EAD Engr. v. Purac America

34 Neb. 24, 34 Neb. Ct. App. 24
CourtNebraska Court of Appeals
DecidedJanuary 27, 2026
DocketA-25-080
StatusPublished
Cited by1 cases

This text of 34 Neb. 24 (EAD Engr. v. Purac America) is published on Counsel Stack Legal Research, covering Nebraska Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
EAD Engr. v. Purac America, 34 Neb. 24, 34 Neb. Ct. App. 24 (Neb. Ct. App. 2026).

Opinion

Nebraska Supreme Court Online Library www.nebraska.gov/apps-courts-epub/ 01/27/2026 08:14 AM CST

- 24 - Nebraska Court of Appeals Advance Sheets 34 Nebraska Appellate Reports EAD ENGR. V. PURAC AMERICA Cite as 34 Neb. App. 24

EAD Engineering, Inc., appellant, v. Purac America Inc., doing business as Corbion, appellee. ___ N.W.3d ___

Filed January 27, 2026. No. A-25-080.

1. Contracts. The meaning of a contract is a question of law. 2. Arbitration and Award. Arbitrability presents a question of law. 3. Judgments: Appeal and Error. When reviewing questions of law, an appellate court resolves the questions independently of the lower court’s conclusions. 4. Arbitration and Award: Contracts. Arbitration is a matter of contract, and a party cannot be required to submit to arbitration any dispute which he or she has not agreed to submit. 5. Constitutional Law: Waiver: Intent. A party has a constitutional right to adjudication of a justiciable dispute, and the law will not find a waiver of that right absent direct and explicit evidence of actual intent of a party’s agreement to do so. 6. Assignments: Words and Phrases. An assignment is the transfer of some identifiable property, claim, or right from the assignor to the assignee. 7. Contracts: Assignments. An assignee stands in the shoes of the assignor and is bound by the terms of the contract to the same extent as the assignor. 8. Appeal and Error. In order to preserve each party’s right to meaningful appellate review of issues presented to but not decided by the district court, an appellate court will decline to decide such issues in the first instance. Instead, it will remand to the district court with directions to consider and decide these alternative issues.

Appeal from the District Court for Washington County: Zachary L. Blackman, Judge. Reversed and remanded for further proceedings. - 25 - Nebraska Court of Appeals Advance Sheets 34 Nebraska Appellate Reports EAD ENGR. V. PURAC AMERICA Cite as 34 Neb. App. 24

Todd W. Weidemann, Bruce A. Smith, and Lexi A. Weisbeck, of Woods Aitken, L.L.P., for appellant. Julie E. Parisi, Christopher Tillery, and Gregory S. Gerstner, pro hac vice, and Timothy J. Davis of Seigfreid Bingham, P.C., and Michael T. Gibbons, of Woodke & Gibbons, P.C., L.L.O., for appellee. Riedmann, Chief Judge, and Moore and Bishop, Judges. Riedmann, Chief Judge. INTRODUCTION EAD Engineering, Inc. (Engineering), appeals from the order of the district court for Washington County compelling Engineering to arbitrate with Purac America Inc., doing busi- ness as Corbion (Corbion). For the reasons outlined below, we reverse the order of the district court and remand the cause for further proceedings as directed in this opinion. BACKGROUND In October 2020, Corbion and Engineering entered into an “Engineering Services Agreement” (ESA). Engineering is a subsidiary of Engineering Automation & Design, Inc. EAD Constructors, Inc. (Constructors) is also a subsidiary. Stephen Lichter is the chief executive officer of Engineering Automation & Design, Engineering, and Constructors. Lichter signed the ESA on behalf of Engineering. The ESA specified that in the agreement, Engineering was referred to as “Service Provider,” and that both Corbion and “Service Provider” were referred to in the agreement separately as a “Party” and collectively as the “Parties.” It contained a provi- sion providing for judicial determination of disputes. It stated that the [a]greement and any dispute arising hereunder will be interpreted and governed by the Laws of the state of the State of Kansas, U.S.A., excluding its conflict of law rules. The state and federal courts located in Johnson - 26 - Nebraska Court of Appeals Advance Sheets 34 Nebraska Appellate Reports EAD ENGR. V. PURAC AMERICA Cite as 34 Neb. App. 24

County, Kansas will have exclusive jurisdiction for any litigation or other proceeding arising out of or relating to the [a]greement. On May 28, 2021, Corbion and Constructors signed an “Engineering, Procurement and Construction Agreement” (EPCA). The EPCA did not define the parties to the agree- ment, but stated it was entered into between “Purac America, Inc., (‘Owner’)” and “EAD Constructors Inc. (‘Contractor’).” Despite “Parties” being an undefined term, the second para- graph of the scope of work provision in the EPCA provided: The Parties acknowledge that, prior to the execution of this Agreement, the Parties entered into a separate [ESA], dated October 13, 2020[,] between . . . Corbion and . . . Engineering . . . , which pertained to many of the engi- neering services to be provided for the Project . . . . For purposes of the present Agreement, and upon the execu- tion of this Agreement, it is understood and agreed that all services, rights and obligations by and between the Parties under the [ESA] are hereby incorporated herein by this reference and merged into the present Agreement so that the present Agreement is understood to provide for all services to be provided and furnished by Contractor as one [EPCA]. The EPCA provided that the method of dispute resolution would be binding arbitration. Another provision in the EPCA recognized that “[t]he Parties acknowledge that the dispute provisions between the two agreements conflict. The Parties agree that the dispute provisions in this EPC Agreement and the General Conditions shall govern and control.” Lichter signed the EPCA on behalf of Constructors. There was no signature line for Engineering. That same day, Engineering, as assignor, and Constructors, as assignee, entered into an “Assignment and Assumption” agreement (the Assignment). The Assignment set forth Engineering’s and Constructor’s respective obligations. It stated in part: - 27 - Nebraska Court of Appeals Advance Sheets 34 Nebraska Appellate Reports EAD ENGR. V. PURAC AMERICA Cite as 34 Neb. App. 24

(1) Assignment. Effective as of the date of the EPC[A], Assignor hereby grants, conveys, assigns, and transfers to Assignee, its successors and assigns, any and all right, title and interest of Assignor, in and to the [ESA]. (2) Acceptance and Assumption. Effective as of the date of the EPC[A], Assignee hereby accepts and agrees to perform all of the terms, covenants and conditions of the [ESA] required to be performed by Assignor from and after the date of the EPC[A]. Lichter signed the Assignment agreement twice—once on behalf of Engineering, and again on behalf of Constructors. In 2023, a dispute arose between Corbion and Constructors. Pursuant to the EPCA, Corbion filed a request for medi- ation and demand for arbitration against Constructors. Following an unsuccessful mediation between the two, the issue of joining Engineering was raised. In an amended complaint and application to stay arbitration proceedings filed by Engineering in January 2024, Engineering alleged that Corbion served Constructors with a demand for arbitra- tion and later served Engineering with a similar demand. It sought a stay of the arbitration proceedings as to Engineering because Engineering was not a party or signatory to the EPCA. In September, Corbion filed an application to compel Engineering to arbitrate on the basis that a valid arbitra- tion agreement existed between them in the EPCA and that Engineering had refused to arbitrate. Corbion asserted that the ESA between Corbion and Engineering was incorporated into the EPCA and that the dispute resolution provisions in the EPCA controlled. Engineering resisted the application to arbitrate, again asserting it was neither a signatory nor a party to the EPCA. The district court found that a valid arbitration agreement existed between Corbion and Engineering. It determined that Engineering had assigned its rights under the ESA to Constructors, which signed the EPCA, which incorpo- rated the ESA into it.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gross v. GIKK Investments
34 Neb. Ct. App. 34 (Nebraska Court of Appeals, 2026)

Cite This Page — Counsel Stack

Bluebook (online)
34 Neb. 24, 34 Neb. Ct. App. 24, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ead-engr-v-purac-america-nebctapp-2026.