Friends of Outlet Creek v. Mendocino County Air Quality Management District

11 Cal. App. 5th 1235, 218 Cal. Rptr. 3d 212, 2017 Cal. App. LEXIS 481
CourtCalifornia Court of Appeal
DecidedMarch 23, 2017
DocketNo. A148508
StatusPublished
Cited by4 cases

This text of 11 Cal. App. 5th 1235 (Friends of Outlet Creek v. Mendocino County Air Quality Management District) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Friends of Outlet Creek v. Mendocino County Air Quality Management District, 11 Cal. App. 5th 1235, 218 Cal. Rptr. 3d 212, 2017 Cal. App. LEXIS 481 (Cal. Ct. App. 2017).

Opinion

Opinion

BANKE,

This is one of several lawsuits Friends of Outlet Creek (Friends) is pursuing in an effort to prevent asphalt production at the site of an aggregate operation. The Mendocino County Air Quality Management District (District) and Grist Creek Aggregates, LLC (Grist Creek), successfully demurred on the ground Friends can only proceed against the District in an administrative mandamus proceeding under Health and Safety Code section 40864, which the District and Grist Creek contend cannot embrace a challenge under the California Environmental Quality Act (CEQA; Pub. Resources Code, § 21000 et seq.). Friends, in turn, has expressly disclaimed any reliance on Health and Safety Code section 40864 and asserts it can sue the District directly under CEQA. The trial court sustained the District and Grist Creek’s demurrer, and dismissed the action.

We reverse, as there is established precedent allowing CEQA claims against air quality management districts. However, that does not mean Friends can challenge any land use designations or authorizations pertaining [1238]*1238to the site that have been made by the County of Mendocino (County). The only action taken by the District (a separate and independent governmental agency) in connection with the land use dispute here, is an assessment of the proposed asphalt production’s impact on air quality and issuance of an “Authority to Construct”—and that is the only action Friends can challenge in this lawsuit. Further, even under CEQA, this is an administrative mandamus proceeding governed by Code of Civil Procedure section 1094.5. Accordingly, the only relief Friends can obtain through this lawsuit against the District is invalidation of the Authority to Construct.

Background

Since 1972, the County has granted land use approvals for aggregate and asphalt production on the site at issue.1 The County approved one such use permit in 2002, and in doing so, conducted environmental review under CEQA. The County ultimately issued a mitigated negative declaration.2

Seven years later, in 2009, the County updated its general plan, changing the land use designation of the site from rangeland to industrial. In doing so, the County proceeded under CEQA and prepared an environmental impact report (EIR). The following year, in 2010, the County, consistent with its updated general plan, rezoned 61 parcels, including the site at issue, to conform to the updated use designations. In doing so, the County relied on its previously certified EIR. According to County planning staff the “approved zoning change thus allows, by right, industrial uses that were previously considered to be non-conforming and subject to discretionary land use entitlements.” There was no judicial challenge to either the general plan update or the rezoning.

After Grist Creek acquired the site, it applied to the County for development review of its proposed continuation and resumption of aggregate and asphalt production at the site. The County Planning and Building Services Department’s (Planning Department) staff report for the review stated there had been little asphalt production primarily due to market conditions and over the years much of the asphalt processing equipment had been removed. It further stated that due to environmental impacts that could result from asphalt [1239]*1239production, Grist Creek had opted to proceed for the time being only with an aggregate and concrete operation. The Planning Department undertook an initial environmental review under CEQA, and recommended issuance of a negative declaration subject to two dozen conditions in mitigation. The District was listed as a referral agency that had provided comments to the County.

In late 2014, the Planning Department and Grist Creek again discussed the production of asphalt, and in March 2015, the matter was presented directly to the County Board of Supervisors by way of an “Operational Statement” that asked the board to decide whether the proposed resumption of asphalt production at the site would be a “new or changed” industrial use under the County’s zoning ordinance.3 The public notice thus stated the matter to be considered was whether the “proposed resumption of the asphalt plant ... is not a new or changed use and may resume operation subject to the conditions” of the 2002 use permit.

The board, by way of a March 2015 resolution, declared the proposed use was neither a new, nor a changed, industrial use, and that it was a permitted use subject to the conditions of approval of the 2002 use permit (which were attached to the resolution). Three days later, the Planning Department issued a “Notice of Exemption” for the “[rjesumption of activity at the . . . aggregate processing plant,” specifying the County as the “Public Agency Approving Project,” checking a box that the “Exempt Status” was “Ministerial (§ 21080, (b)(1); 51268).” Friends promptly filed a lawsuit against the County challenging this resolution.

Having obtained approval of asphalt production from the County, Grist Creek applied to the District for an Authority to Construct.4 As part of the review, the District’s air pollution control officer issued a report stating, [1240]*1240among other things, that use of the site by two previous owners for “aggregate processing, concrete, as well as a hot mix asphalt plant and concrete batch plant, ... led to the determination by the lead Planning agency that a new [E]nvironmental Impact Review (EIR) was not required.” Without further discussion, the report concluded the proposed asphalt facility was “a project or a portion of a project for which another public agency has already acted as the lead agency in compliance with CEQA.” Given that determination, the air pollution control officer concluded no further environmental review by the District was required. The bulk of the report discussed emissions related to the proposed use and concluded the proposed use would “not result in a significant net increase in emissions of any air contaminant regulated under the Clean Air Act[5] Amendments of 1990 and as amended at the time of the application.” In June 2015, the officer issued an Authority to Construct.

Later in the same month, the County Board of Supervisors adopted a second resolution. Expressly stating it wished to avoid protracted and expensive litigation under CEQA, the board of supervisors rescinded its March 2015 resolution. The new, June 16, 2015, resolution also expressly stated it did not impact any land use entitlements or authorizations that existed in connection with the site prior to the March 2015 resolution. Friends then filed an amended pleading in its lawsuit against the County. The County, in turn, successfully demurred on the ground the lawsuit was moot, given that the March 2015 resolution Friends was challenging had been rescinded. Friends appealed, and that appeal (Friends of Outlet Creek v. County of Mendocino, supra, A147499) now rests with another division of this court.

In the meantime, a month after the District’s air pollution control officer approved an Authority to Construct, Friends, in July 2015, filed an administrative appeal to the District’s hearing board.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
11 Cal. App. 5th 1235, 218 Cal. Rptr. 3d 212, 2017 Cal. App. LEXIS 481, Counsel Stack Legal Research, https://law.counselstack.com/opinion/friends-of-outlet-creek-v-mendocino-county-air-quality-management-district-calctapp-2017.