Scullin Steel Co. v. Paccar, Inc.

748 S.W.2d 910, 6 U.C.C. Rep. Serv. 2d (West) 433, 1988 Mo. App. LEXIS 289, 1988 WL 26319
CourtMissouri Court of Appeals
DecidedMarch 29, 1988
Docket52935, 52938
StatusPublished
Cited by4 cases

This text of 748 S.W.2d 910 (Scullin Steel Co. v. Paccar, Inc.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Scullin Steel Co. v. Paccar, Inc., 748 S.W.2d 910, 6 U.C.C. Rep. Serv. 2d (West) 433, 1988 Mo. App. LEXIS 289, 1988 WL 26319 (Mo. Ct. App. 1988).

Opinions

STEPHAN, Presiding Judge.

In Scullin Steel Co. v. PACCAR, Inc., 708 S.W.2d 756 (Mo.App.1986), hereinafter Scullin I, we affirmed the circuit court’s judgment that PACCAR, Inc. was liable to Scullin Steel Co. for breach of a long-term supply contract. We further determined that had it been correctly applied, the method the circuit court used to compute Scul-lin’s damages would have yielded the lost net profit and reasonable overhead award authorized by § 400.2-708(2), RSMo. We found, however, that the circuit court had not correctly applied the method. Accordingly, we remanded the matter for a recalculation of the lost net profit and reasonable overhead elements of the damages award. Scullin appeals from the judgment as modified on remand. PACCAR cross-[912]*912appeals. We reverse in part, affirm in part, and remand.

I

PACCAR, Inc. manufactures railroad cars. Until September 18, 1981, when it closed its plant, Scullin Steel Co. manufactured railroad car components called “car-sets”. In 1979, PACCAR contracted to purchase carsets from Scullin. Subsequently, PACCAR breached. The details of PACCAR’s contract with Scullin are set out fully in Scullin I, 708 S.W.2d at 758-761, and need not be repeated here, inasmuch as the only question before us on this appeal is whether damages for the breach have been correctly calculated. Suffice it to say simply that in Scullin I we held that the contract the parties signed in 1979 obligated PACCAR to purchase 1,908 carsets from Scullin during 1981-1983 at a fixed price per carset of $4,048.00; that PAC-CAR breached this obligation; that, as a result, Scullin was, in accordance with § 400.2-708(2), RSMo, entitled to recover from PACCAR the net profit it would have realized if PACCAR had not breached, plus the reasonable overhead it would have satisfied from the contract proceeds; but that the circuit court had incorrectly calculated lost net profit and reasonable overhead.

II

Lost Net Profit

To arrive at lost net profit in the first instance, the circuit court subtracted $3,822.00, what it deemed to be Scullin’s average cost per carset for 1981-1983, from $4,048.00, the fixed contract price per carset, and multiplied the difference by 1,908, the number of carsets PACCAR was contractually obligated to purchase during the 1981-1983 period. In Scullin I, we expressly approved the “average cost per carset” as a component of the lost net profit formula.1 708 S.W.2d at 764-765. We found, however, that $3,822.00 did not fairly approximate this cost for contract years 1981-1983. Id.

The flaw in the circuit court’s calculation, as we saw it, was this: From Scullin’s records, the circuit court had determined that $3,822.00 was the average cost per carset during 1980, the last full year of Scullin’s operation. It then simply adopted $3,822.00 as the average cost per carset for contract years 1981-1983. One of the costs included in the $3,822.00 figure, however, was the cost of labor, which was paid in 1980 according to rates prescribed in a union contract. It was undisputed that this contract had been renegotiated for 1981-1983 and would have effected a marked increase in the cost of labor. Nevertheless, the circuit court failed to adjust the $3,822.00 figure to reflect this increased expense. Accordingly, in Scullin I we remanded, directing the trial court to account for the “undisputed increase of direct production cost attributable to the increase in labor costs” that Scullin would have realized during 1981-1983 if it had remained in business. Id.

On remand, the circuit court determined that Scullin’s 1981 labor costs would have exceeded its 1980 labor costs by 5% if Scul-lin had remained in business. The court adjusted the 1981 average cost per carset accordingly, then subtracted that adjusted cost from the fixed contract price per car-set to find that in 1981 Scullin would have [913]*913realized $126.00 net profit on each carset it sold to PACCAR.

The circuit court then turned to consider what effect increased labor costs would have had on Scullin’s profits in 1982 and 1983. In this regard, it stated:

The Court has considered the effects of increased labor costs, increased efficiencies, changing material and energy prices, taxes, insurance, et al., and concludes that it is not possible to arrive at a precise measure of predicted costs and profits for 1982 and 1983. Therefore, the Court, based upon [Scullin’s] avowed intentions of turning its operations into a profitable entity, will assume that adjustments in cost or price could have been made to retain a level of profits at $126 per carset.

The circuit court then multiplied $126.00 times 1,908, the number of carsets PAC-CAR was contractually obligated to purchase from Scullin during the 1981-1983 period. The product, $240,408.00, became the lost net profit award.

In its first point, Scullin asserts the record does not support the circuit court’s determination that Scullin’s 1981 labor costs would have exceeded its 1980 labor costs by 5%. Scullin is correct. No evidence of a 5% increase was adduced at trial. In a memorandum to the court on remand, Scullin did suggest that an “assumed” 5% increase in labor costs would have been offset by increased productivity. A party’s self-serving suggestion is not evidence, however, and though it might have risen to the dignity of a stipulation if PACCAR had accepted it, PACCAR did not.

To what evidence then were we referring when we directed the trial court to adjust the 1981-1983 average cost per carset to reflect “the undisputed increase of direct production cost attributable to the increase in labor costs”? Plainly, it was the unchallenged testimony of William F. Golus, a Scullin consultant who served as the company’s vice president of manufacturing when the union contract was negotiated for the period 1981-1983.

Golus’s testimony establishes that if Scullin had remained in business after 1980, the renegotiated labor contract would have effected a 10 million dollar increase in the cost of labor over the 1981-1983 period, that at least one-third of that increase would have been realized in 1981, and that, therefore, the cost of labor in 1981 alone would have exceeded the cost of labor in 1980 by at least 67%. When the average cost per carset is adjusted to reflect this 67% increase,2 it exceeds $4,048.00, the fixed contract price per carset. We therefore conclude Scullin would have realized no net profit on the sale of carsets to PACCAR after 1980.3

Scullin argues, as it did in Scullin I, that “increased efficiencies” would have [914]*914offset any increased labor costs. We find no evidence in the record to support this claim, nor can we sustain a finding of increased efficiencies on Scullin’s “avowed intentions of turning its operations into a profitable entity”. The judgment insofar as it awards Scullin lost net profit accordingly is reversed.

Ill

Reasonable Overhead

In Scullin I, we determined that in addition to lost net profit, Scullin was entitled to recover as damages from PACCAR the “fixed” costs, or “reasonable overhead”, it would have satisfied out of the proceeds of the breached contract.4

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Williams Construction, Inc. v. Wehr Construction, L.L.C.
403 S.W.3d 660 (Missouri Court of Appeals, 2012)
Moore Ex Rel. Moore v. Bi-State Development Agency
132 S.W.3d 241 (Supreme Court of Missouri, 2004)
Investors Title Co. v. Chicago Title Insurance Co.
18 S.W.3d 70 (Missouri Court of Appeals, 2000)
Scullin Steel Co. v. Paccar, Inc.
748 S.W.2d 910 (Missouri Court of Appeals, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
748 S.W.2d 910, 6 U.C.C. Rep. Serv. 2d (West) 433, 1988 Mo. App. LEXIS 289, 1988 WL 26319, Counsel Stack Legal Research, https://law.counselstack.com/opinion/scullin-steel-co-v-paccar-inc-moctapp-1988.