Frost Crushed Stone Co. v. Odell Geer Construction Co.

110 S.W.3d 41, 2002 Tex. App. LEXIS 8877, 2002 WL 31778399
CourtCourt of Appeals of Texas
DecidedDecember 11, 2002
Docket10-00-282-CV
StatusPublished
Cited by36 cases

This text of 110 S.W.3d 41 (Frost Crushed Stone Co. v. Odell Geer Construction Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Frost Crushed Stone Co. v. Odell Geer Construction Co., 110 S.W.3d 41, 2002 Tex. App. LEXIS 8877, 2002 WL 31778399 (Tex. Ct. App. 2002).

Opinions

OPINION

REX D. DAVIS, Chief Justice.

Odell Geer Construction Company (“Geer”) sued Frost Crushed Stone Company (“Frost”) under theories of breach of contract, negligent misrepresentation, and promissory estoppel. Before trial, Geer non-suited Frost on all claims except promissory estoppel. Following a jury trial, the court entered judgment in favor of Geer. The jury awarded actual damages in the amount of $40,000 plus attorney’s fees. Frost argues that 1) there is no evidence and factually insufficient evidence to support the reliance element of Geer’s promissory estoppel claim; 2) there is no evidence and factually insufficient evidence to overcome the statute of frauds defense established by Frost; 3) the statute of frauds bars recovery on Frost’s oral promise as a matter of law; 4) the trial court erred in submitting the question of lost profits to the jury; and 5) the trial court erred in permitting Geer to recover attor[44]*44ney fees based on a contingent fee percentage.

Background

On October 12, 1995, Geer submitted a bid (as a subcontractor) to Ellis McGinnis Construction Company (“Ellis”), the general contractor, to produce and haul “flex base” rock for a highway project. Geer contends Frost offered to supply the rock to Geer for the project in a telephone conversation. On October 30, 1995, Geer sent a letter to Texas Trucking Company (“TTC”) offering to contract to haul the “flex base” rock, conditioned upon Geer’s receipt of a contract from Ellis. Geer asserts that it relied on Frost’s promise to furnish the rock when it contracted with TTC to haul the rock. Ellis subsequently accepted Geer’s bid on November 2, 1995. After Ellis accepted Geer’s bid, Frost provided a written price quote for the rock. TTC signed a hauling contract with Geer on November 9, 1995, to transport the rock. Several months later, Frost notified Geer that it would be unable to supply the rock as previously promised.

Promissory Estoppel

Although promissory estoppel is normally a defensive theory, it is an available cause of action to a promisee who relied to his detriment on an otherwise unenforceable promise. See Wheeler v. White, 398 S.W.2d 93, 96-97 (Tex.1965); Reyna v. First Nat’l Bank Edinburg, 55 S.W.3d 58, 70 n. 4 (Tex.App.-Corpus Christi 2001, no pet.); Bodies v. Brighton Builders, Inc., 29 S.W.3d 159, 166 (Tex.App.-Houston [14th Dist.] 2000, no pet.); Bailey v. City of Austin, 972 S.W.2d 180, 193 (Tex.App.-Austin 1998, pet. denied); Cherokee Communications, Inc. v. Skinny’s, Inc., 893 S.W.2d 313, 317 (Tex.App.-Eastland 1994, writ denied); Henderson v. Texas Commerce Bank-Midland, N.A, 837 S.W.2d 778, 781-82 (Tex.App.-El Paso 1992, writ denied). The requisites of promissory estoppel in Texas are: (1) a promise; (2) foreseeability of reliance thereon by the promisor; and (3) substantial reliance by the promisee to his detriment. See English v. Fischer, 660 S.W.2d 521, 524 (Tex.1983); Bailey, 972 S.W.2d at 193; Allied Vista, Inc. v. Holt, 987 S.W.2d 138, 141 (Tex.App.-Houston [14th Dist.] 1999, pet. denied).

The San Antonio Court has held that promissory estoppel is a viable cause of action in bid construction cases. The court held:

As is true in most, if not all, bid construction cases, the present situation does not involve a contract. Therefore, were we to hold that promissory estop-pel does not exist in bid construction cases, this would necessarily mean that, notwithstanding any language or conduct by the subcontractor which leads the general contractor to do that which he would not otherwise have done and, thereby, incur loss or injury, the general contractor would be denied all relief. This proposition is untenable and conflicts with the underlying premise of promissory estoppel. Accordingly, we find that promissory estoppel is a viable cause of action in bid construction cases.

Traco, Inc. v. Arrow Glass Co., Inc., 814 S.W.2d 186, 189 (Tex.App.-San Antonio 1991, writ denied) (citations omitted); see also Sipco Sens. Marine, Inc. v. Wyatt Field Sen. Co., 857 S.W.2d 602, 605 (Tex.App.-Houston [1st Dist.] 1993, no writ) (permitting recovery for promissory estop-pel where plaintiff relied on subcontractor’s promise to do painting job).

Reliance

A central element of promissory estoppel is detrimental reliance. See Gilmartin v. KVTV-Channel IS, 985 S.W.2d [45]*45553, 558 (Tex.App.-San Antonio 1998, no pet.) (citing Collins v. Allied Pharmacy Mgt, Inc., 871 S.W.2d 929, 937 (Tex.App.-Houston [14th Dist.] 1994, no writ)). Reliance on the promise must be reasonable and justified. Id. (citing American Tobacco Co. v. Grinnell, 951 S.W.2d 420, 436 (Tex.1997); Sipco, 857 S.W.2d at 605).

In point one, Frost contends that there is no evidence and factually insufficient evidence to support the reliance element of Geer’s promissory estoppel claim. Frost contends that the evidence shows that Geer did not rely on Frost’s promises because: 1) Geer did not use Frost’s figures in submitting its bid to Ellis; and 2) Frost’s written quote came after Geer had contracted with TTC. Geer argues, however, that it detrimentally relied on Frost’s oral promise in contracting with TTC to haul the rock.

No Evidence

When we review a no evidence claim, we consider only the evidence and inferences which tend to support the contested issue and disregard all evidence and inferences to the contrary. See Merrell Dow Pharms., Inc. v. Havner, 953 S.W.2d 706, 711 (Tex.1997); Beard v. Beard, 49 S.W.3d 40, 55 (Tex.App.-Waco 2001, pet. denied). We will sustain such a point if: (a) there is a complete absence of evidence of a vital fact; (b) we are barred by rules of law or evidence from giving weight to the only evidence offered to prove a vital fact; (c) the evidence offered to prove a vital fact is no more than a mere scintilla; or (d) the evidence conclusively establishes the opposite of the vital fact. Id. (citing Robert W. Calvert, “No Evidence” and “Insufficient Evidence” Points of Error, 38 Tex. L.Rev. 361, 362-63 (I960)). “More than a scintilla of evidence exists when the evidence supporting the finding, as a whole, ‘rises to a level that would enable reasonable and fair-minded people to differ in their conclusions.’ ” Id. (quoting Burroughs Wellcome Co. v. Crye, 907 S.W.2d 497, 499 (Tex.1995)).

Rey Whitener testified that Frost made an oral promise to furnish the rock before Geer contracted with TTC.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

in Re Steven Eaton
Court of Appeals of Texas, 2022
Theresa Lee Kamke v. Brian Kelly Kamke
Court of Appeals of Texas, 2021
Simulis, L.L.C. v. General Electric Capital Corporation
439 S.W.3d 571 (Court of Appeals of Texas, 2014)
In Re Acm-Tex., Inc.
430 B.R. 371 (W.D. Texas, 2010)
Addicks Services, Inc. v. GGP-BRIDGELAND, LP
596 F.3d 286 (Fifth Circuit, 2010)
Ted Booher v. Zeig Enterprises, Inc.
Court of Appeals of Texas, 2009

Cite This Page — Counsel Stack

Bluebook (online)
110 S.W.3d 41, 2002 Tex. App. LEXIS 8877, 2002 WL 31778399, Counsel Stack Legal Research, https://law.counselstack.com/opinion/frost-crushed-stone-co-v-odell-geer-construction-co-texapp-2002.