Clearwater Assocs., Inc. v. FH BRIDGE & SON
This text of 365 A.2d 200 (Clearwater Assocs., Inc. v. FH BRIDGE & SON) is published on Counsel Stack Legal Research, covering New Jersey Superior Court Appellate Division primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
CLEARWATER ASSOCIATES, INC., A NEW JERSEY CORPORATION, ET AL., PLAINTIFFS-APPELLANTS,
v.
F.H. BRIDGE & SON, CONTRACTORS, FRANK H. BRIDGE AND ASTRID C. BRIDGE, INDIVIDUALLY AND REPUBLIC INSURANCE COMPANY, ETC., DEFENDANTS-RESPONDENTS.
Superior Court of New Jersey, Appellate Division.
Before Judges BISCHOFF, MORGAN and COLLESTER.
Mr. Robert S. Moraff argued the cause for appellants (Messrs. Marcus, Rosen, Breslow, Levy, Jaffe & Fiorello, attorneys).
*224 Mr. Louis Aueracher, Jr. argued the cause for respondent Republic Insurance Company.
PER CURIAM.
Plaintiffs Borough of Butler (borough) and Clearwater Associates (Clearwater) appeal from a judgment of involuntary dismissal entered at the conclusion of plaintiffs' case. The underlying suit was brought to enforce the obligation of the defendant surety, Republic Insurance Company, on a performance bond.
Clearwater's predecessor in title, F.H. Bridge & Son, sought to develop residential property within the borough and secured the necessary subdivision approvals for the contemplated work. In compliance with the conditions to the approval, Bridge executed, on October 26, 1966, a performance bond, with defendant as surety and the borough as obligee, in the penal sum of $20,000, conditioned for the construction by Bridge of a number of improvements to the site (such as curbs, streets, sidewalks, water mains and the like), all of which were to be completed within one year of the date of the bond. Because of financial difficulties, Bridge was unable to complete the development or the improvements covered by the bond, and abandoned the project, leaving two partially completed houses, partially completed sewers and curbs and rough graded streets. Neither Bridge, the principal, nor the surety ever completed the improvements despite written requests from the borough to do so.
Thereafter an estimate of the cost of completing the improvements, prepared by the borough's engineer, disclosed that the cost of the improvements had risen to an estimated $55,000, thus requiring the expenditure of $35,000 of municipal funds over the full amount of the bond. Because of the prospective high cost to the borough, any thought of completion of the improvements was rejected.
Nothing was done with respect to the incomplete development until May 16, 1972 when the borough entered into an agreement with Clearwater which had previously acquired the *225 property in question. In this agreement Clearwater agreed to complete the improvements in return for issuance of certificates of occupancy and building permits. Paragraph 13 of this agreement provided:
Both parties hereto agree to cooperate in efforts to obtain from the Republic Insurance Company, surety on the original performance bond posted by the original developer, full or partial satisfaction of its obligations by reason of the default of the original Developer, it being understood that the Borough's participation may be limited by such applicable law as investigation shall reveal.
Clearwater thereafter completed the improvements and sold 11 of the houses in the development at a profit. Plaintiffs have stipulated that the borough made no payment toward the improvements and that improvements were made and paid for by Clearwater.
At the close of plaintiffs' proofs and on defendant's motions, the trial court, sitting without a jury, entered a judgment of involuntary dismissal on the grounds that the borough's cause of action against the surety on the performance bond was not assignable and hence Clearwater, the purported assignee, acquired no rights under the bond by the agreement of May 16, 1972; Clearwater was not in privity with the surety and hence could assert no claim against it; since the borough made no payments on account of the improvements covered by the bond, it suffered no damage from the bonding company's default, and therefore can recover nothing on the bond.
At trial all parties implicitly conceded the import of the above-quoted provision of the May 16, 1972 agreement as effecting an assignment of the borough's rights under the bond to Clearwater. During oral argument the fact of assignment was expressly conceded by all parties. Hence, despite our doubts as to whether this agreement did constitute an assignment of those rights and because resolution of the issue is not material to the issue posed, we confront the problem posed as if the agreement had its stipulated effect.
*226 Defendant surety contends here, as it did before the trial court, that neither the bond itself nor the statutes prescribing the consequences of a default in the guaranteed performance make provision for the assignability of a municipality's claim on such a bond, and hence the purported assignee thereof lacks standing to enforce the surety's obligation thereon. The performance bond in question was issued in accordance with the Municipal Planning Act. N.J.S.A. 40:55-1.1.[1] Before final approval of a subdivision, a governing body may require the installation of certain improvements which it may deem to be necessary or appropriate in the public interest, or the furnishing of a performance guarantee in lieu thereof. N.J.S.A. 40:55-1.21. N.J.S.A. 40:55-1.22 provides, in pertinent part:
If the required improvements shall not have been installed in accordance with the performance guarantee, the obligor and surety, if any, shall be liable thereon to the municipality for the reasonable cost of the improvements not installed and upon the receipt of the proceeds thereof the municipality shall install such improvements.[2]
Although it is quite true, as the surety contends, that neither this provision nor the bond itself makes claims thereunder assignable, it is equally clear that there exists no provision forbidding the assignment thereof. The issue is one of novel impression in this State. Authority elsewhere is not plentiful. Two cases, both somewhat distinguishable, have confronted the issue. In Morro Palisades Co. v. Hartford Acc. & Indem. Co., 52 Cal.2d 397, 340 P.2d 628 (Sup. Ct. (1959), the assignee of a county's rights on a performance bond sought to compel performance by the bonding company. The bond purported to guarantee Westfall's improvements of all the streets in a subdivision he was developing. As in the *227 present case, Westfall commenced improving the roads but abandoned the work before completion, and the surety refused to honor its obligation on the bond. The obligee county thereafter assigned its rights in the bond to plaintiff, who owned 50% of the land being developed. The California Supreme Court affirmed the trial court's dismissal of the assignee's claim, holding the county's claim under the bond not to be assignable, saying:
* * * the county presumptively is entitled to receive the road work which Westfall agreed to complete. And here the right to recover under the bond appears clearly to be a right of the county rather than of the owner of a portion of the property which might be affected by the default. * * * It is the county which is indemnified by the express terms of the bond against loss * * * The general rule appears to be that if a public improvement faithful performance bond runs to the public body, action thereon must be brought in that body's name. [340 P.2d at 631]
According to the Morro
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
365 A.2d 200, 144 N.J. Super. 223, Counsel Stack Legal Research, https://law.counselstack.com/opinion/clearwater-assocs-inc-v-fh-bridge-son-njsuperctappdiv-1976.