Smith Jamison Constr. v. APAC-Atlantic, Inc.

811 S.E.2d 635, 257 N.C. App. 714
CourtCourt of Appeals of North Carolina
DecidedFebruary 6, 2018
DocketCOA17-761
StatusPublished
Cited by4 cases

This text of 811 S.E.2d 635 (Smith Jamison Constr. v. APAC-Atlantic, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Smith Jamison Constr. v. APAC-Atlantic, Inc., 811 S.E.2d 635, 257 N.C. App. 714 (N.C. Ct. App. 2018).

Opinion

TYSON, Judge.

*714 Yates Construction Company, Inc. ("Yates") appeals the superior court's order, which denied Yates' motion to compel Smith Jamison Construction to submit to binding arbitration and to stay all other proceedings *637 in the dispute between these parties. We affirm the trial court's denial of Yates' motion asserting a right to demand arbitration.

I. Background

Smith Jamison Construction ("Jamison") is a concrete contractor based in Winston-Salem, North Carolina. In October 2012, Jamison entered into a contract (the "Subcontract") with APAC-Atlantic, Inc. ("APAC"), a general contractor, to construct catch basins, drop inlets, *715 concrete curbs, gutters, sidewalks, curb ramps, driveways, and concrete paved ditches along the Interstate 73 highway corridor.

Contained within section 22 of the Subcontract was a mandatory arbitration provision in which Jamison and APAC agreed to arbitrate claims arising out of or relating to the Subcontract as follows:

All claims or controversies arising out of or related to this Subcontract shall be submitted to and resolved by binding arbitration by a single arbitrator in any County and State where the project is located. The American Arbitration Association ("AAA") shall conduct the arbitration unless the parties mutually agree to use an alternative arbitration service. Judgment upon any award made by the arbitrator may be entered in any court having jurisdiction thereof, if necessary.

Yates is a separate North Carolina corporation, which has engaged in construction work with APAC and Jamison on past projects. Yates is neither a party to nor a signatory of the Subcontract between Jamison and APAC.

Jamison alleges, although it was awarded the Subcontract for the concrete work on Interstate 73, the APAC Project Manager exchanged emails with Yates' vice president on multiple times concerning a subcontract approval form, under which Jamison would further subcontract to Yates the curb work previously assigned to Jamison's scope of work under the Subcontract. Jamison further alleges it did not request nor authorize Yates to be added to the project as a sub-subcontractor, but that, "Yates was expecting to perform [Jamison's] work as early as July 2013, due to such representations from APAC." Jamison further alleges APAC expressly requested Jamison to allow Yates to subcontract the curb and gutter scope of work, but Jamison refused. Jamison asserts that after it refused, APAC started sending it daily complaint emails. On 20 December 2013, the Department of Transportation approved APAC's request to terminate Jamison and replace them with Yates. Jamison was informed that the Subcontract had been terminated.

Jamison filed a complaint against APAC and Yates on 13 April 2016, alleging that APAC had terminated Jamison and replaced it with Yates. Jamison also asserted claims against Yates for: (1) fraudulent misrepresentation; (2) tortious interference with a contract; (3) civil conspiracy; and (4) unfair and deceptive trade practices in violation of N.C. Gen. Stat. § 75-1.1 .

*716 Yates filed an answer on 14 June 2016, denied all allegations of wrongdoing and asserted, in part, "the presence of a mandatory and binding arbitration clause in the subcontract between [Jamison] and Defendant APAC[.]"

The trial court entered a consent order compelling arbitration between Jamison and APAC and staying the claims against APAC on 30 December 2016. In the consent order, Jamison and APAC agreed to stay the action with respect to their claims and to submit those claims to binding arbitration, based upon the arbitration provision contained in the Subcontract between Jamison and APAC.

Yates filed a motion to compel arbitration and stay court proceedings on 24 March 2017. Yates sought the court to order Jamison to arbitrate its claims against it. The trial court denied Yates' motions by an order entered 13 April 2017. Yates filed timely notice of appeal.

II. Jurisdiction

Although an order denying a party's motion to compel arbitration is interlocutory, this Court has repeatedly held that "[it] is immediately appealable because it involves a substantial right which might be lost if appeal is delayed." Prime South Homes, Inc. v. Byrd , 102 N.C. App. 255 , 258, 401 S.E.2d 822 , 825 (1991) (citing Sims v. Ritter Constr., Inc. , 62 N.C. App. 52 , 302 S.E.2d 293 (1983) ); N.C. Gen. Stat. §§ 1-277 (a), 7A-27(d)(1) (2017).

*638 Yates' interlocutory appeal is properly before us.

III. Standard of Review

"[The] trial court's conclusion as to whether a particular dispute is subject to arbitration is a conclusion of law, reviewable de novo by the appellate court." Raspet v. Buck , 147 N.C. App. 133 , 136, 554 S.E.2d 676 , 678 (2001). "Under de novo review, [this Court] consider[s] the matter anew and [is] free to substitute [its] judgment for that of the trial court." Westmoreland v. High Point Healthcare Inc. , 218 N.C. App. 76 , 79, 721 S.E.2d 712 , 716 (2012).

IV. Analysis

Yates argues the trial court erred in denying its motion to compel arbitration and stay the action.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
811 S.E.2d 635, 257 N.C. App. 714, Counsel Stack Legal Research, https://law.counselstack.com/opinion/smith-jamison-constr-v-apac-atlantic-inc-ncctapp-2018.