Heritage Constructors, Inc. v. Chrietzberg Electric, Inc., and Richard Marc Chrietzberg

Court of Appeals of Texas·Decided March 4, 2015·No. 06-14-00048-CV·Published

Opinion

In The

Court of Appeals

Sixth Appellate District of Texas at Texarkana

No. 06-14-00048-CV

HERITAGE CONSTRUCTORS, INC., Appellant V.

CHRIETZBERG ELECTRIC, INC., AND RICHARD MARC CHRIETZBERG, Appellees

On Appeal from the 202nd District Court Bowie County, Texas

Trial Court No. 12C0591-202

Before Morriss, C.J., Moseley and Carter*, JJ.

Memorandum Opinion by Chief Justice Morriss

*Jack Carter, Justice, Retired, Sitting by Assignment

MEMORANDUM OPINION

The deadline was looming for aspiring prime contractors to submit their bids to

TexAmericas Center to build a wastewater treatment plant on its property in Bowie County. The subcontract bid of Chrietzberg Electric, Inc. (Electric) submitted at the last minute by Richard Marc Chrietzberg (Chrietzberg) to aspiring prime contractor Heritage Constructors, Inc. (Heritage), for the electrical portion of that treatment plant never once mentioned Heritage’s name. After Heritage was named the prime contractor for the project, Electric withdrew its subcontract bid, requiring Heritage to use the next lowest subcontract bidder and resulting in this lawsuit, which was submitted to a Bowie County jury. Few of the parties were entirely happy with the result of that trial. 1 On appeal, 2 we affirm the take-nothing judgment favoring Chrietzberg and the denial of Heritage’s claims for negligent misrepresentation, but reverse the judgment favoring Heritage and render a take-nothing judgment, because (1) the statute of frauds bars Heritage’s claim for breach of contract, (2) there is no evidence of damages recoverable based on promissory estoppel, (3) denying Heritage’s claims for negligent misrepresentation was proper, and (4) Heritage’s recovery of attorney fees also fails.

1 Based on a jury verdict and its own findings, the trial court entered judgment in favor of Heritage against Electric in the amount of $50,000.00, attorney fees through trial of $58,041.00, and costs and interest. Earlier, the trial court had entered judgment in favor of Chrietzberg, individually, on all claims asserted against him, also based on the jury’s verdict. 2 Heritage’s appeal challenges the sufficiency of the evidence supporting the amount of damages and attorney fees found and awarded and the judgment in favor of Chrietzberg. Electric challenges the legal sufficiency of the evidence supporting the award of damages based on contract and promissory estoppel and the award of attorney fees in favor of Heritage.

Heritage is a general contractor that specializes in the construction of water and wastewater treatment plants. In October 2011, Heritage was preparing a bid in an effort to become general contractor for the TexAmericas Center-East wastewater treatment plant improvement project (the Project) in Bowie County, Texas. The Project was contemplated to take nineteen months, with a projected start date of December 31, 2011, and a completion date of July 31, 2013. Although Heritage would perform eighty to eighty-five percent of the Project itself, certain aspects of the Project, including the electrical work, necessitated the use of subcontractors. TexAmericas required all bids from potential general contractors to be submitted no later than 2:00 p.m. on October 20, 2011. On that day, Carl Smith, Heritage’s vice president, was in his office receiving last minute bids and revised bids from suppliers and subcontractors. The pricing was fluctuating, and Heritage’s initial bid calculation was revised by as much as one million dollars within the last thirty minutes before the deadline. Meanwhile, Dennis Smith, Heritage’s president, was in the TexAmericas parking lot waiting for Carl to telephone him with the final bid numbers so he could hand deliver the bid by the deadline. Earlier that day, Carl had received a telephone bid from Electrique Corporation in the amount of $886,400.00 to perform the electrical work on the Project. Ten minutes before the deadline, Carl received a faxed bid from Electric, quoting $704,857.00 3 to perform the electrical work on the Project, but excluding any and all concrete work. After reviewing the bid, Carl had his assistant call Electric at 1:53 p.m. to confirm that the bid included all of the electric work in the Project plans. After confirming the bid, Carl reviewed Electric’s bid again and realized the bid did not include money

3 Electric’s base bid was $707,857.00, but provided for a deduction from the base bid of $3,000.00.

to bond the job. He then had his assistant call Electric again at 1:59 p.m., to obtain its bond rates. Once he was confident that Electric could bond his bid, Carl decided to use Electric’s bid in Heritage’s final bid to TexAmericas. He conveyed the final calculations to Dennis so Dennis could finalize the bid and submit it to TexAmericas. 4 Shortly thereafter, the project engineer notified Carl that Heritage was the low bidder for the Project. He also told him the Project was above the owner’s budget and that he wanted to work with Heritage on value engineering 5 ideas to help get the project cost down. Carl then called Chrietzberg to let him know that Heritage was the low bidder and that, if Heritage got the job, so would Electric. He also asked Chrietzberg to provide him with some value engineering ideas on the electrical work. Heritage worked with Electric over the next week on value engineering and also asked Electric to give it a price for the duct bank concrete work, which had been excluded from Electric’s bid. Electric gave Heritage a quote of $68,575.00 to perform all duct bank concrete work, including all labor and materials. 6 Heritage thought this was excessive and decided to do the concrete work itself. On January 24, 2012, the TexAmericas board of directors approved awarding the Project to Heritage, and Heritage emailed Electric to notify it of the award. In the email, Heritage stated, “Look forward to working with you on this project.” Electric responded, “Thank you, Carl. Same here.”

4 The second page of Heritage’s final bid for item 1 (“For construction of all improvements at the TexAmericas Center East Wastewater Treatment Plant site except as listed below, complete as shown on the Plans and specified herein (except for all seal slabs and sidewalks shown) for a total lump sum amount of”) shows a strike-through change from “$5,636,500” to “5,536,500.” There was no testimony explaining this strike-through change. 5 Value engineering attempts to provide the same functionality at a lower cost.

6 Electrique Corporation’s bid included performing all concrete work.

On February 3, after receiving an executed contract from TexAmericas, Heritage sent Electric a proposed subcontract for the electrical work on the Project. The subcontract terms did not exclude the duct bank concrete work from the description of the work required of Electric and did not include an amount to pay for the duct bank concrete work or to reimburse Electric for its bond. 7 When Carl called Chrietzberg to let him know the subcontract was on its way, Chrietzberg asked Carl about the difference between Electric’s bid and the next lowest bid. Carl compared the two bids, adjusted for the duct bank concrete work, called Chrietzberg back, and told him the difference was about $90,000.00–100,000.00. On February 7, Electric notified Heritage that it was withdrawing its bid. That afternoon, Dennis called Electric to ask it to reconsider, which Electric refused to do. Heritage then contacted Electrique Corporation, the next lowest electrical bidder, and entered into a subcontract on March 2 with it to perform all of the electrical work on the Project for $886,400.00. Electrique Corporation’s acceptance of the subcontract was conditioned on Heritage accepting certain revisions to the subcontract.

Free access — add to your briefcase to read the full text and ask questions with AI

Heritage Constructors, Inc. v. Chrietzberg Electric, Inc., and Richard Marc Chrietzberg, (Tex. Ct. App. 2015).

Heritage Constructors, Inc. v. Chrietzberg Electric, Inc., and Richard Marc Chrietzberg (Heritage Constructors, Inc. v. Chrietzberg Electric, Inc., and Richard Marc Chrietzberg) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Mustang Pipeline Co. v. Driver Pipeline Co.
134 S.W.3d 195 (Texas Supreme Court, 2004)
Baylor University v. Sonnichsen
221 S.W.3d 632 (Texas Supreme Court, 2007)
Haase v. Glazner
62 S.W.3d 795 (Texas Supreme Court, 2002)
1001 McKinney Ltd. v. Credit Suisse First Boston Mortgage Capital
192 S.W.3d 20 (Court of Appeals of Texas, 2006)
Doctors Hospital 1997, L.P. v. Sambuca Houston, L.P.
154 S.W.3d 634 (Court of Appeals of Texas, 2005)
Justice v. State Farm Lloyds Insurance Co.
246 S.W.3d 762 (Court of Appeals of Texas, 2008)
Barrand, Inc. v. Whataburger, Inc.
214 S.W.3d 122 (Court of Appeals of Texas, 2006)
Plano Surgery Center v. New You Weight Management Center
265 S.W.3d 496 (Court of Appeals of Texas, 2008)
Dixon v. Amoco Production, Co.
150 S.W.3d 191 (Court of Appeals of Texas, 2004)
Frost National Bank v. Burge
29 S.W.3d 580 (Court of Appeals of Texas, 2000)
In Re the Estate of Boren
268 S.W.3d 841 (Court of Appeals of Texas, 2008)
Cecil v. Smith
804 S.W.2d 509 (Texas Supreme Court, 1991)
Nagle v. Nagle
633 S.W.2d 796 (Texas Supreme Court, 1982)
Traco, Inc. v. Arrow Glass Co., Inc.
814 S.W.2d 186 (Court of Appeals of Texas, 1991)
FORECA, SA v. GRD Development Co., Inc.
758 S.W.2d 744 (Texas Supreme Court, 1988)
Weitzel v. Barnes
691 S.W.2d 598 (Texas Supreme Court, 1985)
Owen v. Hendricks
433 S.W.2d 164 (Texas Supreme Court, 1968)
Walker v. Tafralian
107 S.W.3d 665 (Court of Appeals of Texas, 2003)
Niday v. Niday
643 S.W.2d 919 (Texas Supreme Court, 1982)