Sipco Services Marine, Inc. v. Wyatt Field Service Co.

857 S.W.2d 602, 1993 WL 82707
CourtCourt of Appeals of Texas
DecidedMarch 25, 1993
Docket01-91-00916-CV
StatusPublished
Cited by64 cases

This text of 857 S.W.2d 602 (Sipco Services Marine, Inc. v. Wyatt Field Service Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sipco Services Marine, Inc. v. Wyatt Field Service Co., 857 S.W.2d 602, 1993 WL 82707 (Tex. Ct. App. 1993).

Opinions

OPINION ON REHEARING

SAM BASS, Justice.

After a nonjury trial, the judge ruled for appellee (Wyatt) on its contract claim and awarded damages of $40,488 plus attorney's fees. We reform the judgment to make the award of attorney’s fees to Wyatt on appeal to the supreme court con[604]*604ditional on Sipco’s appeal being unsuccessful, and as reformed, we affirm.1

FACTS

In early July of 1987, Wyatt solicited bids from various subcontractors for the external painting and internal lining of two storage tanks to be constructed at the Shell — Deer Park plant. On July 10, 1987, Wyatt telephoned appellant (Sipco) and asked Sipco to submit a bid immediately. Based on information provided by Wyatt, Sipco submitted a written bid of $477,700 on July 13, 1987.

Six contractors originally submitted bids, and two were lower than Sipco’s. However, Wyatt contended at trial that it relied on Sipco’s bid because the lower bidders were financially unstable, had questionable performance records, or were unacceptable to the owner. Sipco argued that the two lower bids were acceptable because both contractors offered to obtain performance and payment bonds, and one offered an extended warranty on the project.

Wyatt used Sipco’s $477,700 bid to calculate its bid for its own work on the project, and submitted its bid to S.I.P., the general contractor. S.I.P. orally awarded the contract to Wyatt on August 14, 1987. Sipco knew Wyatt had used its bid in Wyatt’s own project estimates, and also knew Wyatt was awarded the project. Wyatt signed a written contract with S.I.P. on September 8, 1987. Wyatt’s engineers then finalized the storage tank’s design sketches.

Around September 11, 1987, Wyatt provided all bidders the final, detailed drawings of the storage tanks and requested a “confirmation” of the subcontractor’s respective bids. Wyatt’s agent testified that this resolicitation was meant to prevent changes in the bids submitted. Sipco argues that Wyatt’s request or resolicitation of new bids was a rejection of the original bids, and that these final drawings introduced complex new requirements that Sip-co had not anticipated when preparing its original bid.

After receiving the updated drawings, Sipco did not rebid, but did propose a price reduction from its original bid if a less expensive lining was used. Wyatt understood this correspondence to be a reconfirmation of Sipco’s $477,700 bid from July. Sipco, on the other hand, argued that its failure to rebid a new (higher) price was not a confirmation of its old bid. Instead, Sipco argued no bid was made because the new requirements would have increased Sipco’s bid, and Sipco believed that Wyatt already considered Sipco’s July bid to be too high. To show its reliance, Wyatt argued at trial that it never expressly rejected Sipco’s July offer, but a Wyatt employee testified that while The main goal of the September resolicitation was to maintain the July price of $477,700, Wyatt hoped to receive a lower bid.

On November 11,1987, Wyatt telephoned Sipco and orally awarded Sipco the painting/lining project. The trial judge found that the several months between the bidding and the November phone call was a reasonable period of time. Also on November 11, Wyatt sent the proposed subcontract to Sipco. Wyatt argued that this written contract was a mere formality, as the contract was formed when Wyatt orally awarded the bid to Sipco. Sipco argued that there was never any oral or written contract formed due to the complex changes and cost increases the new drawings involved.

The parties met on November 18, 1987, to discuss their differences. At this meeting, Sipco requested an additional $156,467 to cover increases in labor and material costs (for a total bid of $634,167). After discussing this price increase, Sipco agreed to absorb the extra work costs if Wyatt would pay $82,500 for the increased cost of the tank lining material, Plasite 4300, amounting to a revised bid of $560,200. (Sipco claimed the price of the material had risen during the time between its bid and Wyatt’s acceptance.) Wyatt asked S.I.P. to authorize and accept the $82,500 increase, but because Sipco had failed to provide [605]*605verification of this alleged price increase for the Plasite 4300, S.I.P. refused.

On December 3, 1987, Wyatt received confirmation of a bid from another subcontractor, TIPCO, to do the work for $518,-188. On December 30, 1987, Wyatt asked S.I.P. to allow TIPCO to replace Sipco, and perform the painting and lining work. S.I.P. approved, but required Wyatt to absorb the difference between TIPCO’s replacement bid of $518,188 and Sipco’s original bid of $477,700, a total of $40,488. In late January of 1988, Wyatt notified Sipco that Wyatt would hold Sipco responsible for that $40,488 difference.

Sipco and Wyatt met in February of 1988 to discuss Sipco’s obligation to perform the work as bid in July. At this meeting, Sipco indicated its continued interest in the project, but complained of the drafted subcontract prepared by Wyatt in November of 1987. Sipco contended that several key provisions materially changed the original specifications on which Sipco had based its July bid. Wyatt claimed that the drafted subcontract contained no material changes and was but a mere formality anyway, as a contract had already been formed on the basis of promissory estoppel.

In March of 1988, Wyatt and TIPCO contracted for the painting/lining work. After completion of the work in December 1988, Wyatt demanded payment of $40,488, and then brought this suit.

I. Points of error one, three, and six.

In its first point of error, Sipco asserts it deserved a directed verdict because Wyatt waived its promissory estoppel claim by engaging in “bid shopping” and “bid chiseling.” In its third point of error, Sipco asserts it deserved a directed verdict because Wyatt did not reasonably rely on Sipco’s bid. In its sixth point of error, Sipco asserts it deserved a directed verdict because Wyatt failed to prove its damages.

A. Was promissory estoppel waived by “bid shopping” and “bid chiseling?”

Sipco contends Wyatt waived its promissory estoppel claim by “bid shopping” or “bid chiseling.”

The elements of promissory estop-pel are; (1) a promise, (2) foreseeability of reliance by the promisor, and (3) substantial reliance by the promisee to its detriment. English v. Fischer, 660 S.W.2d 521, 524 (Tex.1983); Adams v. Petrade Int’l, Inc., 754 S.W.2d 696, 707 (Tex.App. — Houston [1st Dist.] 1988, writ denied). The promise will be enforced if necessary to avoid injustice. Adams, 754 S.W.2d at 707. Reliance on the promise must be reasonable. Douglas v. Aztec Petroleum Corp., 695 S.W.2d 312, 317 (Tex.App — Tyler 1985, no writ); Thate v. Texas & Pac. Ry., 595 S.W.2d 591, 595-96 (Tex.Civ.App. — Dallas 1980, writ dism’d).

Sipco argues that Wyatt’s “bid shopping” and “bid chiseling” show that Wyatt did not rely on Sipco’s bid. Sipco relies on Preload Technology, Inc. v. A.B. & J. Construction Co., 696 F.2d 1080

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Carmen Aleman v. Standard Casualty Company
Court of Appeals of Texas, 2025
In Re C.J.S., a Child v. the State of Texas
Court of Appeals of Texas, 2024
Vrabel v. Kagin
S.D. Texas, 2022
Eric Lopez v. Rocky Creek Partners, LLC
Court of Appeals of Texas, 2021
in Re Troy Lee Christensen
Court of Appeals of Texas, 2017
Hern Family Ltd. Partnership v. Compass Bank
863 F. Supp. 2d 613 (S.D. Texas, 2012)
P. McGregor Enterprises, Inc. v. Hicks Construction Group, LLC
420 S.W.3d 45 (Court of Appeals of Texas, 2012)
Ansell Healthcare Products, Inc. v. United Medical
355 S.W.3d 736 (Court of Appeals of Texas, 2011)
Motten v. Chase Home Finance
831 F. Supp. 2d 988 (S.D. Texas, 2011)
Collins v. Walker
341 S.W.3d 570 (Court of Appeals of Texas, 2011)
Tariq Majeed v. Sajjad Hussain
Court of Appeals of Texas, 2010
City of Grey Forest v. Vernon
254 S.W.3d 548 (Court of Appeals of Texas, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
857 S.W.2d 602, 1993 WL 82707, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sipco-services-marine-inc-v-wyatt-field-service-co-texapp-1993.