, the law seeks to restore him for his “full actual loss” by awarding him the “monetary equivalent” of the destroyed property so as to place him in “as good a position as he would have enjoyed in the absence of the destruction.” Stark Bro’s Nurseries & Orchards Co. v. Wayne Daniel Truck, Inc., 718 S.W.2d 204, 205-06 (Mo.App.1986). Typically, where destroyed property can be replaced, “the owner of the property is fully compensated upon receipt of the expenses of replacement.” Id. at 206. But an owner is not fully compensated if he suffers lost profits where the replacement of his destroyed property is delayed. See id. In such cases, as in Plaintiffs case, lost profits may be necessary to accomplish fully compensating the claimant for his loss.6

[185]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Chemline Incorporated v. Timothy Mauzy
Missouri Court of Appeals, 2021
Wieland v. Owner-Operator Servs., Inc.
540 S.W.3d 845 (Supreme Court of Missouri, 2018)
J & D Towing, LLC v. American Alternative Insurance Corp.
478 S.W.3d 649 (Texas Supreme Court, 2016)
O'Gorman & Sandroni, P.C. v. Steve Dodson d/b/a Clayton Computer
478 S.W.3d 539 (Missouri Court of Appeals, 2015)
American Eagle Waste Industries, LLC v. St. Louis County
463 S.W.3d 11 (Missouri Court of Appeals, 2015)
Harland Hawley v. Edward D. Tseona
453 S.W.3d 837 (Missouri Court of Appeals, 2014)
Patrick Blanks v. Fluor Corporation
450 S.W.3d 308 (Missouri Court of Appeals, 2014)
Payton v. Union Pacific Railroad
405 S.W.3d 1 (Missouri Court of Appeals, 2013)
Williams Construction, Inc. v. Wehr Construction, L.L.C.
403 S.W.3d 660 (Missouri Court of Appeals, 2012)
Ries v. Shoemake
359 S.W.3d 137 (Missouri Court of Appeals, 2012)
Dutch Jackson Iatg, LLC v. Basketball Marketing Co.
846 F. Supp. 2d 1044 (E.D. Missouri, 2012)
Belt v. WRIGHT COUNTY, MO.
347 S.W.3d 665 (Missouri Court of Appeals, 2011)
Arnold v. Minger
334 S.W.3d 650 (Missouri Court of Appeals, 2011)
Unerstall Foundations, Inc. v. Corley
328 S.W.3d 305 (Missouri Court of Appeals, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
279 S.W.3d 179, 2009 Mo. LEXIS 38, 2009 WL 837698, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gateway-foam-insulators-inc-v-jokerst-paving-contracting-inc-mo-2009.