Fluor Federal Solutions, LLC v. BAE Systems Ordnance Systems, Inc.

CourtDistrict Court, W.D. Virginia
DecidedJanuary 13, 2023
Docket7:19-cv-00698
StatusUnknown

This text of Fluor Federal Solutions, LLC v. BAE Systems Ordnance Systems, Inc. (Fluor Federal Solutions, LLC v. BAE Systems Ordnance Systems, Inc.) is published on Counsel Stack Legal Research, covering District Court, W.D. Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fluor Federal Solutions, LLC v. BAE Systems Ordnance Systems, Inc., (W.D. Va. 2023).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE WESTERN DISTRICT OF VIRGINIA ROANOKE DIVISION

FLUOR FEDERAL SOLUTIONS, LLC, ) ) Plaintiff, ) ) v. ) Civil Action No. 7:19-cv-00698 ) BAE SYSTEMS ORDNANCE SYSTEMS, ) By: Elizabeth K. Dillon INC., ) United States District Judge ) Defendant. )

MEMORANDUM OPINION

Trial in this matter is currently scheduled to begin on January 17, 2023. Pending before the court are both parties’ cross motions for partial summary judgment. Both motions are fully briefed, and the court heard argument on December 16, 2022. For the reasons stated herein, the court will grant in part and deny in part BAE Systems Ordnance Systems, Inc.’s (“BAE”) motion for partial summary judgment (Dkt. No. 104) and deny in full Fluor Federal Solutions, LLC’s (“Fluor”) motion for partial summary judgment (Dkt. No. 112). I. BACKGROUND1 This case concerns a dispute between BAE and Fluor regarding a subcontract for the construction of a new natural-gas-fired boiler facility at the Radford Army Ammunition Plant in Radford, Virginia. In May 2011, the United States Army (“Army”) awarded BAE a Basic Ordering Agreement and, in December 2013, executed Task Order 00029 with BAE. This Task Order funded the design of a new natural gas-fired combined heating and power plant (“CHPP”); one of the purposes of this project was to replace the coal-fired boilers in the plant.

1 The following material facts are taken from the summary judgment record and, unless otherwise stated, are undisputed. Facts not material to the issues are omitted. On October 7, 2015, BAE issued a request for proposal (“RFP”) for a firm-fixed price subcontract for the design and construction of a temporary boiler facility to several bidders, including Fluor. On December 10, 2015, Fluor submitted a firm-fixed price proposal for the design, construction and commissioning of a temporary facility in the amount of $10,965,787. On December 14, 2015, four days after receiving Fluor’s proposal, the Army notified BAE that

the CHPP project was cancelled and that it intended to move the boiler facility to a permanent location elsewhere. At that time, all bidders, including Fluor, had submitted proposals for the original temporary facility scope of work at the temporary location. BAE decided to complete the competition and award a design subcontract to Fluor. On December 30, 2015, BAE and Fluor executed a Subcontract only for the ‘design’ phase (but not the ‘construction’ phase) of the temporary package boiler facility in the amount of $1,519,560.85. (Dkt. Nos. 105-6; 113-53.) The next day, on December 31, 2015, Jared Hendrick of BAE emailed Roy Harris of Fluor, informing Fluor that the Army had decided to change the location of the boiler to a permanent facility and thus that the project scope would be

changing. (Dkt Nos. 105-7; 113-15.) On January 12, 2016, BAE issued Fluor a proposed Statement of Work Addendum, Revision 0 for the change to the permanent facility. On January 15, 2016, Erin Phalen of BAE emailed Lura Lewis of Fluor to “request that [Fluor] review the changes in [scope of work] and send any cost impact by 12:00 p.m. on January 21[, 2016],” including “a detailed breakdown of cost element.” (Dkt. No. 105-8.) On January 21, 2016, Fluor submitted a change proposal addressing potential cost impact associated with Statement of Work Addendum, Revision 0, reflecting an increase price of $336,248 for the design changes. The construction phase work for the project was not added to Fluor’s agreement with BAE until March 23, 2016, when the parties executed Modification 1 (“Mod 1”). (Dkt. No. 105- 9 [“Mod 1”].) Mod 1 included the same price for the construction portion of the original scope of work (i.e., the temporary facility) that Fluor had initially proposed in its December 2015 proposal update to BAE, as a starting point for pricing changes. (Dkt. Nos. 105-9, 105-29.) At the time, the contract had not been modified to reflect a permanent facility, but when the parties executed Mod 1, it was understood by both parties that a temporary facility would not be built.

(Answer ¶ 34.) On April 1, 2016, the parties executed Modification 2 to the Subcontract (“Mod 2”), which also included the same prices from the December 2015 proposal update. (Dkt. No. 105-10 [“Mod 2”].) On September 1, 2016, the parties executed Modification 3 to the Subcontract (“Mod 3”), which established the agreed total firm-fixed price of $1,852,723.82 for the design of the permanent facility and authorized payment. (Dkt. No. 105-11 [“Mod 3”].) The parties proceeded to negotiate a firm-fixed price for the changes to the project, including Fluor’s construction work. On April 4, 2016, Fluor submitted its first proposal to complete construction of a permanent facility at a fixed-firm price of $27,490,300.39. (Dkt. No. 113-27.) On June 17, 2016, Fluor submitted a second proposal for construction of a permanent

facility at a fixed-firm price of $24,942,758. (Dkt. No. 113-28.) Then, on or about November 29, 2016, after continued negotiations, the parties executed Modification 4 to the Subcontract (“Mod 4”). (Dkt. No. 105-22 [“Mod 4”].) Mod 4 was an Unpriced Change Order2 (“UCO”) which incorporated Statement of Work Addendum, Revision 4—i.e., construction of a permanent facility—into the subcontract, with the firm-fixed price to be definitized later (by a deadline upon which the parties still do not agree).

2 A ‘change order’ is “a written order, signed by the contracting officer, that directs the contractor to make a change that the Changes clause authorizes the contracting officer to order without the contractor’s consent.” FAR § 2.101. An ‘unpriced change order,’ or UCO, generally refers to a change order not forwardly priced, meaning it defines the work to be performed while leaving the final negotiated priced to be determined later. On March 29, 2017, with the firm-fixed price for construction still not definitized, the parties executed Modification 7 to the Subcontract (“Mod 7”), which revised the Mod 4 UCO in several important respects. (Dkt. No. 105-27 [“Mod 7”].) For one, under the revised UCO (Dkt. No. 105-40 [“Revised UCO”]), Fluor was required to “promptly submit a change proposal in accordance with [Federal Acquisition Regulation] 15.408 Table 15-2, Section III.” (Id. at 3.) On

August 15, 2017, Fluor submitted a change proposal that purported to reflect $33,230,509 in costs incurred to construct the permanent facility, and $15,732,472 in charges, delays, acceleration, and other costs. (Dkt. No. 113-40.) On October 26, 2017, BAE rejected Fluor’s change proposal, noting that the “primary inadequacy found is that the Proposal does not comply with Section 2” of Mod 7. (Dkt. No. 113-41.) In August 2019, Fluor submitted an updated change proposal to capture what Fluor submitted were its actual costs. (Dkt No. 113-42.) This proposal claimed $50,254,837 in costs on the project. (Id.) Fluor claims it has only been paid $29,478,827.33 by BAE; BAE disputes that Fluor is entitled to this amount, or the costs claimed in its August 2019 proposal. (Dkt. Nos. 113 at 46, 134 at 46.)

Fluor brought this action in October 2019, asserting claims for breach of contract, quantum meruit, unjust enrichment, breach of the duty of good faith and fair dealing, fraud in the inducement, and for declaratory judgment. (Dkt. No. 1 at 14–21.) BAE asserted counterclaims for breach of contract and for declaratory judgment. (Dkt. No. 40 at 54–59.) After cross- motions to dismiss, only the breach-of-contract claims remain. II. LEGAL STANDARDS A. Summary Judgment In considering cross-motions for summary judgment, the court “examines each motion separately, employing the familiar standard” provided by Rule 56. Desmond v. PNGI Charles Town Gaming, 630 F.3d 351, 354 (4th Cir. 2011).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Desmond v. PNGI Charles Town Gaming, L.L.C.
630 F.3d 351 (Fourth Circuit, 2011)
Westminster Investing Corp. v. Lamps Unlimited, Inc.
379 S.E.2d 316 (Supreme Court of Virginia, 1989)
United States v. Idlewild Pharmacy, Inc.
308 F. Supp. 19 (E.D. Virginia, 1969)
Rossignol v. Voorhaar
316 F.3d 516 (Fourth Circuit, 2003)
Wachovia Bank, National Ass'n v. Schmidt
445 F.3d 762 (Fourth Circuit, 2006)
Virginian Railway Co. v. Hood
146 S.E. 284 (Supreme Court of Virginia, 1929)
Dixon Lumber Co. v. Austinville Limestone Co.
256 F. Supp. 3d 658 (W.D. Virginia, 2017)
SAS Institute, Inc. v. World Programming Ltd.
874 F.3d 370 (Fourth Circuit, 2017)
Anderson v. Cox
977 F. Supp. 413 (W.D. Virginia, 1997)
Beale v. Hardy
769 F.2d 213 (Fourth Circuit, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
Fluor Federal Solutions, LLC v. BAE Systems Ordnance Systems, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/fluor-federal-solutions-llc-v-bae-systems-ordnance-systems-inc-vawd-2023.