Fluor Federal Solutions, LLC v. BAE Systems Ordnance Systems, Inc.

CourtDistrict Court, W.D. Virginia
DecidedJune 18, 2020
Docket7:19-cv-00698
StatusUnknown

This text of Fluor Federal Solutions, LLC v. BAE Systems Ordnance Systems, Inc. (Fluor Federal Solutions, LLC v. BAE Systems Ordnance Systems, Inc.) is published on Counsel Stack Legal Research, covering District Court, W.D. Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fluor Federal Solutions, LLC v. BAE Systems Ordnance Systems, Inc., (W.D. Va. 2020).

Opinion

FIONR T THHEE U WNIETSETDE RSTNA DTIESST RDIICSTT ROIFC TV ICROGUINRITA ROANOKE DIVISION

FLUOR FEDERAL SOLUTIONS, LLC, ) ) Plaintiff, ) ) v. ) Civil Action No. 7:19-cv-00698 ) BAE SYSTEMS ORDNANCE SYSTEMS, ) By: Elizabeth K. Dillon INC., ) United States District Judge ) Defendant. ) MEMORANDUM OPINION

Fluor Federal Solutions, LLC (Fluor) filed a complaint on October 17, 2019, asserting claims of breach of contract, quantum meruit, unjust enrichment, breach of the duty of good faith and fair dealing, fraud in the inducement, and a declaratory judgment action against BAE Systems Ordnance Systems, Inc. (BAE). This matter is before the court on BAE’s motion to dismiss all counts for failure to state a claim. (Mot. Dismiss, Dkt. No. 8.) The court held a hearing on BAE’s motion, and at the hearing, the court denied BAE’s motion as to Fluor’s breach of contract claim and granted the motion as to Fluor’s equitable claims of quantum meruit and unjust enrichment and as to Fluor’s claim for declaratory judgment. The court further denied Fluor’s claim for breach of the duty of good faith and fair dealing as moot by agreement of counsel. With respect to Fluor’s fraud claim, the court took the matter under advisement, and the parties submitted supplemental briefing. For the reasons stated below, the court will grant BAE’s motion in part and dismiss Fluor’s fraud claim as time-barred. I. BACKGROUND1

1 The following factual background is taken from the allegations in Fluor’s complaint, which are accepted as true for purposes of this motion. In 2011, the United States Army awarded BAE a basic ordering agreement under which BAE was responsible for modernization projects at the Radford Army Ammunition Plant in Radford, Virginia. This action stems from a subcontract between Fluor and BAE, under which Fluor agreed to design and construct a new natural gas boiler at the Plant. Fluor has completed work on the project, and BAE has accepted that work. Nonetheless, Fluor claims that BAE has refused or failed to pay for the balance of the project costs. (Compl. ¶¶ 1–2, 13, 72, Dkt. No. 1.) The primary dispute is over an increase in the cost of the project after the United States Army changed the scope of the project from designing and building a temporary facility in one location to designing and building a permanent facility in a different location. Fluor alleges that BAE issued a request for proposal to Fluor seeking a proposal for design, construction, and

commission of a temporary facility on October 7, 2015. Later in October, the Army issued a modification to the contract, which changed the location of the facility. In December, BAE received additional modifications from the Army that changed the project to a permanent facility instead of a temporary facility. Although Fluor does not provide the date that it submitted its bid to BAE, it alleges that it executed a subcontract for the design of a temporary facility on December 30, 2015. (Id. ¶¶ 17–27.) Throughout 2016, BAE issued several modifications to Fluor reflecting the modifications BAE received from the Army. Despite the subcontract to build a temporary facility, in March 2016, BAE directed Fluor to begin construction of a permanent facility. On September 1, 2016, BAE

issued another modification to Fluor, authorizing payment for the design of a permanent facility. On November 29, 2016, BAE and Fluor executed a fourth modification, which eliminated the requirement for Fluor to construct a temporary facility and incorporated the requirement to construct a permanent facility. The parties did not agree to a definite price, instead agreeing to negotiate and definitize the price by December 2016. (Id. ¶¶ 33–43.) As relevant to Fluor’s fraud claim, Fluor alleges that BAE received several changes to its prime contract from the Army but did not pass those changes along to Fluor until after BAE solicited a bid from Fluor and entered a contract with Fluor to build a temporary facility. Instead, BAE continued to misrepresent the scope of the project. Fluor alleges that the change in plans increased costs substantially, but that BAE withheld information about those changes so that it could solicit lower bids. Fluor notes, for example, that a temporary facility would have been designed and constructed to last approximately eighteen months, whereas a permanent facility would last approximately thirty years, significantly increasing costs. (Id. ¶¶ 125–143.) Fluor alleges that it requested a copy of BAE’s prime contract on numerous occasions, but BAE failed to provide a copy of it. Instead, Fluor submitted a request under the Freedom of

Information Act. It received a copy of BAE’s prime contract on October 3, 2018. (Id. ¶¶ 134–136.) Fluor then filed its complaint in this court on October 17, 2019. II. DISCUSSION2 A. Standard of Review To survive a motion to dismiss under Rule 12(b)(6), the complaint must “state a claim to relief that is plausible on its face.” Ashcroft v. Iqbal, 556 U.S. 662, 678 (2009) (quoting Bell Atlantic Corp. v. Twombly, 550 U.S. 544 (2007)). A claim is facially plausible if the plaintiff pleads factual content that allows the court to draw a “reasonable inference that the defendant is liable for the alleged misconduct.” Iqbal, 556 U.S. at 678. In determining whether the plaintiff has satisfied

this plausibility standard, the court must accept as true all well-pleaded facts in the complaint and “draw[] all reasonable factual inferences from those facts in the plaintiff’s favor,” Edwards v. City of Goldsboro, 178 F.3d 231, 244 (4th Cir. 1999), but it need not “accept legal conclusions couched

2 Fluor alleges, and BAE appears to agree, that the subcontract “is to be interpreted under the laws of the Commonwealth of Virginia.” (Compl. ¶ 12; see generally Mot. Dismiss.) Accordingly, the court will apply Virginia as facts or unwarranted inferences, unreasonable conclusions, or arguments.” Giarratano v. Johnson, 521 F.3d 298, 302 (4th Cir. 2008). As already noted, BAE argues that Fluor’s fraud claim is time-barred. Statutes of limitation create affirmative defenses that may be raised in a motion to dismiss under Federal Rule of Civil Procedure 12(b)(6). United States v. Kivanc, 714 F.3d 782, 789 (4th Cir. 2013) (citing Dean v. Pilgrim’s Pride Corp., 395 F.3d 471, 474 (4th Cir. 2005)). While a Rule 12(b)(6) motion “invites an inquiry into the legal sufficiency of the complaint, not an analysis of potential defenses to the claims set forth therein, dismissal nevertheless is appropriate when the face of the complaint clearly reveals the existence of a meritorious affirmative defense.” Brockington v. Boykins, 637 F.3d 503, 506 (4th Cir. 2011) (quoting Brooks v. City of Winston-Salem, 85 F.3d 178, 181 (4th Cir. 1996));

see also McPike v. Zero-Gravity Holdings, Inc., 280 F. Supp. 3d 800, 807 (E.D. Va. 2017) (“[A] statute of limitations question under Va. Code § 8.01-249(1) may be resolved on a threshold motion to dismiss, but only if all the facts necessary for resolution of the motion appear on the face of the complaint or are otherwise indisputable.”).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
Brockington v. Boykins
637 F.3d 503 (Fourth Circuit, 2011)
Author A.E. Berkley v. American Cyanamid Company
799 F.2d 995 (Fifth Circuit, 1986)
Childers Oil Company, Inc. v. Exxon Corporation
960 F.2d 1265 (Fourth Circuit, 1992)
United States v. 4219 University Drive, Fairfax
714 F.3d 782 (Fourth Circuit, 2013)
Giarratano v. Johnson
521 F.3d 298 (Fourth Circuit, 2008)
Newman v. Walker
618 S.E.2d 336 (Supreme Court of Virginia, 2005)
Stemple v. Dobson
400 S.E.2d 561 (West Virginia Supreme Court, 1990)
STB Marketing Corp. v. Zolfaghari
393 S.E.2d 394 (Supreme Court of Virginia, 1990)
Eshbaugh v. Amoco Oil Co.
360 S.E.2d 350 (Supreme Court of Virginia, 1987)
Hughes v. Foley
128 S.E.2d 261 (Supreme Court of Virginia, 1962)
Culpeper National Bank, Inc. v. Tidewater Improvement Co.
89 S.E. 118 (Supreme Court of Virginia, 1916)
Edwards v. City of Goldsboro
178 F.3d 231 (Fourth Circuit, 1999)
McPike v. Zero-Gravity Holdings, Inc.
280 F. Supp. 3d 800 (E.D. Virginia, 2017)
Jones v. Shooshan
855 F. Supp. 2d 594 (E.D. Virginia, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
Fluor Federal Solutions, LLC v. BAE Systems Ordnance Systems, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/fluor-federal-solutions-llc-v-bae-systems-ordnance-systems-inc-vawd-2020.