Galesburg & K. Electric Ry. Co. v. Hart

221 F. 7, 136 C.C.A. 533, 1915 U.S. App. LEXIS 1280
CourtCourt of Appeals for the Seventh Circuit
DecidedJanuary 5, 1915
DocketNo. 2137
StatusPublished
Cited by8 cases

This text of 221 F. 7 (Galesburg & K. Electric Ry. Co. v. Hart) is published on Counsel Stack Legal Research, covering Court of Appeals for the Seventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Galesburg & K. Electric Ry. Co. v. Hart, 221 F. 7, 136 C.C.A. 533, 1915 U.S. App. LEXIS 1280 (7th Cir. 1915).

Opinion

BAKER, Circuit Judge

(after stating the facts as above). [1] I. Appellees filed their original bill on April 14, 1904. On March 3, 1914, appellees were permitted by the court to file certain amendments to the bill. These amendments were required by the court and made by appellees on the theory that they were proper, and probably necessary, in order to make the pleadings conform to the facts as established by the proofs. Appellant, however, insists, first, that the original bill was based upon the contract of November 18, 1902, as a written contract, and that the bill as amended was bottomed on the oral contract of December 5, 1902, and that, therefore, a new and different cause of action viras stated, which was barred by limitation and laches; and, second, that in any event it was error, under the equity rules, to permit the amendment.

These contentions require a' consideration of the pleadings and proofs as they stood prior to the amendment. The original bill was not, as appellant insists, based upon the contract of November 18, 1902, as a written contract between appellant and appellees under which the work was done. As a premise, the bill alleged that appellees and Brandenburg entered into the contract of November 18, 1902, with appellant’s approval, and that shortly thereafter, on December 5, 1902, appellant bought out Brandenburg and procured its release from all [11]*11obligations to him. And upon this premise the bill proceeded to charge that thereby Brandenburg became unable to carry on the construction as contemplated, and that thereupon appellant became legally obligated to enter into a contract with appellees for the completion df the railroad in accordance with the terms of the writing of N'ovember 18, 1902. The proofs showed that Brown, after appellant had bought out Brandenburg and before suit was instituted, signed the writing of November 18, 1902, as agent of Brandenburg. The master found it unnecessary to determine what, if any, legal obligations existed between the parties prior to December 5, 1902, because he found that on that date the parties had orally agreed, as they had a right to do, to certain terms which would work a slight modification of the preexistent legal obligations, if such there were. Appellees were earnestly insisting during the taking of the proofs that at the meeting of December 5, 1902, appellant had orally agreed with them that’ they should continue the construction according to all of the terms and conditions of the writing which had been signed by appellees and approved by appellant on November 18, 1902. On the other hand, appellant, through its promoters, was contending that at the meeting of December 5, 1902, appellees had agreed to build a railroad “of standard construction” through Kewanee to Weathersfield, and to grade the line •from Weathersfield to Galva for the gross sum of $75,000, with additional payments for extras ordered by appellant. Appellant was bringing forward this testimony to sustain its answer and also a cross-bill under which it was claiming damages for appellees’ failure to build a railroad “of standard construction.” The master found that at the meeting of December 5, 1902, the parties had agreed that all of the terms and conditions and specifications of the writing of November 18, 1902, should be observed on both sides except as to compensation. In the writing of November 18, 1902, the price per mile for completed road was $15,942, and the price for grading beyond where the road was completed was $3,000 per mile. At those rates the work would have come to $78,202.07. The master found that these rates were modified at the meeting of December 5, 1902, so that, while grading should be paid for at the rate of $3,000 per mile, the completed work was to be enough less so that the whole work, exclusive of extras, should aggregate $75,000. This finding was counter to the contention of appellant that no plans and specifications or terms or conditions of pay had been agreed upon, and that appellant was to pay $75,000 for “standard construction.” The amendment to the bill was drafted by appellees to cover their acquiescence in the master’s finding that, while the parties had accepted the writing of November 18, 1902, in all other respects, they had diminished the gross compensation by $3,202.07. The bill as amended recites the same premises with regard to the situation between appellant and Brandenburg, and the same act of appellant in eliminating Brandenburg from the situation, and then proceeds to charge that on December 5, 1902, the parties adopted the writing of November 18, 1902, in all respects except as to compensation, which was reduced to $75,000.

In our judgment the bill as amended does not set up a new and different cause of action. It is to be observed that the statute gives a [12]*12lien to all persons who do work or furnish materials for a railroad “by contract with said corporation.” If the railroad corporation has contracted for the work—in other words, if the contractor is not an interloper—the statute gives a lien. This statutory right was the law basis of the 'original bill, and it was likewise the law basis of the bill as amended. The original bill asserted, as a fact basis, that the writing of November 18, 1902, became, by reason of the circumstances and the acts of the parties, the expression of all the- terms and conditions of the contract under which appellees did the work for which appellant had failed to pay. The bill as amended asserted, as a fact basis, that the writing of November 18, 1902, became, by reason of the circumstances and the acts and the oral agreements of the parties, the expression of all the terms and conditions of the contract except that the consideration was reduced $3,202.07. Instead of the amendment 'bringing forward a new and different cause of action, it seems to us to make merely a slight change in stating the details of the origi-nal fact basis of the cause of action.

[2] Between stating a new cause of action and amending the details of the original cause of action, the difference is vital and is clearly illustrated by the leading cases. Departures occur either where the pleader deserts, in point of fact, the ground that he had first taken, or where he puts the same facts on a new ground in point of law. Union Pacific Railway Co. v. Wyler, 158 U. S. 285, 15 Sup. Ct. 877, 39 L. Ed. 983, is an instance of departure from law to law. Wyler, an employé of the railway company, was injured through an act of a fellow employé. For this there would be no liability on the part of the railway company at common- law unless the fellow employé was incompetent and his incompetency was known to the railroad company, which nevertheless continued him in its service, and unless such incompetency was unknown to Wyler. Wyler alleged that his f'ellow employé was incompetent, failed to state that his fellow servant was negligent in performing the injurious act (unless such negligence was to be inferred from the previous allegation regarding incompetency), charged that the railroad company knew of the fellow employé’s incompetency, and nevertheless retained him in its service, and averred that Wyler neither knew nor was chargeable with knowledge of the incompetency of his fellow servant. In his amended declaration he charged that he was injured through the negligent act of a fellow servant, and that a statute of Kansas, within which state the injury was inflicted, made the railroad company liable to Wyler for the negligent act of the fellow employé, regardless of his incompetency and of knowledge thereof.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kintner v. United States
71 F.2d 961 (Tenth Circuit, 1934)
Henderson v. Midwest Refining Co.
43 F.2d 23 (Tenth Circuit, 1930)
America Land Co. v. City of Keene
41 F.2d 484 (First Circuit, 1930)
Gamble v. Brown
29 F.2d 366 (Fourth Circuit, 1928)
Combined Metals, Inc. v. Bastian
267 P. 1020 (Utah Supreme Court, 1928)
Walker v. Iowa Cent. Ry. Co.
241 F. 395 (S.D. Iowa, 1916)

Cite This Page — Counsel Stack

Bluebook (online)
221 F. 7, 136 C.C.A. 533, 1915 U.S. App. LEXIS 1280, Counsel Stack Legal Research, https://law.counselstack.com/opinion/galesburg-k-electric-ry-co-v-hart-ca7-1915.