For a Better Bayou v. FERC

Court of Appeals for the D.C. Circuit·Decided August 25, 2026·No. 24-1291·Published

Opinion

United States Court of Appeals FOR THE DISTRICT OF COLUMBIA CIRCUIT

Argued March 24, 2026 Decided August 25, 2026

No. 24-1291

FOR A BETTER BAYOU, ET AL., PETITIONERS

v.

FEDERAL ENERGY REGULATORY COMMISSION, RESPONDENT

VENTURE GLOBAL CP EXPRESS, LLC AND VENTURE GLOBAL CP2 LNG, LLC,

INTERVENORS

Consolidated with 24-1292, 25-1157

On Petitions for Review of Orders of the Federal Energy Regulatory Commission

Nathan Matthews argued the cause for petitioners. With him on the joint briefs were Megan Gibson, Spencer T. Gall, Clara Derby, Caroline Reiser, Thomas Zimpleman, Gillian Giannetti, and Rebecca McCreary.

Scott R. Ediger, Attorney Advisor, Federal Energy Regulatory Commission, argued the cause for respondent. With him on the brief was Robert H. Solomon, Solicitor. Susanna Y. Chu, Senior Attorney, entered an appearance.

Eric Konopka argued the cause for intervenors in support of respondent. With him on the brief were Gregory G. Garre, Joel P. Nevins, Peter Prindiville, Halle H. Edwards, and Sandra Snyder.

Before: HENDERSON and MILLETT, Circuit Judges, and GINSBURG, Senior Circuit Judge.

Opinion for the Court filed by Senior Circuit Judge GINSBURG.

I. Background ...................................................................... 4 A. Relevant Statutes ...................................................... 4 B. Commission Proceedings ......................................... 9 II. Analysis ......................................................................... 11 A. Challenges under the NGA ..................................... 12 1. The Commission’s interpretation of the NGA ................................................................ 13 2. The Commission’s application of the NGA .... 17 a. The project’s harms .................................. 17 b. The Terminal’s benefits ........................... 19 c. The authorization of the Pipeline ............. 20 B. Challenges under the NEPA ................................... 23 1. The Terminal’s cumulative effects .................. 23 a. New model ............................................... 24 b. Magnolia Terminal. .................................. 25 c. Marine vessels serving other terminals .................................................................. 27 2. The Commission’s use of NAAQS in the cumulative effects analysis.............................. 30 3. The Moss Lake Compressor Station’s cumulative effects ........................................... 33 4. The harm to the commercial fishing industry ............................................................ 37 a. Temporary harm................................... 37 b. Localized harm..................................... 38 III. Conclusion ..................................................................... 41

GINSBURG, Senior Circuit Judge: In December 2021 Venture Global CP2 LNG and Venture Global CP Express, the Intervenors here, sought authorization from the Federal Energy Regulatory Commission for the siting, construction, and operation of a terminal and pipeline for the exportation of liquefied natural gas (LNG). A long review process followed, resulting in two environmental impact statements, an initial authorization order, three rehearing orders and, in 2025, the FERC’s approval of the project.

The petitioners are individuals and advocacy groups seeking review of those orders. Leaving no stone unturned, they improbably allege the Commission committed no fewer than eleven errors under the Natural Gas Act (NGA) and the National Environmental Policy Act (NEPA). Because these arguments lack merit, we deny the petitions for review.

I. Background

This appeal implicates not only the NGA and the NEPA, but also the Clean Air Act (CAA). We begin by discussing the relevant provisions of these laws before turning to the procedural history of the case.

A. Relevant Statutes

The NGA regulates “the business of transporting and selling natural gas for ultimate distribution to the public.” 15 U.S.C. § 717(a). It prohibits the export of natural gas by any entity “without first having secured an order of the Commission authorizing it to do so.” § 717b(a). A party must also obtain prior authorization before constructing a natural gas terminal or a pipeline. See Big Bend Conservation All. v. FERC, 896 F.3d 418, 420 (D.C. Cir. 2018).

The United States Department of Energy (DOE) has delegated authority to the FERC to “[a]pprove or disapprove” the siting, construction, and operation of particular facilities used to export natural gas, including LNG terminals. DOE, Delegation Order No. S1-DEL-FERC-2006, § 1.21A (2006); see § 717b(e)(1); see also § 717a(11) (defining “LNG terminal”). 1 The Congress has laid down different standards for the approval of an LNG export terminal than it has for the approval of a pipeline used to transport natural gas. Under Section 3 of the NGA the FERC “shall issue” an order authorizing an LNG export terminal “unless” it finds the terminal “will not be consistent with the public interest.” § 717b(a). By contrast, under Section 7 the FERC may not authorize the construction and operation of a pipeline unless it determines the pipeline “is or will be required by the present or future public convenience and necessity.” § 717f(e).

Although the FERC exercises authority over the approval of LNG terminals, the DOE has “retained for itself the authority to authorize exports . . . of natural gas.” Sierra Club v. DOE (Alaska Gasline), 134 F.4th 568, 570 n.2 (D.C. Cir. 2025). Any exportation of gas to a country with which the United States has “a free trade agreement requiring national treatment for trade in natural gas[] shall be deemed to be consistent with the public interest, and applications for such . . . exportation shall be granted without modification or delay.” § 717b(c).

The FERC follows its longstanding Certificate Policy Statement when it reviews an application for the construction

1 “Commission” as used in the NGA refers to the Federal Power Commission, § 717a(9), the predecessor to the FERC. In 1977 the Congress “transferred to” the Secretary of Energy “the function of the Federal Power Commission.” 42 U.S.C. § 7151(b), who as just mentioned, has delegated some of those functions to the FERC.

of a pipeline. See Certification of New Interstate Nat. Gas Pipeline Facilities, 88 FERC 61227 (1999), clarified, 90 FERC 61128 (2000), further clarified, 92 FERC 61094 (2000). The Commission first considers whether there is a “market need” for the project by asking whether it can proceed without subsidies from the applicant’s existing customers. Env’t Def. Fund v. FERC, 2 F.4th 953, 961 (D.C. Cir. 2021). If it finds there is a market need for the pipeline, then the FERC determines whether the pipeline will have an adverse effect on the applicant ’s existing customers, pipelines in the same market and their captive customers, or landowners and communities surrounding the project. Id. If the pipeline will cause an adverse effect, then the FERC balances that effect against the pipeline’s public benefits. Id. In doing so, the Commission will “consider all relevant factors reflecting on the need for the project.” Id.

Free access — add to your briefcase to read the full text and ask questions with AI

For a Better Bayou v. FERC, (D.C. Cir. 2026).

For a Better Bayou v. FERC (For a Better Bayou v. FERC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Atlantic Refining Co. v. Public Service Commission
360 U.S. 378 (Supreme Court, 1959)
Horne v. Flores
557 U.S. 433 (Supreme Court, 2009)
Sierra Club v. Environmental Protection Agency
705 F.3d 458 (D.C. Circuit, 2013)
Encino Motorcars, LLC v. Navarro
579 U.S. 211 (Supreme Court, 2016)
Sierra Club v. United States Department of Energy
867 F.3d 189 (D.C. Circuit, 2017)
Sierra Club v. Federal Energy Regulatory Commission
867 F.3d 1357 (D.C. Circuit, 2017)
Woodhull Freedom Foundation v. United States
948 F.3d 363 (D.C. Circuit, 2020)
Environmental Defense Fund v. FERC
2 F.4th 953 (D.C. Circuit, 2021)
City of Oberlin, Ohio v. FERC
39 F.4th 719 (D.C. Circuit, 2022)