Board of Supervisors v. Ecology One., Inc.

245 S.E.2d 425, 219 Va. 29, 1978 Va. LEXIS 156
CourtSupreme Court of Virginia
DecidedJune 9, 1978
DocketRecord 770268 and 770269
StatusPublished
Cited by27 cases

This text of 245 S.E.2d 425 (Board of Supervisors v. Ecology One., Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Board of Supervisors v. Ecology One., Inc., 245 S.E.2d 425, 219 Va. 29, 1978 Va. LEXIS 156 (Va. 1978).

Opinion

I’ANSON, C.J.,

delivered the opinion of the Court.

This action was instituted by the Board of Supervisors of Fairfax County (County) against Ecology One, Inc., a residential housing development corporation, Forrest W. Stout, Edward Gwathmey, Jr., Buford W. Duke, Jr., R. David Winesett, Jr., and James J. Hricko, all hereinafter referred to collectively as Ecology, and Republic Insurance Company (Republic) to recover judgment jointly and severally against Ecology as principal, and Republic as surety on a bond, as a result of Ecology’s alleged breach of its contract with the County to construct streets and drainage facilities in a residential subdivision Ecology was developing in Fairfax County.

Pursuant to Rule 3:10(a), Rules of Court, Republic filed a third party motion for judgment against H.L. Rust Company (Rust) alleging that Rust would be indebted to Republic if the County obtained a judgment against it in this proceeding.

*31 The case was heard by a jury but, at the conclusion of the County’s evidence, the trial court sustained the motion of Ecology and Republic to strike the County’s evidence and summary judgment was entered accordingly. The County and Rust filed separate petitions for appeal, which we granted and consolidated for hearing.

The evidence shows that Ecology was the subdivider and developer of Rainbow, a residential subdivision. Pursuant to a County ordinance and State statute concerning subdivisions and approval of plats relating thereto, Ecology entered into a contract with the County on May 9,1973, in which it agreed to construct the public streets and drainage facilities as shown on its plats and plans of the Rainbow subdivision in accordance with the County and State standards. The contract provided that Ecology would complete the public improvements by May 9, 1976. Ecology also executed a bond on May 9, 1973, as principal, with Republic as surety and the County as obligee, in the amount of $172,000 guaranteeing the performance of its contract with the County.

On March 1, 1974, Ecology obtained a construction loan from Rust which was secured by a deed of trust on certain lots within the Rainbow subdivision. In August 1974, Rust made an additional loan to Ecology in an attempt to shore up what appeared to be problems with cost overruns which were preventing the completion of residences and public improvements in the subdivision.

In October 1974, a county public utility inspector was assigned to the subdivision to make necessary inspections. He testified that “there was very little activity” at the job site at that time; that there were no approved plans present at the construction site and there did not appear to be adequate supervision for construction of the streets and drainage facilities; that in the early months of 1975, the level of activity within the subdivision had deteriorated to the point where work had come to a complete halt on both the public and non-public improvements; that during this period of time, electricity and telephone service for the job headquarters had been cut off; and that it was necessary to issue notices to Ecology for its violation of the siltation and erosion control requirements, which it never remedied.

In the meantime, Ecology had defaulted on the payments of its loans to Rust and a foreclosure sale was held on April 2,1975. Rust was the only bidder on the property. Eight of the lots were *32 improved in various stages of construction and nine were unimproved. Four houses in the subdivision had been completed and were occupied notwithstanding the fact that the streets were surfaced with gravel only, and drainage facilities were practically nonexistent.

At the time of the foreclosure, street improvements were 60 percent complete. After the foreclosure sale, an official of Ecology told the county’s public utility inspector that “the street work [was] what did them in.” Ecology made no attempt whatsoever to complete any public improvements after the foreclosure. It took the position that it was divested of control over the work to be performed in the areas it had dedicated to public use.

Relying on the complete lack of activity on the part of Ecology with respect to the public improvements within the subdivision, the abandonment of the job site, and the deteriorating conditions at the site, the officials of the County concluded that Ecology had no intention of performing its obligations under its contract. So on June 25, 1975, the County filed this action against Ecology and Republic on the performance bond.

After obtaining title to the lots sold at the foreclosure sale, Rust applied for permits to complete the work on the houses in order to minimize its loss. The County refused to issue the permits to Rust unless it agreed to complete the street and drainage improvements within the subdivision in accordance with the standards stipulated in the county’s contract with Ecology. Three months after the County instituted this action against Ecology and Republic to recover on the performance bond, the County issued permits to Rust conditioned upon its completion of the street and drainage work in the subdivision. The County also assigned to Rust any money received by it in the pending action against Ecology and Republic, not to exceed the amount actually spent by Rust. Rust completed the street and drainage facilities in accordance with the requirements in Ecology’s contract with the County at a cost of $171,725.03, which all the parties to this action stipulated was reasonable. At no time did Ecology or Republic perform, or offer to perform, the work after the foreclosure sale.

The trial court, in sustaining Ecology’s and Republic’s motions to strike plaintiff’s evidence, held (1) that the County had not made out a prima facie case with respect to the question of anticipatory breach of contract; and (2) that the assignment to Rust was invalid. *33 The court further held that the surety bond was “an indemnifying bond and was not a penal or forfeiture bond.”

The County contends the trial court erred in holding as a matter of law that it had not made out a prima facie case showing that Ecology had abandoned the Rainbow subdivision at the time this action was instituted.

In order to maintain a cause of action for an anticipatory breach of contract, it is not necessary that there be an unequivocal or positive expression of abandonment if the acts and conduct of the obligor evince an intent wholly inconsistent with the intention to perform its contract. Roehm v. Horst, 178 U.S. 1, 8 (1900).

Under the law in Virginia, the abandonment of a contract will give rise to an action for anticipatory breach. We said in Mut. R. Fund Ass’n v. Taylor, 99 Va. 208, 37 S.E. 854 (1901) that:

“[W]hen one party to a contract has entirely abandoned it, or has absolutely refused to perform it, the other party may elect to sue on it without waiting for the time of performance to arrive.” 99 Va. at 213, 37 S.E. at 855-56.

Whether there has been an abandonment of a public works contract depends on the particular facts and circumstances of each case.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Brad Ferrell v. Playfly, LLC
Court of Appeals of Virginia, 2026
Under Wild Skies v. NRA
Supreme Court of Virginia, 2025
Bennett v. Sage Payment Solutions, Inc.
710 S.E.2d 736 (Supreme Court of Virginia, 2011)
Enomoto v. Space Adventures, Ltd.
624 F. Supp. 2d 443 (E.D. Virginia, 2009)
Merrifield Industrial Corp. v. Glaze
77 Va. Cir. 264 (Fairfax County Circuit Court, 2008)
Elite Entertainment, Inc. v. Khela Bros. Entertainment Inc.
396 F. Supp. 2d 680 (E.D. Virginia, 2005)
Lee v. Garrett Homes of Virginia, L.C.
64 Va. Cir. 136 (Spotsylvania County Circuit Court, 2004)
Bazzle v. Bazzle
561 S.E.2d 50 (Court of Appeals of Virginia, 2002)
Nowland v. Tri Core, Inc.
60 Va. Cir. 469 (Virginia Circuit Court, 2000)
LENDERS FINANCIAL CORPORATION v. Talton
455 S.E.2d 232 (Supreme Court of Virginia, 1995)
Hurt v. Hurt
433 S.E.2d 493 (Court of Appeals of Virginia, 1993)
Transdulles Center, Inc. v. USX Corp.
976 F.2d 219 (Fourth Circuit, 1992)
Transdulles Centre Ltd. Partnership v. USX Corp.
761 F. Supp. 430 (E.D. Virginia, 1991)
FSG Capital Corp. v. Bristol Associates
22 Va. Cir. 231 (Fairfax County Circuit Court, 1990)
Carley Capital Group v. City of Newport News
709 F. Supp. 1387 (E.D. Virginia, 1989)
Fairfax County Board of Supervisors v. Culbertson Construction Co.
12 Va. Cir. 118 (Fairfax County Circuit Court, 1987)
Goddin v. Lerner Stores
8 Va. Cir. 238 (Alexandria County Circuit Court, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
245 S.E.2d 425, 219 Va. 29, 1978 Va. LEXIS 156, Counsel Stack Legal Research, https://law.counselstack.com/opinion/board-of-supervisors-v-ecology-one-inc-va-1978.