Frohberg Elec. Co. v. Grossenburg Implement

297 Neb. 356, 900 N.W.2d 32
Nebraska Supreme Court·Decided July 28, 2017·No. S-16-987·Published·Cited by 8 cases

Opinion

Nebraska Supreme Court Online Library www.nebraska.gov/apps-courts-epub/ 10/20/2017 09:13 AM CDT

- 356 -

Nebraska Supreme Court A dvance Sheets 297 Nebraska R eports

FROHBERG ELEC. CO. v. GROSSENBURG IMPLEMENT Cite as 297 Neb. 356

Frohberg Electric Company, Inc., a Nebraska corporation, appellee, v. Grossenburg I mplement, I nc., a Nebraska corporation, and K iehm Construction, I nc., a M innesota corporation, appellants.

___ N.W.2d ___

Filed July 28, 2017. No. S-16-987.

1. Contracts. The meaning of a contract and whether a contract is ambiguous are questions of law.

2. Arbitration and Award. Arbitrability presents a question of law. 3. Judgments: Appeal and Error. When reviewing questions of law, an appellate court resolves the questions independently of the lower court’s conclusions.

4. Arbitration and Award: Contracts: Appeal and Error. Where an issue concerns the formation or existence of an arbitration agreement and not its validity, enforceability, or scope, an appellate court applies state law.

5. Arbitration and Award: Federal Acts: Contracts. The Federal Arbitration Act’s application is triggered only if a contract involving interstate commerce actually contains an arbitration clause.

6. Arbitration and Award: Federal Acts: Contracts: States. In a contract involving interstate commerce, the equal-treatment principle of the Federal Arbitration Act applies in determining whether a valid arbitration agreement exists: States may not apply a state rule discriminating against arbitration and are required to place arbitration agreements on equal footing with all other contracts.

7. Contracts. In interpreting a contract, a court must first determine, as a matter of law, whether the contract is ambiguous.

8. ____. A contract written in clear and unambiguous language is not subject to interpretation or construction and must be enforced according to its terms.

9. Contracts: Words and Phrases. A contract is ambiguous when a word, phrase, or provision in the contract has, or is susceptible of, at least two reasonable but conflicting interpretations or meanings.

Nebraska Supreme Court A dvance Sheets 297 Nebraska R eports

FROHBERG ELEC. CO. v. GROSSENBURG IMPLEMENT Cite as 297 Neb. 356

10. Arbitration and Award: Federal Acts: Contracts. If a contract containing an arbitration clause involves interstate commerce, the Federal Arbitration Act governs the contract.

11. Contracts: States: Words and Phrases. Contracts involving interstate commerce include contracts for services between parties of different states.

12. Appeal and Error. An appellate court is not obligated to engage in an analysis that is not necessary to adjudicate the case and controversy before it.

Appeal from the District Court for Wayne County: James G. Kube, Judge. Reversed and remanded with directions.

Timothy Engler, of Rembolt Ludtke, L.L.P., for appellants.

David E. Copple and Michelle M. Schlecht, of Copple, Rockey, McKeever & Schlecht, P.C., L.L.O., for appellee.

Heavican, C.J., Wright, Miller-Lerman, Cassel, Stacy, K elch, and Funke, JJ.

Cassel, J.

INTRODUCTION

This is an appeal from an order denying a motion to compel arbitration of a construction dispute. A subcontractor sued the project’s owner and general contractor, which in turn sought to compel arbitration. The appeal turns on whether the subcontract effectively incorporated a mandatory arbitration clause from the general contract, thereby mandating the subcontractor to arbitrate. Because we conclude that it did, we reverse, and remand with directions.

BACKGROUND Parties and Governing

Contracts

Grossenburg Implement, Inc. (Owner), a Nebraska corporation , executed a standard form contract (the general

Nebraska Supreme Court A dvance Sheets 297 Nebraska R eports

FROHBERG ELEC. CO. v. GROSSENBURG IMPLEMENT Cite as 297 Neb. 356

contract) with Kiehm Construction, Inc. (Contractor), a Minnesota corporation, for the construction of several structures on Owner’s property in Wayne County, Nebraska. The general contract included a mandatory arbitration clause for “any Claim . . . not resolved by mediation pursuant to [the general conditions].”

Contractor then subcontracted with Frohberg Electric Company, Inc. (Subcontractor), a Nebraska corporation, to provide electrical services and materials in constructing the structures. The subcontract referenced the existence of the general contract and stated, “Contractor has made available to . . . Subcontractor all of the above documents, and . . . the above have been carefully examined by . . . Subcontractor.”

The general contract was also referenced in several sections of the subcontract, including one (Section 11) in which Subcontractor agreed “[t]o be bound to . . . Contractor by the terms of the General Contract” and “to conform to and to comply with the provisions of the General Contract.” Another section (Section E), under the heading “The Contractor Agrees as Follows,” provided: “If arbitration of disputes is provided for in the General Contract, any dispute arising between . . . Contractor and . . . Subcontractor under this Subcontract, including the breach thereof, shall be settled by arbitration in the manner provided for in the General Contract.”

Lower Court Proceedings

After Subcontractor provided services pursuant to the subcontract , a dispute arose concerning the payment owed to Subcontractor. Subcontractor then obtained a construction lien against Owner’s property and later filed a complaint against Owner and Contractor to obtain a judgment and foreclose on the construction lien.

Owner and Contractor jointly moved to dismiss the complaint or, in the alternative, to compel arbitration pursuant to the terms of the subcontract and the general contract. They

Nebraska Supreme Court A dvance Sheets 297 Nebraska R eports

FROHBERG ELEC. CO. v. GROSSENBURG IMPLEMENT Cite as 297 Neb. 356

alleged that the subcontract included specific provisions in Section 11 and Section E which incorporated the alternative dispute resolution clauses from the general contract and general conditions signed by Owner and Contractor. Thus, they argued that the matter should be settled by arbitration as provided in those documents.

The district court overruled the motion and specifically held that the terms of the subcontract did not bind Subcontractor to the dispute resolution provisions of the general contract or general conditions. The court noted that the only provision specifically purporting to bind the parties to alternative dispute resolution was under the subcontract section titled “The Contractor Agrees as Follows” and not contained within the other sections, “The Subcontractor Agrees as Follows” or “The Contractors and Subcontractors Agree as Follows.” Accordingly, the court found that Subcontractor did not agree to that provision by the express terms of the subcontract.

The court also found that the provision of Section 11 in which Subcontractor agreed “[t]o be bound to . . . Contractor by the terms of the General Contract” was vague as to whether it applied to disputes between Subcontractor and Owner or between Subcontractor and Contractor. Since the general contract spoke only to disputes between Owner and Contractor, the court found that the general contract language was inconsistent with the subcontract and that the language of the subcontract should govern. Because it had already determined that the express terms of the subcontract did not bind Subcontractor to the dispute resolution process within the general contract, the court concluded that there was no arbitration agreement.

Owner and Contractor appealed, and we moved the case to our docket.1

1 See Neb. Rev. Stat. § 24-1106(3) (Reissue 2016).

Nebraska Supreme Court A dvance Sheets 297 Nebraska R eports

FROHBERG ELEC. CO. v. GROSSENBURG IMPLEMENT Cite as 297 Neb. 356

ASSIGNMENTS OF ERROR

Free access — add to your briefcase to read the full text and ask questions with AI

Frohberg Elec. Co. v. Grossenburg Implement, 297 Neb. 356, 900 N.W.2d 32 (Neb. 2017).

297 Neb. 356 (Frohberg Elec. Co. v. Grossenburg Implement) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Gross v. GIKK Investments
34 Neb. Ct. App. 34 (Nebraska Court of Appeals, 2026)
EAD Engr. v. Purac America
34 Neb. 24 (Nebraska Court of Appeals, 2026)
Ray Anderson, Inc. v. Buck's, Inc.
300 Neb. 434 (Nebraska Supreme Court, 2018)
Cullinane v. Beverly Enters.-Neb., Inc.
300 Neb. 210 (Nebraska Supreme Court, 2018)
Cullinane v. Beverly Enters. - Neb.
300 Neb. 210 (Nebraska Supreme Court, 2018)
Baumgart v. O'Sullivan (In Re Estate of Karmazin)
299 Neb. 315 (Nebraska Supreme Court, 2018)
In re Estate of Karmazin
299 Neb. 315 (Nebraska Supreme Court, 2018)
Estates at Prairie Ridge Homeowners Assn. v. Korth
298 Neb. 266 (Nebraska Supreme Court, 2017)