This text of Addicks Services, Inc. v. GGP-Bridgeland, LP, et a (Addicks Services, Inc. v. GGP-Bridgeland, LP, et a) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Addicks Services, Inc. v. GGP-Bridgeland, LP, et a, (5th Cir. 2010).

Opinion

REVISED MARCH 8, 2010 IN THE UNITED STATES COURT OF APPEALS FOR THE FIFTH CIRCUIT United States Court of Appeals Fifth Circuit

FILED February 8, 2010 No. 09-20155 Charles R. Fulbruge III Clerk ADDICKS SERVICES, INC.,

Plaintiff - Appellant v.

GGP-BRIDGELAND, LP, formerly known as Rouse-Houston, LP; BRIDGELAND GP, LLC; SAFECO INSURANCE COMPANY OF AMERICA,

Defendants - Appellees

Appeal from the United States District Court for the Southern District of Texas

Before KING, GARZA, and HAYNES, Circuit Judges. KING, Circuit Judge: In this contract action, plaintiff–appellant is a contractor seeking damages for extra work and delay costs incurred performing land improvement for a residential development in Harris County, Texas. The district court granted summary judgment to defendants–appellees, holding that plaintiff–appellant’s claims were barred by waivers and releases it executed monthly to receive progress payments. We affirm. I. BACKGROUND No. 09-20155

GGP-Bridgeland, LP (“Bridgeland”)1 is the owner of Bridgeland, a residential development in Harris County, Texas. Addicks Services, Inc. (“Addicks”), submitted a bid to perform excavation and grading work on the approximately 500-acre site. On July 20, 2004, Addicks and Bridgeland executed a Standard Form of Agreement Between Owner and Contractor (the “Contract”). Addicks’s role was to perform “cut and fill” services, which involve excavating or “cutting” the land on the site to create lakes and other scenic features. The excavated dirt or “spoil” produced from the excavation would then be spread or “filled” across the development to create a uniform elevation. Under the original terms of the Contract, Addicks was required to cut and fill slightly more than 2 million cubic yards of dirt in 150 calendar days; it would receive $4,582,721.79 for this service. The parties contemplated that the Contract would consist of multiple documents. The Contract defines “Work” as “the work described in the Drawings and Specifications . . . and any requirements set forth in any other Contract Documents enumerated in Article XIX.” (Contract ¶ 1.1.) Article XIX is labeled “Integration Clause” and consists of two provisions. The first provides that the Contract, together with its attached exhibits and documents incorporated by reference, is the entire agreement and supersedes prior negotiations, representations, and agreements. (Contract ¶ 19.1.) It further contained a no- oral-modification clause stating that the Contract could be amended or modified only in written change order forms signed by both Addicks and Bridgeland. (Id.) The second provision enumerated the documents constituting the Contract.2

1 Bridgeland GP, LLC, is the general partner of GGP-Bridgeland, LP. GGP-Bridgeland, LP, secured a Release of Lien Bond from Safeco Insurance Company of America, so that it would be able to sell residential units within the Bridgeland development free and clear of any liens. Unless otherwise specified, we refer to Appellees collectively as “Bridgeland.” 2 Those documents listed were: a) This Agreement and Special Conditions of Agreement;

2 No. 09-20155

(Contract ¶ 19.2.) Two articles in the Contract dealt specifically with changes and modifications to the work Addicks was to perform under the Contract. Addicks was required to notify Bridgeland of any “claim[] for additional compensation, extra work, delay, extensions of time, or loss, injury or damages” within ten days of its occurrence. (Contract ¶ 10.1.) Addicks was then required to submit a detailed claim within thirty days and to submit a change order proposal on request of Bridgeland. (Contract ¶ 10.2.) Addicks agreed to perform changes and modifications to the scope of work under the Contract that were requested by Bridgeland in writing; payment for such changes was governed by the Contract’s schedule or by the cost plus a 5% markup. (Contract ¶ 12.1.) If the parties disagreed over a particular change, Addicks was required to proceed with the modification and prepare a change order proposal, which was “subject to full audit, review and approval by [Bridgeland].” (Id.) Article VIII of the Contract governed payment to Addicks. The Contract specified that Addicks would perform the requested work for $4,582,721.79 (Contract ¶ 8.1), but it also provided for monthly progress payments (Contract ¶ 8.2). To receive a progress payment, the Contract contemplated that Addicks would submit a written application detailing the work performed to date; the application would be accompanied by an executed lien waiver that would release

b) Exhibits to this Agreement; c) Performance, Payment, and other Bonds identified; d) Invitation to Bidders; e) Instructions to Bidders; f) Notice to Proceed; g) Standard and Special Specifications; h) Construction Drawings; i) Storm Water Pollution Prevention Plan[;] j) Addenda; k) All Change Orders and written modifications that amend or supplement the Contract Documents pursuant to the Contract Documents; l) All documents incorporated by reference into the Contract Documents. (Contract ¶ 19.2.)

3 No. 09-20155

Addicks’s mechanic’s and materialman’s lien on the project. (Id.) Blank lien waiver forms were attached to the Contract. The relevant form was entitled “Waiver and Release of Lien upon Progress Payment” (the “Interim Waiver”), and provides, in relevant part: [Addicks], in consideration of the sum of $__________, hereby waives and releases its lien and right to claim a lien for labor, services, or materials furnished through __________ (date of this waiver) under contract with __________ on the job of __________ (Owner) to the following property: __________ (Name and Address of Project). This waiver and release does not cover any retention or labor, services or materials furnished after the date specified. Any and all . . . subcontractors . . . have been paid and satisfied in full, and there are no outstanding claims of any character arising out of, or related to, the undersigned’s activities on, or improvements to, the Project. This Waiver constitutes a representation by [Addicks] that the payment referenced above, once received, constitutes full and complete payment for all work[3] performed, and all costs or expenses incurred (including, but not limited to, costs for supervision, field office overhead, home office overhead, interest on capital, profit, and general conditions costs) relative to the work or improvements at the Project as of the date of this Waiver, except for the payment of retainage. [Addicks] specifically waives, quitclaims and releases any claim for damages due to delay, hindrance, interference, acceleration, inefficiencies or extra work, or any other claim of any kind it may have . . . as of the date of this Waiver, except as follows: _________________________________. This Waiver is specifically made for the benefit of [Bridgeland]. The amount of money set forth as due and owing in the immediately preceding Waiver dated _____, 20__, has been received, and is deemed paid in full.

3 Addicks argues that it is unclear whether the word “work” in the Interim Waiver form refers to the term “Work” defined by paragraph 1.1 of the Contract. We address this contention below.

4 No. 09-20155

(Contract Ex. E.)4 Addicks received notice to proceed with the project in August 2004. Addicks claims that, subsequent to commencing work, a number of factors hindered its timely performance, including Bridgeland’s requests for additional work, inclement weather, and site accessibility problems. Pursuant to the mechanisms in the Contract, Addicks made numerous requests for information regarding work, for extension of time, and for change orders to reflect the additional work performed and to adjust the price of the Contract accordingly.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Chaplin v. NationsCredit Corp.
307 F.3d 368 (Fifth Circuit, 2002)
State of Texas v. American Tobacco Co
463 F.3d 399 (Fifth Circuit, 2006)
Foradori v. Harris
523 F.3d 477 (Fifth Circuit, 2008)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Marian Fontenot, Etc. v. The Upjohn Company
780 F.2d 1190 (Fifth Circuit, 1986)
J.M. Davidson, Inc. v. Webster
128 S.W.3d 223 (Texas Supreme Court, 2003)
Van Independent School District v. McCarty
165 S.W.3d 351 (Texas Supreme Court, 2005)
In Re Weekley Homes, L.P.
180 S.W.3d 127 (Texas Supreme Court, 2005)
Stafford v. Allstate Life Insurance Co.
175 S.W.3d 537 (Court of Appeals of Texas, 2005)
Bath Junkie Franchise, Inc. v. Hygiene, L.L.C.
246 S.W.3d 356 (Court of Appeals of Texas, 2008)
Schomburg v. TRW VEHICLE SAFETY SYSTEMS, INC.
242 S.W.3d 911 (Court of Appeals of Texas, 2008)
Eckland Consultants, Inc. v. Ryder, Stilwell Inc.
176 S.W.3d 80 (Court of Appeals of Texas, 2004)
Coker v. Coker
650 S.W.2d 391 (Texas Supreme Court, 1983)
Fairfield Financial Group, Inc. v. Gawerc
814 S.W.2d 204 (Court of Appeals of Texas, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
Addicks Services, Inc. v. GGP-Bridgeland, LP, et a, Counsel Stack Legal Research, https://law.counselstack.com/opinion/addicks-services-inc-v-ggp-bridgeland-lp-et-a-ca5-2010.