P. McGregor Enterprises, Inc. v. Hicks Construction Group, LLC

420 S.W.3d 45, 2012 WL 28538, 2012 Tex. App. LEXIS 87
CourtCourt of Appeals of Texas
DecidedJanuary 5, 2012
DocketNo. 07-11-00012-CV
StatusPublished
Cited by6 cases

This text of 420 S.W.3d 45 (P. McGregor Enterprises, Inc. v. Hicks Construction Group, LLC) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
P. McGregor Enterprises, Inc. v. Hicks Construction Group, LLC, 420 S.W.3d 45, 2012 WL 28538, 2012 Tex. App. LEXIS 87 (Tex. Ct. App. 2012).

Opinion

OPINION

MACKEY K. HANCOCK, Justice.

Appellant, P. McGregor Enterprises, Inc. (McGregor), appeals the granting of a summary judgment in favor of appellees, David Nance and Denman Building Products, Ltd. (Nance and Denman), that ordered that McGregor take nothing against Nance and Denman. We will affirm.

Factual and Procedural Background

On April 5, 2001, McGregor entered into a “Standard Form of Agreement Between Owner and Construction Manager” with Hicks Construction Group, LLC (Hicks).3 This contract covered the building of an addition to the Ashmore Inn & Suites in Lubbock, Texas. In connection with this project, Hicks sought bids from subcontractors for a portion of the work involving the framing, drywall, exterior finishing and insulation system (EFIS), roof trusses, and roof decking. A bid was received from Martinez Acoustical Drywall for $413,600 on May 31, 2001. On June 14, 2001, Den-man submitted a bid that totaled $446,914, but excluded the 5/8ths inch plywood roof decking and excluded tape, bed, and texture of the drywall. Later that same day, Denman submitted a second bid that included the 5/8ths inch plywood roof decking but still excluded the tape, bed, and texture of the drywall. The second Den-man bid was for a total of $413,400. The second Denman bid also included a statement that “the availability for our men to stay at the Ashmore Inn and Suites is also considered in the above referenced bid.” Included in the second bid was the statement that:

The above referenced quotation is offered with the understanding and commitment that Denman Building Products will be the subcontractor for the above [48]*48referenced scope of work on the Amarillo project.

The second bid reflects that the sum of $12,800 was added to the bid for per diem expenses for the employees of Denman. Denman’s bid was accepted by Hicks, and a standard contract between the contractor, Hicks, and subcontractor, Denman, was signed on June 25, 2001. Denman commenced its work on the project and, during the construction, submitted change orders to Hicks. Issues arose between Hicks and McGregor that resulted in McGregor terminating Hicks on April 1, 2002. Denman completed its work on the Lubbock project and, on April 18, 2002, submitted a request for final payment to McGregor directly. McGregor paid the final invoice on or about May 14, 2002, as evidenced by a deposit slip showing the check to be deposited in Denman’s bank on that day.

McGregor filed the lawsuit concerning the addition to the Lubbock Ashmore Inn on December 2, 2003, by which it alleges causes of action against Denman in the nature of negligent construction, breach of contract, and civil conspiracy. The original petition also contained allegations against Denman regarding the Amarillo construction project. The Amarillo project was subject to an arbitration agreement and was subsequently arbitrated. The trial court confirmed the arbitrator’s award by an order filed on August 27, 2004. The Amarillo project lawsuit was severed from the matter before the Court. This Court subsequently upheld the arbitration award. P. McGregor Enters., Inc. v. Denman Bldg. Prods., Ltd., 279 S.W.3d 717 (Tex.App.-Amarillo 2007, pet. ref'd).4

After severance of the Amarillo portion of the lawsuit, Denman filed a no-evidence motion for summary judgment,5 to which McGregor filed a response. Denman then filed an amended motion for summary judgment which included a traditional motion for summary judgment6 as to some of McGregor’s claims and amended the no-evidence motion for summary judgment previously filed. Subsequently, Denman filed a supplemental motion for summary judgment which added an additional ground for no-evidence summary judgment and an additional ground for traditional summary judgment. On January 28, 2008, a final summary judgment was filed that ordered that McGregor take nothing by its claims against Denman. The summary judgment entered did not specify which of the various grounds put forth by Denman was relied upon by the court. McGregor is appealing the granting of the summary judgment.

McGregor’s brief basically contends that the trial court erred in granting a motion for summary judgment upon any of the grounds alleged in the motions. Accordingly, we will review all of the theories put forth by Denman. See W. Invs., Inc. v. Urena, 162 S.W.3d 547, 550 (Tex.2005) (“Because the trial court’s order granting summary judgment does not specify the basis for the ruling, we must affirm the trial court’s judgment if any of the theories advanced are meritorious.”).

Standard of Review

We review the granting of a summary judgment, either traditional or no evidence, de novo. See D.R. Horton-Texas, Ltd. v. Market Int’l Ins. Co., 300 S.W.3d 740, 743 (Tex.2009). We review the evi[49]*49dence in the light most favorable to the non-movant and resolve all doubt and indulge every reasonable inference against movants. See Provident Life & Accident Ins. Co. v. Knott, 128 S.W.3d 211, 215 (Tex.2003).

The party moving for a traditional summary judgment has the burden of conclusively establishing the absence of any genuine issue of material fact and that it is entitled to judgment as a matter of law. Tex.R. Civ. P. 166a(c);7 Browning v. Prostok, 165 S.W.3d 336, 344 (Tex.2005). A defendant’s motion for summary judgment should be granted if the defendant disproves at least one essential element of the plaintiffs causes of action. See Little v. Tex. Dep’t of Criminal Justice, 148 S.W.3d 374, 381 (Tex.2004). Further, if the summary judgment evidence establishes all elements of an affirmative defense as a matter of law, then summary judgment for the defendant is proper. See Shah v. Moss, 67 S.W.3d 836, 842 (Tex.2001).

In order to prevail on a no-evidence motion for summary judgment, the movant must establish that there is no evidence of one or more essential elements of the claim or claims that the non-movant has the burden to prove at trial. Rule 166a(i). A no-evidence motion for summary judgment will be sustained when 1) there is complete absence of evidence of a vital fact, 2) the court is barred by rules of law or evidence from giving weight to the only evidence offered to prove an essential element of the claim, 3) the evidence offered to prove a vital fact is no more than a mere scintilla, or 4) the evidence conclusively establishes the opposite of the vital fact. King Ranch, Inc. v. Chapman, 118 S.W.3d 742, 751 (Tex.2003). Once the no-evidence motion for summary judgment is filed, the non-movant must then present more than a scintilla of probative evidence to raise a genuine issue of material fact. See Forbes Inc. v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
420 S.W.3d 45, 2012 WL 28538, 2012 Tex. App. LEXIS 87, Counsel Stack Legal Research, https://law.counselstack.com/opinion/p-mcgregor-enterprises-inc-v-hicks-construction-group-llc-texapp-2012.