Ellen v. A.C. Schultes of Maryland, Inc.

615 S.E.2d 729, 172 N.C. App. 317, 2005 N.C. App. LEXIS 1425, 2005 WL 1802421
CourtCourt of Appeals of North Carolina
DecidedAugust 2, 2005
DocketCOA04-1320
StatusPublished
Cited by23 cases

This text of 615 S.E.2d 729 (Ellen v. A.C. Schultes of Maryland, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ellen v. A.C. Schultes of Maryland, Inc., 615 S.E.2d 729, 172 N.C. App. 317, 2005 N.C. App. LEXIS 1425, 2005 WL 1802421 (N.C. Ct. App. 2005).

Opinion

TIMMONS-GOODSON, Judge.

A.C. Schultes of Maryland, Inc. (“AC Schultes”), A.C.S. & Sons, Inc. (“ACS”), John O’Brien (“O’Brien”), and William Jefferys (“Jefferys”) (collectively, “defendants”) appeal the trial court order denying their motions to compel arbitration of a suit filed by Rebecca Hoyle Ellen (“Rebecca”), Angela Ellen (“Angela”), and Florence Oakley (“Oakley”) (collectively, “plaintiffs”). 1 Because we conclude that the arbitration clause at issue is not enforceable against plaintiffs, we affirm the order of the trial court.

The facts and procedural history pertinent to the instant appeal are as follows: Plaintiffs are shareholders in Atlantic Coast Construction & Utility, Inc. (“ACCU”), a construction company specializing in water and sewer utilities work. In 1999, ACCU entered into a series of agreements with AC Schultes, whereby ACCU would serve as subcontractor on several construction projects awarded to and supervised by AC Schultes. Five of these projects were referred to as the “Water Wells,” “SJAFB,” “Potable Water Lines,” “Burton,” *318 and “Wash Racks” projects. The subcontracts of these five projects contained the following pertinent arbitration clause:

Any controversy or claim between the Contractor and the Subcontractor arising out of or related to this Subcontract, or the breach thereof, shall be settled by arbitration ....

On several occasions in Spring 2000, officers of ACCU and AC Schultes met to discuss the proposed partial purchase of ACCU by AC Schultes. ACCU eventually turned down AC Schultes’ proposals, and ACCU and AC Schultes continued to work with one another. However, the relationship between ACCU and AC Schultes subsequently deteriorated, and on 12 September 2001, AC Schultes filed a complaint against ACCU, requesting that the trial court require arbitration of all claims arising out of the Water Wells, SJAFB, Potable Water Lines, Burton, and Wash Racks projects. AC Schultes also requested a declaration of the financial obligations and liabilities of the parties on a sixth project, the North Lenoir project. The trial court thereafter ordered the parties to arbitrate all claims and controversies arising out of the projects.

On 3 January 2004, plaintiffs filed a complaint against defendants, alleging unfair and deceptive trade practices and tortious interference with prospective business advantages. In their complaint, plaintiffs allege that at or around the time ACCU declined AC Schultes’ purchase attempts, O’Brien “began a course of inappropriate and unwanted sexual advances” toward Angela. Plaintiffs allege that although Angela “attempted to ignore [O’Brien’s] behavior and continue the business relationship” between ACCU and AC Schultes, O’Brien continued to contact and harass Angela by “professing his love” for her and by “following] her to . . . pursue his desired illicit relationship.” Plaintiffs assert that after repeated rejections, O’Brien “apparently got the message that [Angela] would not give in to his carnal desire” in December 2000. However, AC Schultes nevertheless “failed and refused to pay ACCU for work performed by ACCU and for materials supplied'by ACCU on virtually all projects ACCU was working on.”

According to plaintiffs’ complaint, the relationship between ACCU and AC Schultes subsequently “broke down further, to the point that the principals of ACCU were taking personal money and obtaining personal loans to complete the projects ACCU had with [AC Schultes][.]” Jefferys and O’Brien thereafter allegedly “contacted ACCU vendors and subcontractors and slandered ACCU by stating *319 that ACCU would not pay its bills even though it had been paid by [AC Schultes], which they knew not to be true.” Jefferys and O’Brien also allegedly “asked at least some vendors not to do further business with ACCU[,]” and “stated to ACCU vendors that [AC Schultes] was going to put ACCU out of business.” Plaintiffs assert that Jefferys and O’Brien also “contacted ACCU employees and told them that ACCU was going to be put out of business and told them they should come to work for [AC Schultes] while they could[,]” and “filed fraudulent documentation with the Federal Government to obtain payment for work performed by ACCU, and then continued to withhold payment to ACCU for the work performed.” According to plaintiffs, “ [t]he actions of Jefferys and O’Brien were taken with the deliberate purpose of destroying the plaintiffs’[] business and reputations in the very limited field of utilities contracting [,]” and the actions “were taken in retaliation for [Angela’s] refusal of [O’Brien’s] illegal, unwanted and adulterous sexual advances toward her.” Plaintiffs contend that the actions of Jefferys and O’Brien were on behalf of AC Schultes, and because ACS received profits from the operation of AC Schultes, it was a “knowing beneficiary” of the actions and thus should be responsible for the damages resulting from the alleged actions.

As a result of the alleged actions, plaintiffs assert that by August 2001, “all of ACCU’s funds were exhausted, all of [plaintiffs’] funds were depleted, and all of their ability to obtain credit was depleted as well.” Plaintiffs further assert that after the parties’ “last attempt to resolve the payment issues” was unsuccessful, AC Schultes “almost immediately filed for arbitration on five projects for which it owed ACCU money and filed a lawsuit in Lenoir County[.]” AC Schultes thereafter allegedly “paid exorbitant amounts of money to other contractors for the purported purpose of completing the outstanding work[,]” in an effort to “establish[] enough ‘back charges’ against ACCU [so] as to cancel out all amounts owed to ACCU.” Plaintiffs allege that “[a]s a direct result of the foregoing illegal actions, plaintiffs have lost their entire investment in the company as well as incurred substantial additional damages for loss of future earnings and return on capital,” and further “lost the prospective business advantage of having vendors and subcontractors that will work with them to conduct future business in the utilities field, in a manner customary for that field.”

On 19 February 2004, defendants filed a motion to dismiss plaintiffs’ claim pursuant to N.C. Gen. Stat. § 1A-1, Rule 12(b)(6). The trial *320 court subsequently denied defendants’ motion, and on 23 April 2004, defendants filed separate answers to plaintiffs’ complaint as well as separate motions to compel arbitration of the issues in the complaint. Following a hearing on the matter, on 14 June 2004, the trial court issued an order denying defendants’ motions to compel arbitration. It is from this order that defendants appeal.

The only issue on appeal is whether the trial court erred by. denying defendants’ motions to compel arbitration. Defendants argue that plaintiffs and their complaint are subject to arbitration. ■ We disagree.

We note initially that a trial court’s decision to deny a motion to compel arbitration is interlocutory in nature. See Raspet v. Buck, 147 N.C. App. 133, 135, 554 S.E.2d 676, 677 (2001). Nevertheless, this Court has previously held that “ ‘[t]he right to arbitrate a claim is a substantial right which may be lost if review is delayed, and an order denying arbitration is therefore immediately appealable.’ ”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Untitled Case
W.D. North Carolina, 2026
Multari v. Fakhoury
E.D. North Carolina, 2024
Ayers v. Markiewicz
E.D. North Carolina, 2024
Jarman v. Twiddy & Co. of Duck
Court of Appeals of North Carolina, 2023
Jackson v. Home Depot U.S.A.
Court of Appeals of North Carolina, 2021
Piascik v. Biomass Controls PBC
E.D. North Carolina, 2020
Smith Jamison Constr. v. APAC-Atlantic, Inc.
811 S.E.2d 635 (Court of Appeals of North Carolina, 2018)
Big League Analysis, LLC v. Office of the Comm'r of Baseball
2016 NCBC 66 (North Carolina Business Court, 2016)
Talisman Software, Sys. & Servs., Inc. v. Atkins
2016 NCBC 1 (North Carolina Business Court, 2016)
Neusoft Med. Sys., United States, Inc. v. Neuisys, LLC
774 S.E.2d 851 (Court of Appeals of North Carolina, 2015)
Bergenstock v. legalzoom.com, Inc.
2015 NCBC 63 (North Carolina Business Court, 2015)
Heron Bay Acquisition, LLC v. United Metal Finishing, Inc.
2014 NCBC 15 (North Carolina Business Court, 2014)
Flexible Foam Products, Inc. v. Vitafoam Inc.
980 F. Supp. 2d 690 (W.D. North Carolina, 2013)
MORTON v. IVEY, McCLELLAN, GATTON & TALCOTT, LLP
2013 NCBC 23 (North Carolina Business Court, 2013)
TP, Inc. v. Bank of America, N.A. (In re TP, Inc.)
486 B.R. 698 (E.D. North Carolina, 2013)
Pearson v. Hilton Head Hospital
733 S.E.2d 597 (Court of Appeals of South Carolina, 2012)
Erichsen v. RBC Capital Markets, LLC
883 F. Supp. 2d 562 (E.D. North Carolina, 2012)
Carter v. TD AMERITRADE HOLDING CORP.
721 S.E.2d 256 (Court of Appeals of North Carolina, 2012)
Klopfer v. Queens Gap Mountain, LLC
816 F. Supp. 2d 281 (W.D. North Carolina, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
615 S.E.2d 729, 172 N.C. App. 317, 2005 N.C. App. LEXIS 1425, 2005 WL 1802421, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ellen-v-ac-schultes-of-maryland-inc-ncctapp-2005.