Essex County Preservation Ass'n v. Campbell

399 F. Supp. 208, 7 ERC 2136
CourtDistrict Court, D. Massachusetts
DecidedJuly 9, 1975
DocketCiv. A. 74-2680-M
StatusPublished
Cited by11 cases

This text of 399 F. Supp. 208 (Essex County Preservation Ass'n v. Campbell) is published on Counsel Stack Legal Research, covering District Court, D. Massachusetts primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Essex County Preservation Ass'n v. Campbell, 399 F. Supp. 208, 7 ERC 2136 (D. Mass. 1975).

Opinion

OPINION

BOWNES, District Judge, Sitting by Designation.

This is a petition for a preliminary injunction based on a complaint in which the plaintiffs allege that the defendants have knowingly failed to fulfill their obligations of good faith compliance with the National Environmental Policy Act of 1969, 42 U.S.C. § 4321 et seq. Jurisdiction is pursuant to 5 U.S. C. §§ 701-706 and 28 U.S.C. § 1331.

Counsel have agreed that only the first and third causes of action as set forth in the complaint are in issue as far as the preliminary injunction is concerned.

The plaintiffs seek to enjoin any further work involving the reconstruction and widening of a portion of Interstate Route 95 from four to eight lanes. The road in question begins at the DanversMiddleton Town Line approximately eighteen miles north of Boston and ends at the Merrimack River at the north edge of Newburyport, approximately three miles south of the New Hampshire border. The highway to be widened is a four lane divided highway passing through the Towns of Middleton, Tops-field, Boxford, Rowley, Georgetown, Newbury, West Newbury, and the City of Newburyport. The southern terminus of the proposed reconstruction will join an eight lane highway connecting to Route 128. The northern terminus will connect to the New Hampshire section of Route 1-95 running from the Merrimack River to the City of Portsmouth. The New Hampshire section is currently being widened to eight lanes. Interstate Route 95 is the major north-south route on the Atlantic Coast and provides a direct route from the urban centers of the Atlantic seaboard to New Hampshire, Maine, and the Maritime Provinces of Canada.

A hearing was held on the motion for a preliminary injunction on June 27, 1975, at the Federal Courthouse in Boston. At the hearing, I made several rulings affecting the posture of the case which I now reiterate. I rule that, in determining whether or not the requirements of NEPA have been met, a federal court has neither the duty nor, indeed, the right to engage in a substantive review and in-depth analysis of the Environmental Impact Statement (EIS). The role of the court is restricted to determining whether or not the EIS meets the procedural requirements of NEPA. The plaintiffs claim that the EIS is defective because it failed to take into consideration the so-called energy crisis. I rule now, as I ruled at the hearing, that *211 the question of whether or not there is an energy crisis and, if so, the impact of such a crisis on automobile traffic in Massachusetts is highly speculative and need not, as a matter of law, be considered in formulating the EIS. I exclude now, as I excluded at the hearing, any evidence as to the validity and accuracy of traffic counts. As stated at the hearing, I consider all affidavits and exhibits that have been filed to be evidence and part of the record in this case.

The pleadings and exhibits show that the basis of the opposition to the reconstruction and widening of 1-95 is that such reconstruction is not justified because, as a result of a combination of the energy crisis and the Sargeant moratorium, there will be a reduction in traffic or, at least, the increase predicted by the highway officials will not materialize. While I take judicial notice of the fact that any increase in the size of a highway is bound to have some deleterious effect on the environment, there is no claim here that any portion of the area affected is particularly fragile or will be harmed to an extent beyond that which is ordinarily to be anticipated by highway reconstruction.

Before treating the legal issues, certain basic facts must be noted. The final EIS was published in September of 1973, and was approved by the Department of Transportation in January of 1974. This suit was instituted July 17, 1974, and plaintiffs’ request for a temporary restraining order was denied on the same day. The project is divided into four contracts:

First Contract — Total price, $14,879,-387; length, 4.4 miles; completion date, November 6, 1976; status of construction as of June 25, 1975, 36% complete.

Second Contract — Total price, $18,-889,858; length, 5.7 miles; completion date, July 30, 1977; status of construction as of June 25, 1975, 10% complete.

Third Contract — Total price, $11,577,-499; length, 4.1 miles; completion date, July 30, 1977; status of construction as of June 25, 1975, 13% complete.

Fourth Contract — Total price, $9,246,-210; length, 2.7 miles; completion date, November 27, 1976; status of construction as of June 25,1975, 25% complete.

There are three main issues:

(1) Whether the preparation of the EIS by Fay, Spofford and Thorndike was fatally defective because it was also design engineer for part of the project;

(2) Whether the moratorium on highway construction in the Boston area imposed by Governor Sargeant prior to the start of construction on this project was considered sufficiently in the EIS and, if not, whether such failure requires a supplement to the EIS; and

(3) Whether federal funding was improperly given because of the Commonwealth’s failure to timely prepare an Action Plan pursuant to 23 U.S.C. § 109(h).

THE ROLE OF FAY, SPOFFORD AND THORNDIKE

The first issue is whether NEPA proscribes the delegation of EIS preparation to a State employed private consulting firm that is also the design engineer for a portion of the project in question. 1

NEPA requires that the “responsible official” prepare and circulate to the public and various commenting agencies, a detailed statement disclosing the adverse environmental effects of any “major Federal action significantly affecting the quality of the human environment, . . . .” 42 U.S.C. § 4332(C).

There is a present split in the Circuits on the issue of whether the federal agency may delegate the preparation of the EIS to a state agency.

The Second Circuit held in Conservation Soc. of S. Ver., Inc. v. Secretary of Tran., 508 F.2d 927 (2nd Cir. 1974), Petition for cert. filed, sub nom., Coleman v. Conservation Society of Southern Vermont, Inc., 43 U.S.L.W. 3648 (U.S. *212 May 9, 1975) (No. 74-1413), that the FHWA has an exclusive nondelegable duty to prepare the EIS. 2 Other Circuits have held that the responsibility for preparing an EIS may be delegated to state agencies, provided that there is “significant federal participation.” Fayetville Area Chamber of Commerce v. Volpe,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

New Hanover Township v. United States Army Corps of Engineers
796 F. Supp. 180 (E.D. Pennsylvania, 1992)
Maryland Wildlife Federation v. Lewis
560 F. Supp. 466 (D. Maryland, 1983)
Webster Associates v. Town of Webster
85 A.D.2d 882 (Appellate Division of the Supreme Court of New York, 1981)
Grazing Fields Farm v. Neil Goldschmidt
626 F.2d 1068 (First Circuit, 1980)
Aertsen v. Landrieu
488 F. Supp. 314 (D. Massachusetts, 1980)
Citizens for Responsible Area Growth v. Adams
477 F. Supp. 994 (D. New Hampshire, 1979)
Save Our Wetlands, Inc. (Sowl) v. Rush
424 F. Supp. 354 (E.D. Louisiana, 1976)
Mont Vernon Preservation Society v. Clements
415 F. Supp. 141 (D. New Hampshire, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
399 F. Supp. 208, 7 ERC 2136, Counsel Stack Legal Research, https://law.counselstack.com/opinion/essex-county-preservation-assn-v-campbell-mad-1975.