Williams Construction, Inc. v. Wehr Construction, L.L.C.

403 S.W.3d 660, 2012 WL 5451725, 2012 Mo. App. LEXIS 1405
CourtMissouri Court of Appeals
DecidedNovember 8, 2012
DocketNo. SD 31542
StatusPublished
Cited by8 cases

This text of 403 S.W.3d 660 (Williams Construction, Inc. v. Wehr Construction, L.L.C.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Williams Construction, Inc. v. Wehr Construction, L.L.C., 403 S.W.3d 660, 2012 WL 5451725, 2012 Mo. App. LEXIS 1405 (Mo. Ct. App. 2012).

Opinion

JEFFREY W. BATES, J.

Wehr Construction, L.L.C. (Wehr) appeals from a judgment awarding damages for breach of contract to Williams Construction, Inc. (Williams). Wehr contends the trial court erred by: (1) finding Wehr’s termination of a purchase order was a breach of the agreement when Williams’ earlier noncompliance with the agreement’s terms was the first breach; and (2) awarding damages for lost profits and overhead expenses. The trial court correctly determined that there was a breach of contract by Wehr and that Williams sustained a $30,000 loss of profits from that breach. The trial court’s award of an additional $5,000 for overhead expenses, however, was not supported by the evidence. Therefore, we affirm the judgment as modified. The cause is remanded with directions to enter an amended judgment in Williams’ favor in the net amount of $15,028.

In this court-tried case, our review is governed by Rule 84.13(d) and the principles set out in Murphy v. Carron, 536 S.W.2d 30, 32 (Mo. banc 1976).1 “We must affirm the trial court’s judgment unless it is not supported by substantial evidence, it is against the weight of the evidence, or it erroneously declares or applies the law.” Salem United Methodist Church v. Bottorff, 138 S.W.3d 788, 790 (Mo.App.2004). The trial court’s judgment is presumed correct, and an appellant has the burden of proving it erroneous. Surrey Condominium Ass’n, Inc. v. Webb, 163 S.W.3d 531, 535 (Mo.App.2005). We accept all evidence and inferences therefrom in the light most favorable to the prevailing party; all contrary evidence and inferences are disregarded. Essex Contracting, Inc. v. Jefferson County, 277 S.W.3d 647, 652 (Mo. bane 2009); Strobl v. Lane, 250 S.W.3d 843, 844 (Mo.App.2008). The credibility of the witnesses and the weight to be given to their testimony is for the trial court, which is free to believe none, part or all of the testimony of any witness. Christian Health Care of Springfield West Park, Inc. v. Little, 145 S.W.3d 44, 48 (Mo.App.2004). We defer to the credibility determinations of the trial court “because it is in a better position to not only judge the credibility of witnesses directly, but also their sincerity and character as well as other tidal intangibles which may not be completely revealed by the record.” Tichenor v. Vore, 953 S.W.2d 171, 174 (Mo. App.1997); Rule 84.13(d)(2). The following summary of the facts has been prepared in accordance with these principles.

Williams sells metal building packages, and Wehr constructs buildings. On October 18, 2004, Wehr executed Purchase Order No. 003 (the purchase order), requesting that Williams provide four pre-engineered steel buildings for a total cost of $299,435. The four buildings included a warehouse, retail strip center, convenience store and car wash. These buildings were to comprise the “Kansas Plaza,” located at the corner of Kansas Expressway and Sunset Boulevard in Springfield, Missouri (hereinafter re[663]*663ferred to as the project). In connection with the project, Williams submitted an invoice to Wehr to cover the “mobilization” fee for $14,972, which Wehr paid in full in early November.2 On November 11, 2004, Wehr notified Williams by letter that Wehr was placing the project on hold.

In a letter dated December 9, 2004, Wehr canceled the purchase order. Wehr explained that it had been “forced to reassess costs” to build the project and “with regrets [is] forced to cancel the order” because the “costs of construction materials, especially steel, have increased tremendously.” Thereafter, Williams stopped its work on the project.

In a letter dated December 29, 2004, Williams acknowledged Wehr’s cancellation. Williams stated that, according to the terms and conditions of the purchase order, “project cost does not appear to be a just reason” for termination. Instead, Williams stated that the “Termination by The Owner for Convenience” clause applied. Cancellation pursuant to that clause entitled Williams to receive payment for work executed and costs incurred by reason of the termination, along with reasonable overhead and profit on the work not executed. Williams stated that it was owed $60,986.25 because of the cancellation, calculated as follows: (1) $35,000 for lost profit and overhead expenses; and (2) $25,986.25 owed to Williams’ supplier, American Buildings Company (ABC) for engineering services. After reducing that sum to account for the prior $14,972 mobilization fee payment, Williams demanded payment in the amount of $46,014.25 on the purchase order.

Wehr responded in a January B, 2005 letter. Wehr acknowledged that it paid $14,972 for “5% mobilization” and admitted that amount was “quite fair and standard procedure in the construction industry,” but Wehr denied that it owed any additional amount on the purchase order. In February 2005, Williams again made a demand for payment, but Wehr refused. Wehr completed the project with steel buildings purchased from a different supplier.

Williams sued Wehr for breach of contract, and Wehr filed a counterclaim seeking the return of its $14,972 payment. In May 2011, the case was tried to the court. The only witnesses were Williams’ president, David Williams (Mr. Williams), and Wehr L.L.C. member Scott Wehr (Mr. Wehr). After hearing the witnesses’ testimony and considering a number of exhibits, the trial court found in favor of Williams on its breach of contract claim and against Wehr on its counterclaim.3 The court found that Williams had sustained damages in the amount of $20,027.97.4 The court denied Williams’ request for $25,986.25 to pay ABC. This appeal followed. Additional facts necessary to the disposition of the case are included below as we address Wehr’s two points on appeal.

Point I

Wehr’s first point challenges the trial court’s determination that Wehr breached the agreement by terminating the pur[664]*664chase order. The following facts are relevant to this issue.

Paragraphs 5 and 10 of the purchase order apply to Williams as “Supplier” and Wehr as “Contractor.” Paragraph 5 states:

All submittals (shop drawings, samples, cut sheets, etc....) as required by the Contract Documents, are due in Contractor’s office no later than three (3) weeks from the date of this Agreement. Included shall be all anticipated lead times involved with submittals. Failure to comply with the above unless approved by Contractor in writing, may impose liability for job delays.

Paragraph 10 states:

Contractor may at any time terminate this Purchase Order after Two (2) days written notice to Supplier at his last known mailing address for either of the following reasons:
a. Material not in compliance with the specifications or meeting Architect’s approval.
b. Failure by Supplier to deliver the specified material in a timely manner or as required by the construction schedule.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
403 S.W.3d 660, 2012 WL 5451725, 2012 Mo. App. LEXIS 1405, Counsel Stack Legal Research, https://law.counselstack.com/opinion/williams-construction-inc-v-wehr-construction-llc-moctapp-2012.