Fairfax County Board of Supervisors v. Culbertson Construction Co.

12 Va. Cir. 118, 1987 Va. Cir. LEXIS 199
CourtFairfax County Circuit Court
DecidedNovember 17, 1987
DocketCase No. (Law) 69951
StatusPublished
Cited by3 cases

This text of 12 Va. Cir. 118 (Fairfax County Board of Supervisors v. Culbertson Construction Co.) is published on Counsel Stack Legal Research, covering Fairfax County Circuit Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fairfax County Board of Supervisors v. Culbertson Construction Co., 12 Va. Cir. 118, 1987 Va. Cir. LEXIS 199 (Va. Super. Ct. 1987).

Opinion

By JUDGE THOMAS A. FORTKORT

This case involves an indemnity agreement between Republic Insurance Company and Culbertson Construction Company. The agreement was executed so that Culbertson could secure performance bonds on a construction contract it had with Fairfax County. When Culbertson defaulted on the project, the County sued Culbertson as obligor and Republic as surety on the performance bonds. Pursuant to a subsequent settlement agreement, the County released Republic which in turn agreed to fulfill Culbertson’s obligations.

Republic hired The Kauffman Group to finish the project. It then filed a cross-claim against Culbertson and the other indemnitors seeking reimbursement under the Indemnity Agreement for its expenses in completing the job.

At trial, Plaintiff attempted to establish that Republic negligently permitted Kauffman’s work to exceed the terms of the original contract between Culbertson and the County.

Essentially, Culbertson alleges that Kauffman satisfies the inspection requirements of the County by exceeding the scope of the project for the benefit of the sub-division homeowners, who then stop complaining to the County about the contractor’s work. Republic responded to this charge by labelling Culbertson as an inexperienced contractor [119]*119who used equipment inadequate for the undertaking and who was loathe to expend the funds needed to finish the project in a workmanlike manner.

Culbertson says that Republic is entitled to reimbursement only for those items which fall within the contract and that in this case, going beyond the contract was either negligently done or done in bad faith by Republic. Republic asserts that, under the terms of the Indemnity Agreement,1 it is entitled to reimbursement for all expenditures made "in good faith" to complete the project, "whether liable or not ... whether necessary or not." In short, Republic contends the Agreement absolves it from its own negligence, as long as the expenditures were made in good faith.

I. Surety Can Indemnify Itself Against Its Own Negligence

The majority view of courts who have examined surety indemnification contracts containing language similar to the case at bar uphold such provisions. There is no Virginia case authority which addresses the precise issue as to the interpretation of these clauses in indemnity agreements.

Since no Virginia authority directly adopts or refutes the majority view, the Court may refer to established indemnity principles and public policy considerations to find that a surety is entitled to reimbursement for only his reasonable expenditures.

[120]*120II. Argument - The Majority Rule and Some Distinctions

Suretyship is a relation whereby one person, the surety, is answerable for the obligations of another, his principal, upon the latter’s default. It is essentially a contractual relation which may be created by either express contract or operation of law. Whether and to what extent a surety is entitled to reimbursement from his principal for costs incurred in satisfying the principal’s obligations depends largely on how the suretyship arose.

In suretyships implied at law, the rights and obligations of the parties are generally determined by common law indemnity principles and equitable considerations. The same is not true in suretyships created by express contract. The majority of jurisdictions which have considered the surety’s right to reimbursement under an indemnity agreement rely upon the actual contractual language employed. As the United States Court of Appeals for the Fourth Circuit has noted, " ‘resort to implied indemnity principles is improper when an express indemnification contract exists’; when there is such an express indemnification contract, ‘a surety is entitled to stand upon the letter of his contract’." Fidelity & Deposit Co. of Maryland v. Bristol Steel, 722 F.2d 1160, 1163 (4th Cir. 1983) (quoting Com'l Ins. Co. of Newark v. Pacific-Peru Const., 558 F.2d 948, 953 (9th Cir. 1977).

In Bristol Steel the court construed contractual language virtually identical to that in the case at bar. The principal claimed that his surety failed to exercise good faith when it paid a bond although the principal’s liability had not been established. The court held that the surety was nevertheless reasonably justified in paying the bond in order to prevent its disqualification as surety on future projects. In reaching its decision the court noted that the contractual provisions did not violate public policy and were uniformly upheld subject to only one exception: when payment is made fraudulently or in bad faith. 722 F.2d 1163. The court also found that the principal knew of the payment before it was made and, in failing to object, acquiesced in the surety’s performance.

The rule in Bristol Steel has been adopted by virtually every jurisdiction that has considered the issue and [121]*121supports the position that Republic asks this Court to adopt. Indeed the cases upon which Republic relies expressly support the view. See Continental Casualty v. Marman Development Corp., 198 N.Y.S.2d 375 (N.Y. Sup. Ct. 1960); United States Fidelity and Guarantee Co. v. Napier Electric & Construction Co., 571 S.W.2d 644 (Ky. App. 1978), and Hartford Accident and Indemnity Co. v. Millis Roofing and Sheet Metal, Inc., 418 N.E.2d 645 (Mass. App. 1981).

With the exception of Continental Casualty, none of the cases above involved allegations that the surety was negligent in exceeding the terms of the original contract. In Bristol Steel the surety paid the penal amount of the original contract without establishing the principal’s liability. In Napier Electric, the surety satisfied the principal’s obligation by paying the "amount necessary to complete the performance of the contract." 571 S.W.2d at 646. In Millis Roofing, the surety completed the contract in good faith despite its failure to investigate the claim and defend his principal before paying.

Although Continental Casualty involved work which allegedly exceeded the original contract, the court found that the principal had sufficient notice of the claims against him yet failed to object to the surety’s proposed action. As a result, the court held that the principal could not contest the surety’s performance when, under the indemnity agreement, he had every right to dispute or litigate the claim. 198 N.Y.S.2d at 376.

In the case at bar, Culbertson had the right to contest the County’s suit but agreed to the settlement between the County and Republic. Culbertson probably had little chance of defending his suit against the County because of his numerous failures to meet the original deadline and the extended deadlines. Culbertson through his counsel did object to the work being done by Kauffman as beyond his contract with the County.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Collier v. Land & Sea Restaurant Co.
972 F. Supp. 2d 870 (W.D. Virginia, 2013)
Sanderling v. Donohoe Co.
47 Va. Cir. 345 (Fairfax County Circuit Court, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
12 Va. Cir. 118, 1987 Va. Cir. LEXIS 199, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fairfax-county-board-of-supervisors-v-culbertson-construction-co-vaccfairfax-1987.