P. McGregor Enterprises, Inc. v. Denman Building Products, Ltd.

279 S.W.3d 717, 2007 WL 1201545
CourtCourt of Appeals of Texas
DecidedMay 25, 2007
Docket07-05-0385-CV
StatusPublished
Cited by12 cases

This text of 279 S.W.3d 717 (P. McGregor Enterprises, Inc. v. Denman Building Products, Ltd.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
P. McGregor Enterprises, Inc. v. Denman Building Products, Ltd., 279 S.W.3d 717, 2007 WL 1201545 (Tex. Ct. App. 2007).

Opinion

OPINION

JAMES T. CAMPBELL, Justice.

Appellants, P. McGregor Enterprises, Inc. and Inn II, Ltd., appeal a judgment confirming an arbitration award against them in a dispute over a commercial construction project. We modify the trial court’s judgment and affirm the judgment as modified.

The facts surrounding the two construction projects giving rise to this litigation are complicated and we recite only those facts pertinent to the appeal. Paul McGregor is the owner of P. McGregor Enterprises, Inc. (PME). His wife Angela controls Inns, Inc., the general partner of the Inn II limited partnership (Inn II). Inn II contracted with PME for construction of a hotel on property it owned in Amarillo. PME made a contract with Hicks Construction Group 1 (Hicks), which subcontracted with Denman Building Products, Ltd. for a substantial part of the materials and labor. PME had an existing relationship with Hicks based on another construction project at a hotel in Lubbock. Denman was also a subcontractor on that project. PME terminated the contract with Hicks on both projects and contracted directly with Denman to complete construction of the Amarillo hotel. The PME-Denman contract 2 contained an arbitration clause.

Asserting Denman, Hicks and others had engaged in conduct which inflated the cost of the project, PME refused to pay a portion of the contract price. Hicks, Den-man and other subcontractors filed liens against the Amarillo property. Denman made a demand for arbitration in November 2003 with the American Arbitration Association. The demand named PME, Paul and Angela McGregor individually, and Inn II as respondents. Denman’s demand included its claim for unpaid amounts under the construction contract of some $350,000, and its request for foreclosure of its lien.

The following week PME filed suit against Hicks and other defendants including Denman. 3 The petition asserted *720 claims for breach of contract, civil conspiracy and negligence arising out of both the Lubbock and Amarillo construction projects. PME’s petition also sought removal of the cloud “placed on PME’s ownership of the property” by liens filed by Hicks, Nance, Denman and RSM Builders Supply-

Denman’s answer to PME’s petition included a motion to stay the suit and compel arbitration. It filed a brief in support stating it sought arbitration of its right to payment under its contract with PME, but made no mention of its lien on the property. The parties later filed an agreement pursuant to Rule of Civil Procedure 11 providing claims by PME against Denman and Nance, and claims by Denman against PME concerning the Amarillo project, would be resolved by arbitration while the claims concerning the Lubbock project would be resolved through litigation. The agreement made no reference to Inn II.

After the Rule 11 agreement was filed with the trial court, the respondents answered Denman’s arbitration demand. The response referred to the Rule 11 agreement, and stated that “pursuant to that agreement,” the “parties to this arbitration case are: Claimant Denman, Nance, and Respondents McGregor [PME], Paul and Angela McGregor and Inn II.” The response also included the statement, “This pleading is submitted without prejudice to Respondents’ ability to assert claims in the [trial court] that are not involved in this arbitration proceeding.”

The response included allegations that the lien Denman filed against the Amarillo property 4 was fraudulent, and filed in violation of section 12.002(a)(1) of the Texas Civil Practice & Remedies Code. Tex. Civ. Prac. & Rem.Code Ann. § 12.002(a)(1) (Vernon 2002). The response requested relief including a determination that the lien be removed and damages pursuant to section 12.002 against Nance and Denman. Shortly before the arbitration hearing counsel for appellants wrote to Denman’s counsel to question why Inn II and the McGregors were parties to the arbitration since they were not parties to the contract between PME and Denman. The letter acknowledged Denman “may have lien rights against Inn II” but stated that counsel was not aware of any claims against the McGregors individually, and sought “clarification” of the matter. We find no response to that letter in the record.

The parties participated in a two-day arbitration hearing in May 2004. Two attorneys appeared jointly on behalf of PME, the McGregors and Inn II. They voiced no jurisdictional objection when the arbitrator asked if there were any preliminary matters, but at the end of the opening statements, one attorney for the respondents stated:

Our request, and we’ve said this in our pleading, is that the individuals and the corporation, Inn II, who are not parties to the contract and who do not appear to face any personal or corporate responsibility for the contract allegations here, be dismissed from the arbitration proceeding. And I don’t know if now is the right time to urge that request....

The arbitrator concluded the request was “probably premature” and suggested he raise the issue at the close of Denman’s case.

In a post-hearing brief, appellants argued the arbitrator lacked jurisdiction over Inn II and the McGregors because they had not entered any arbitration *721 agreement. The remainder of the brief addressed the merits of the issues before the arbitrator and those arguments were made subject to the jurisdictional challenge. Denman argued any jurisdictional complaint had been waived by the failure to raise it in the initial response as required by rules of the American Arbitration Association.

The arbitrator’s award found PME ha-ble to Denman for the outstanding contract balance of $856,906.24, and $17,228.30 in pre-judgment interest. It awarded Denman attorneys fees of $40,605.55 against PME and declared Denman’s hen against the Amarillo property was perfected in the amount of the outstanding contract liability. The award directed PME to pay the arbitration expenses of $17,639.18. 5

Denman sought confirmation of the award and, after service of process on Inn II and denial of its challenge to the join-der, the trial court rendered an order confirming the award. The order also denied the jurisdictional challenge of Inn II and the McGregors and severed confirmation of the award and all other arbitration issues to a new cause number. After a hearing the trial court overruled appellants’ motion to vacate the award. In August 2005, the court rendered another order, titled final judgment, which recited confirmation of the arbitration award, added $27,104.49 in interest for the period between the arbitration award and July 11, 2005 and $16,150.00 in attorneys fees through the judgment with additional amounts on appeal. Those amounts were awarded against PME only. The judgment separately recognized Denman’s lien “securing all sums awarded in this judgment” against the Amarillo property owned by Inn II. It directed sale of the property to satisfy the debt.

The trial court made findings of fact and conclusions of law in support of its judgment.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
279 S.W.3d 717, 2007 WL 1201545, Counsel Stack Legal Research, https://law.counselstack.com/opinion/p-mcgregor-enterprises-inc-v-denman-building-products-ltd-texapp-2007.