Fluor Federal Solutions, LLC v. BAE Systems Ordnance Systems, Inc.

District Court, W.D. Virginia·Decided January 15, 2023·No. 7:19-cv-00698·Unknown

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE WESTERN DISTRICT OF VIRGINIA ROANOKE DIVISION

FLUOR FEDERAL SOLUTIONS, LLC, ) ) Plaintiff, ) ) v. ) Civil Action No. 7:19-cv-00698 ) BAE SYSTEMS ORDNANCE SYSTEMS, ) By: Elizabeth K. Dillon INC., ) United States District Judge ) Defendant. )

MEMORANDUM OPINION AND ORDER

Trial in this matter is scheduled to begin on January 17, 2023. Pending before the court are two motions by Fluor Federal Solutions, LLC (“Fluor”) to exclude expert testimony (Dkt. Nos. 108, 110) and five motions in limine—three from Fluor (Dkt. Nos. 171, 172, 173) and two from BAE Systems Ordnance Systems, Inc. (“BAE”) (Dkt. Nos. 168, 169). All of the motions are fully briefed; the court heard argument on the motions to exclude expert testimony on December 16, 2022, and heard argument on the motions in limine at the pretrial conference on January 6, 2023. For the reasons stated herein, all seven motions will be denied. I. BACKGROUND This case concerns a dispute arising from a subcontract between Fluor and BAE for the construction of a new natural-gas-fired boiler facility at the Radford Army Ammunition Plant in Radford, Virginia. The United States Army contracted with BAE to construct and design a temporary boiler facility at the Radford plant. BAE then solicited proposal from bidders, including Fluor, for a subcontract. Fluor ultimately won the contract to design the boiler facility (the “Subcontract”), which the parties executed on December 30, 2015. The next day, BAE informed Fluor that the Army had changed the scope of the project to a permanent boiler facility as opposed to a permanent facility, and asked Fluor to submit any cost impact. Over the next several years, the parties negotiated on a new price to design (and, as was eventually added to the Subcontract, to construct) the facility in light of the change from temporary to permanent. In the process, the parties executed several modifications to the Subcontract. Now, Fluor alleges that

BAE has not fully paid Fluor for the work it performed under the Subcontract, and BAE alleges that Fluor has been overpaid and seeks reimbursement for the extent of the alleged overpayment. Fluor brought this action in October 2019, asserting claims for breach of contract, quantum meruit, unjust enrichment, breach of the duty of good faith and fair dealing, fraud in the inducement, and for declaratory judgment. (Dkt. No. 1 at 14–21.) BAE asserts counterclaims for breach of contract and for declaratory judgment. (Dkt. No. 40 at 54–59.) After cross- motions to dismiss, only the breach-of-contract claims remain. II. LEGAL STANDARDS A. Expert Testimony Rule 702 of the Federal Rules of Evidence governs admissibility of expert testimony.

The testimony of a witness “who is qualified as an expert by knowledge, skill, experience, training, or education” is admissible if: “(1) the expert's scientific, technical, or other specialized knowledge will help the trier of fact to understand the evidence or to determine a fact at issue; (2) the testimony is based upon sufficient facts or data; (3) the testimony is the product of reliable principles and methods; and (4) the expert has reliably applied the principles and methods to the facts of the case.” Fed. R. Evid. 702. After an individual qualifies as an expert, this court has an obligation under Daubert to act as a gatekeeper and ensure that any testimony concerning scientific, technical, or other specialized knowledge offered in support of a party's claim is “not only relevant, but reliable.” Daubert v. Merrell Dow Pharm., Inc., 509 U.S. 579, 589 (1993); Kumho Tire Co. v. Carmichael, 526 U.S. 137, 147 (1999) (quoting same). When testimony is based upon “technical” or “other specialized knowledge,” it is admissible if: (1) the expert is qualified to testify competently regarding the matters he intends to address; (2) his methodology is sufficiently reliable; and (3)

the testimony will assist the trier of fact by bringing the expert's knowledge to bear upon a fact in issue. See Daubert, 509 U.S. at 589–91. The proponent of the testimony must establish its admissibility, although it need not prove its expert's theory is correct. Cooper v. Smith & Nephew, Inc., 259 F.3d 194, 199 (4th Cir. 2001); Maryland Cas. Co. v. Therm–O–Disc, Inc., 137 F.3d 780, 783 (4th Cir. 1998). Indeed, “[v]igorous cross examination, presentation of contrary evidence and careful instruction on the burden of proof are traditional and appropriate means of attacking shaky but admissible evidence.” Daubert, 509 U.S. at 596. The Fourth Circuit has explained the Daubert standard as a “two-step gatekeeping function” required of trial courts. First, the trial court must ask whether the proffered evidence is valid and reliable. United States v. Barnette, 211 F.3d 803, 815 (4th Cir. 2000). Second, the

court asks whether the evidence will help the trier of fact, which is generally a question of relevance, or “fit”: assuming the evidence is reliable, will it “assist the trier of fact to understand or determine a fact in issue.” Maryland Cas. Co., 137 F.3d at 784 (quoting Daubert, 509 U.S. at 592). B. Motions in Limine “The purpose of a motion in limine is to allow a court to rule on evidentiary issues in advance of trial in order to avoid delay, ensure an even-handed and expeditious trial, and focus the issues the jury will consider.” Gonzalez v. SeaWorld Parks & Ent., No. 4:20-cv-27, 2021 WL 3203535, at *1 (E.D. Va. July 28, 2021) (citation omitted). However, “[t]he decision to grant or deny a motion in limine is within the district court’s discretion.” Cougill v. Prospect Mortg. LLC, No. 1:13-cv-1433, 2014 WL 348539, at *1–2 (E.D. Va. Jan. 31, 2014). “[A] motion in limine ‘should be granted only when the evidence is clearly inadmissible on all potential grounds.’” Gonzalez, 2021 WL 3203535, at *1 (alteration in original) (citation

omitted); Emami v. Bolden, 241 F. Supp. 3d 673, 681 (E.D. Va. 2017). III. ANALYSIS A. Fluor’s Motion to Exclude the Expert Testimony of Mark LoManto (Dkt. No. 108) Fluor first moves to exclude the testimony of Mark LoManto, a licensed CPA and former Defense Contract Audit Agency (“DCAA”) auditor who BAE has proffered to evaluate whether Fluor’s change proposals adhered to the instructions and formats prescribed in Federal Acquisition Regulation § 15.408, Table 15-2, Section III.B, as well as whether the costs that Fluor classified as Base Scope Work costs in the change proposals were solely attributable to the project change from a temporary to a permanent boiler facility. Fluor first argues that, because interpreting and applying FAR § 15.408 to the facts of

this case call for a legal opinion which LoManto is not qualified to render and which the Court “needs no expert assistance in rendering,” LoManto’s testimony is inadmissible. (Dkt. No. 109, at 1–2.) The court disagrees.

Free access — add to your briefcase to read the full text and ask questions with AI

Fluor Federal Solutions, LLC v. BAE Systems Ordnance Systems, Inc., (W.D. Va. 2023).

Fluor Federal Solutions, LLC v. BAE Systems Ordnance Systems, Inc. (Fluor Federal Solutions, LLC v. BAE Systems Ordnance Systems, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Palmer v. Hoffman
318 U.S. 109 (Supreme Court, 1943)
Daubert v. Merrell Dow Pharmaceuticals, Inc.
509 U.S. 579 (Supreme Court, 1993)
Kumho Tire Co. v. Carmichael
526 U.S. 137 (Supreme Court, 1999)
United States v. Thomas N. Moore
791 F.2d 566 (Seventh Circuit, 1986)
United States v. Offill
666 F.3d 168 (Fourth Circuit, 2011)
United States v. Centex Const. Co., Inc.
638 F. Supp. 411 (W.D. Virginia, 1985)
Metcalf Construction Company v. United States
742 F.3d 984 (Federal Circuit, 2014)
Cooper v. Smith & Nephew, Inc.
259 F.3d 194 (Fourth Circuit, 2001)
Kellogg Brown & Root Services, Inc. v. United States
107 Fed. Cl. 16 (Federal Claims, 2012)
Emami v. Bolden
241 F. Supp. 3d 673 (E.D. Virginia, 2017)
United States v. Leo
941 F.2d 181 (Third Circuit, 1991)