Fidelity & Deposit Co. of Maryland v. Bristol Steel & Iron Works, Inc.

722 F.2d 1160
CourtCourt of Appeals for the Fourth Circuit
DecidedDecember 1, 1983
DocketNo. 83-1166
StatusPublished
Cited by20 cases

This text of 722 F.2d 1160 (Fidelity & Deposit Co. of Maryland v. Bristol Steel & Iron Works, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fidelity & Deposit Co. of Maryland v. Bristol Steel & Iron Works, Inc., 722 F.2d 1160 (4th Cir. 1983).

Opinion

DONALD RUSSELL, Circuit Judge:

This appeal arises out of a. controversy between the plaintiffs Fidelity and Deposit 1 Company of Maryland, The Home Insurance Company, and North American Reinsurance Corporation, (hereinafter referred to collectively as “Sureties”) and their principal, the defendant Bristol Steel & Iron Works, Inc. (hereafter referred to as “Con- ■ tractor”), arising out of a contract of in- ! demnity executed by the Contractor in order to induce the Sureties in turn to execute a performance bond on behalf of the Contractor under a bridge construction contract with the Pennsylvania Department of Transportation (hereafter referred to as PennDOT). The subject of the action was a payment made by the Sureties to PennDOT to satisfy a claim of default asserted by PennDOT under the Contractor’s performance bond. By this action the Sureties seek, under their contract of indemnity, recovery of the payments made to PennDOT, interest on such payment from date made and for attorney’s fees. Federal jurisdiction rests on diversity.1 The District Court, [1162]*1162after a trial without a jury, sustained the Sureties’ right of recovery and granted judgment accordingly. The Contractor has appealed. We affirm.

I

The first ground of appeal raised by the Contractor is that this action by the Sureties under their contract of indemnity is barred by Code of Virginia § 8.01-250 (1950 as Amended). This section, which has been characterized as not “a statute of limitations in the strict sense,”2 provides:

No action to recover for any injury to property, real or personal, or for bodily injury or wrongful death, arising out of the defective and unsafe condition of an improvement to real property, nor any action for contribution or indemnity for damages sustained as a result of such injury, shall be brought against any person performing or furnishing the design, planning, surveying, supervision of construction, or construction of such improvement of real property more than five years after the performance of furnishing of such services and construction.

It will be observed that the statute, by its express terms, is restricted in its application to what are in effect tort actions to recover for “injury” to property or persons and not to actions in contract. That such is the proper construction of the statute was recognized in President and Directors, etc. v. Madden, 505 F.Supp. 557, 576-77 (D.Md. 1980) where the district court held that a District of Columbia statute, similar in language to Section 250, did not extend to “causes of action sounding in contract.” On appeal we implicitly accepted this construction of the statute. 660 F.2d 91 at 94 (4th Cir.1981). Accordingly, since this action is not one sounding in tort but is one arising out of a specific written contract of indemnity, it is outside the scope of Section 250.3

The Sureties have argued that, even if they were in error in their construction of Section 250 and even if such statute were considered applicable in this case, their suit, filed four and a half years after the payment was made, would still have been timely under the statute. They reason that the limitation established by Section 250 only commences with “the final completion date of the entire project.” Federal Reserve Bank of Richmond v. Wright, 392 F.Supp. 1126, 1130 (E.D.Va.1975). The construction contract involved defines the “Date of Completion of Contract,” so far as this project is concerned, as follows:

Date of Completion of Contract. The date on which the Secretary, through his authorized representative, notifies the contractor of the final settlement certificate computations or revised computations, or in case any claim has been filed before the Board of Arbitration of Claims, the date on which the Board of Arbitration of Claims makes an award or dismisses the claim, shall for such purposes be the date of completion of the contract. (Paragraph 109.08(d) of the Construction Contract).

Applying the standard fixed by this definition, the Sureties urge there has been no completion of the project since there has been no acceptance certificate issued and arbitration of the claim of failure of performance by PennDOT against the Contractor has been requested and is presently proceeding, both being conditions to “completion” of the contract. The suit is, therefore, timely. While this argument of timeliness under the statute may be meritorious, we prefer to rest our disposition of this limitation issue on the purpose and scope of the statute as being restricted in application to actions for “injury” sounding in tort and not to actions in contract such as that here.

II

Assuming that the claim of the Sureties is not barred by the limitations of Section [1163]*1163250, the Contractor raises a number of reasons why in its view summary judgment in favor of the Sureties was not authorized. Basically, its contentions in this regard are based on the claim that a surety is under no duty to pay an obligation of its principal ' when the principal’s liability has not been established or admitted and that, if it,, makes payment prior to that determination of its principal’s liability, it does so at the risk of “being able to prove the facts which might have rendered [its principal] liable ... as well as the reasonableness of the amount which it paid.”4 It asserts that the Sureties have offered no such proof and,: therefore, summary judgment was improper.

There is no dispute about the normal principle that “equity generally implies a right to indemnification in favor of a spifety only when the surety pays off a debt for which his principal is liable.” Com’l Ins. Co. of Newark v. Padfic-Peru Const., 558 F.2d 948, 953 (9th Cir.1977). But, as the court hastened to add, “[h]owever, resort to implied indemnity principles is improper when an express indemnification contract exists;” when there is such an express contract, “a surety is entitled to stand upon the letter of his contract.” Id. at 953. There is - in this case an “express indemnification contract.” Accordingly, the rights of the Sureties are not to be determined by general “indemnity principles,” as relied on by the Contractor, but by the “letter of [the Contractor’s] contract” of indemnification. Under the “letter” of this contract, the Sureties had the right to reimbursement by the Contractor for any payment made by them in good faith “under the belief ... that it was necessary or expedient to make such disbursements, whether or not such liability, necessity or expediency existed” under the performance bond executed by the Sureties on behalf of the Contractor and this right did not depend on “whether the Sureties shall have made any payment therefor.”5

Provisions such as those just cited, while strict, are common in contracts of indemnification executed by contractors and others to induce the execution of performance bonds by compensated sureties, and they have been uniformly sustained and upheld, subject to a single exception to be noted. See, Com’l Ins. Co. of Newark v. Pacific-Peru Const., supra, 558 F.2d at 953; Transamerica Insurance Company v. Bloomfield, 401 F.2d 357, 362-63 (6th Cir.1968); Engbrock v. Federal Insurance Company,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lincoln General Insurance v. Gracie Corp. of N.J.
28 Pa. D. & C.5th 419 (Chester County Court of Common Pleas, 2013)
Calvary Christian School, Inc. v. Huffstuttler
238 S.W.3d 58 (Supreme Court of Arkansas, 2006)
Atlantic Contracting & Material Co. v. Ulico Casualty Co.
844 A.2d 460 (Court of Appeals of Maryland, 2004)
PSE Consulting, Inc. v. Mercede
838 A.2d 135 (Supreme Court of Connecticut, 2004)
Ulico Casualty Co. v. Atlantic Contracting & Material Co.
822 A.2d 1257 (Court of Special Appeals of Maryland, 2003)
Fireman's Insurance v. Todesca Equipment Co.
310 F.3d 32 (First Circuit, 2002)
United States Fidelity & Guaranty Co. v. Feibus
15 F. Supp. 2d 579 (M.D. Pennsylvania, 1998)
Exxon Corp. v. Crosby-Mississippi Resources, Ltd.
775 F. Supp. 969 (S.D. Mississippi, 1991)
Fairfax County Board of Supervisors v. Culbertson Construction Co.
12 Va. Cir. 118 (Fairfax County Circuit Court, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
722 F.2d 1160, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fidelity-deposit-co-of-maryland-v-bristol-steel-iron-works-inc-ca4-1983.