Francisco Munoz v. City of Union City

481 F. App'x 754
CourtCourt of Appeals for the Third Circuit
DecidedMay 11, 2012
Docket11-2149
StatusUnpublished
Cited by18 cases

This text of 481 F. App'x 754 (Francisco Munoz v. City of Union City) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Francisco Munoz v. City of Union City, 481 F. App'x 754 (3d Cir. 2012).

Opinion

OPINION

GREENAWAY, JR., Circuit Judge.

Francisco Munoz (“Munoz”) appeals the March 28, 2011 Order of the District Court denying his motion for partial summary judgment and granting summary judgment in favor of Union City, New Jersey; Union City Mayor Brian P. Stack; Union City Construction Code Official Martin Martinetti (collectively, “City Appellees”); and Nacirema Environmental Services, Inc. (together, “Appellees”). For the following reasons, we will affirm the District Court’s Order.

I. BACKGROUND

Because we write primarily for the benefit of the parties, we recount only the essential facts.

In the early morning hours of September 9, 2006, a fire was reported in a building located at 1813 Bergenline Avenue in Union City, New Jersey (the “Building”). The Building was a multi-family, three-story dwelling owned by Munoz. North Hudson Regional Fire and Rescue was the first firefighting company to respond to the call. Upon arrival, several firefighters entered the burning structure. As the intensity and breadth of the fire progressed, additional alarms were put out, and the evacuation of emergency personnel inside the building was ordered. After battling the fire for almost two hours, the fire was brought under control at approximately 7:00 a.m. that morning. 1

*756 Munoz was not at the scene when the fire began. He first received notification of the fire between 5:00 and 6:00 a.m., while at his apartment. After unsuccessfully attempting to get within close proximity of the Building, Munoz returned to his apartment and retained New Jersey Public Adjusters, Inc. to aid him in assessing his losses as a result of the fire. At some point thereafter, Munoz left his apartment and was allowed to approach the Building to be interviewed by emergency personnel at the scene.

At approximately 10:00 a.m., Martin Martinetti (“Martinetti”), Union City’s Construction Code Official, arrived on scene to assess the damage caused by the fire. Martinetti believed that the structural integrity of the Building was so compromised that he could not enter the Building. He proceeded to the upper floors of the adjacent building and peered out on the damaged structure. Martinetti observed that the majority of the Building’s roof had collapsed and that the floors were in the process of collapsing.

Martinetti determined that the Building was structurally unsafe and needed to be immediately demolished. Martinetti informed Munoz in the presence of Ralph Affuso, Munoz’s insurance adjuster; Scott Sandman, the Deputy Director of Parks for Union City; and one of Munoz’s sons that the Building must be demolished. Around this time, Martinetti posted a notice of unsafe structure on the Building, in accordance with N.J. Admin. Code § 5:23-2.32(b)(2). Martinetti claims that he told Munoz that Munoz could retain a contractor to perform the demolition or Union City would retain one and place a tax lien on the property in the amount of the demolition costs. According to Martinetti, Munoz informed him that he (Martinetti) could take whatever actions were necessary.

Martinetti called several demolition companies. Nacirema Environmental Services, Inc. (“Nacirema”) was the first company to respond. Affuso had dealt with Nacirema in the past and determined that Nacirema would be an appropriate contractor to perform the demolition. Nacire-ma was hired. The razing process began sometime after 4:00 p.m. on September 9, 2006 and was completed the next day. Contrary to Martinetti’s viewpoint, Munoz claims that he never received oral or written notification that the Building needed to be demolished and first learned of the demolition approximately three to four days after Nacirema performed the razing.

Four due process hearings were held subsequent to the demolition — three in 2007 and one in 2008. Lane J. Biviano, Esq. was the hearing officer who conducted the proceedings. All parties participated fully. In a July 16, 2008 letter, Biviano submitted his findings. Biviano concluded that Munoz received sufficient oral notice of the impending demolition, prior to the Building being razed. As such, Biviano found that Munoz was required to pay $76,767.75 in total costs. Munoz did not appeal Biviano’s decision, which was adopted by Union City’s Board of Commissioners.

On September 5, 2008, Munoz filed suit in New Jersey state court. Munoz alleged numerous federal constitutional violations, pursuant to 42 U.S.C. § 1983, as well as violations of New Jersey’s constitution and state law. The essence of Munoz’s claims is that his Building did not require demolition and, in any event, Appellees failed to follow required protocol before razing the structure. After answering the complaint, the City Appellees removed the case to the District Court. All parties moved for summary judgment. On March 28, 2011, the District Court granted City Appellees’ and Nacirema’s motions for summary judg *757 ment, in a telephonic ruling. Munoz filed a timely notice of appeal.

II. JURISDICTION AND STANDARD OF REVIEW

City Appellees removed the case to the District Court under 28 U.S.C. § 1441, pursuant to federal question jurisdiction. The District Court, therefore, had jurisdiction under 28 U.S.C. §§ 1331 and 1343. We have jurisdiction under 28 U.S.C. § 1291.

We exercise plenary review over the District Court’s grant of summary judgment, Doe v. Luzerne Cnty., 660 F.3d 169, 174 (3d Cir.2011) (citation omitted), including over determinations of qualified immunity, Bu rns v. Pa. Dep’t of Corr., 642 F.3d 163, 170 (3d Cir.2011) (citation omitted).

III. ANALYSIS

To succeed on a claim brought under 42 U.S.C. § 1983, the “plaintiff must show that the defendants, acting under color of law, violated the plaintiffs federal constitutional or statutory rights, and thereby caused the complained of injury.” Elmore v. Cleary, 399 F.3d 279, 281 (3d Cir.2005) (citation omitted). In particular, the plaintiff must prove two elements: “(1) that the conduct complained of was committed by a person acting under color of state law; and (2) that the conduct deprived the plaintiff of rights, privileges, or immunities secured by the Constitution or laws of the United States.” Schneyder v. Smith,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lehigh Valley Properties, Inc. v. City of Allentown
Commonwealth Court of Pennsylvania, 2026
DOTAN v. CITY OF ALTOONA
W.D. Pennsylvania, 2025
VAN v. CITY OF PHILADELPHIA
E.D. Pennsylvania, 2024
BELFI v. CITY OF PHILADELPHIA
E.D. Pennsylvania, 2024
SMIT v. TOMS RIVER TOWNSHIP
D. New Jersey, 2024
IRAHETA v. HOUSTON COUNTY
M.D. Georgia, 2021
KHAN v. CITY OF BAYONNE
D. New Jersey, 2021
Deiter v. City of Wilkes Barre
M.D. Pennsylvania, 2021
DIETRICH v. MOUNT OLIVER BOROUGH
W.D. Pennsylvania, 2021
FISHER v. PRATT
D. New Jersey, 2020
DAVIS v. SLAUGHTER
D. New Jersey, 2019
Kaul v. Christie
372 F. Supp. 3d 206 (D. New Jersey, 2019)
Win & Son, Inc. v. City of Philadelphia
162 F. Supp. 3d 449 (E.D. Pennsylvania, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
481 F. App'x 754, Counsel Stack Legal Research, https://law.counselstack.com/opinion/francisco-munoz-v-city-of-union-city-ca3-2012.