Communities for a Better Environment v. Bay Area Air Quality Management District

1 Cal. App. 5th 715, 205 Cal. Rptr. 3d 12, 2016 Cal. App. LEXIS 596
CourtCalifornia Court of Appeal
DecidedJuly 19, 2016
DocketA143634
StatusPublished
Cited by9 cases

This text of 1 Cal. App. 5th 715 (Communities for a Better Environment v. Bay Area Air Quality Management District) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Communities for a Better Environment v. Bay Area Air Quality Management District, 1 Cal. App. 5th 715, 205 Cal. Rptr. 3d 12, 2016 Cal. App. LEXIS 596 (Cal. Ct. App. 2016).

Opinion

Opinion

HUMES, P. J.

Communities for a Better Environment, Asian Pacific Environmental Network, Sierra Club, and Natural Resources Defense Council (collectively, CBE) filed a petition for writ of mandate and a complaint under the California Environmental Quality Act (Pub. Resources Code, § 21000) (CEQA) after respondent Bay Area Air Quality Management District (BAAQMD) determined that its approval for a Richmond rail-to-truck facility to transload crude oil instead of ethanol was ‘'ministerial” and exempt from CEQA review. The trial court dismissed the petition and complaint without leave to amend, concluding that the suit was time-barred under Public Resources Code 1 section 21167, subdivision (d) (section 21167(d)).

The only issue on appeal is whether CBE can successfully amend its petition and complaint to allege that the action is timely by virtue of the discovery rule. In the typical case, the discovery rule postpones the accrual of an action from the date an injury occurs until the date the plaintiff has actual or constructive notice of the facts constituting the injury. CBE claims that it should be allowed to rely on the discovery rule here because it could not have learned about BAAQMD’s determination any earlier, as BAAQMD gave no “public notice” of it and “the project itself [was] hidden from the public eye.” But an action to challenge such a determination accrues not at the time of the determination but instead on one of three alternative dates set forth in section 21167(d), dates on which the the public is deemed to have constructive notice of the potential CEQA violation. The discovery rule has never been applied to postpone the accrual of an action beyond the date the plaintiff has constructive notice of an injury, and we decline to so apply it here. We therefore affirm.

*719 I.

Factual and Procedural Background

The relevant facts may be summarized briefly. 2 Respondent Kinder Morgan Material Services, LLC (Kinder Morgan), began operating an ethanol rail-to-truck transloading facility in Richmond around 2009. In February 2013, Kinder Morgan applied to BAAQMD for approval to alter the facility and begin transloading Bakken crude oil. According to CBE, Bakken crude oil is “highly volatile and explosive” and “[t]he range of significant adverse environmental impacts of Kinder Morgan’s operation includes a high risk to public health and safety from derailment, significant increases in toxic air contaminants, potential contamination of California’s precious waterways (that support entire ecosystems), and significant increases in greenhouse gas emissions.”

Upon determining that the project was “ministerial” and not subject to CEQA review, BAAQMD authorized Kinder Morgan to begin transloading crude oil by issuing a permit in July 2013 called an authority to construct. BAAQMD concedes that it did not issue an optional notice of exemption (NOE) that would have publicly announced its determination that the project was exempt from CEQA review. (See §§ 21152, subd. (b), 21167, subd. (d).) Kinder Morgan began transloading crude oil in mid-September 2013.

At Kinder Morgan’s request, BAAQMD later modified two conditions of the authority to construct: in October 2013, it modified the emissions-monitoring requirements, and in December 2013, it required that the crude oil be transloaded to a different type of tanker truck. In February 2014, BAAQMD issued Kinder Morgan a Permit to Operate that incorporated the modified conditions.

On March 27, 2014, CBE filed a petition for writ of mandate against BAAQMD and a complaint for declaratory and injunctive relief against BAAQMD, Kinder Morgan, and Kinder Morgan’s parent company, Kinder Morgan Energy Partners, L.P 3 CBE alleged that (1) BAAQMD’s approval of *720 the operational change at the transloading facility was not ministerial and (2) an environmental impact report (EIR) was required because there was a fair argument that the change would have a significant impact on the environment.

Respondents sought dismissal of the action as time-barred under section 21167(d) because it was filed more than 180 days after “the date of the public agency’s decision to carry out or approve the project”—the July 2013 issuance of the authority to construct. BAAQMD answered the petition for writ of mandate and complaint and moved for judgment under Code of Civil Procedure section 1094, which applies to a petition for peremptory writ of mandate that “presents no triable issue of fact or is based solely on an administrative record,” and the remaining respondents demurred to the complaint.

CBE opposed the motion for judgment and the demurrers. As relevant here, it argued that even if the July 2013 authority to construct would have otherwise triggered the statute of limitations, the trial court should apply the discovery rule to conclude that the limitations period did not begin to run until CBE “first became aware of Kinder Morgan’s operation” on January 31, 2014, when one of CBE’s staff members received an email disclosing that the Richmond facility had begun transloading crude oil. 4 CBE maintained that it did not learn, and could not with reasonable diligence have learned, of the project any earlier, because BAAQMD “gave the public no notice of Kinder Morgan’s switch to . . . Bakken crude oil” and “Kinder Morgan’s transload-ing operation is entirely enclosed, making the transported commodity, and any change to it, invisible.”

After a hearing, the trial court granted the motion for judgment and sustained the demurrers without leave to amend. The court first determined that CBE’s pleading was time-barred on its face because the July 2013 authority to construct triggered the statute of limitations despite the later changes in conditions. The court then turned to whether it should grant CBE leave to amend so it could “plead the facts ... it believes establish that it brought the claim within 180 days of discovering . . . what [it] believe [s] to have been the violations of CEQA.” The court concluded that “there is not a discovery escape provision or exception” to section 21167(d). It reasoned that the Legislature must have “contemplate [d] circumstances where the public wouldn’t know” about the decision to find a project exempt from CEQA, because the filing of an NOE is “entirely optional” and section 21167(d) is not limited to situations “where one by observation [can] tell that the [agency’s] approval has been given” or that a project has commenced. Thus, *721 the court found that CBE could not amend its pleading to avoid the statute of limitations by alleging that it was unaware of the project until January 2014.

II.

Discussion

A. General Legal Standards.

1. The applicable law under CEQA.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
1 Cal. App. 5th 715, 205 Cal. Rptr. 3d 12, 2016 Cal. App. LEXIS 596, Counsel Stack Legal Research, https://law.counselstack.com/opinion/communities-for-a-better-environment-v-bay-area-air-quality-management-calctapp-2016.