Elgard Corporation v. Brennan Construction Company

388 F.3d 30, 2004 U.S. App. LEXIS 21248
CourtCourt of Appeals for the Second Circuit
DecidedOctober 13, 2004
Docket00-9326
StatusPublished

This text of 388 F.3d 30 (Elgard Corporation v. Brennan Construction Company) is published on Counsel Stack Legal Research, covering Court of Appeals for the Second Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Elgard Corporation v. Brennan Construction Company, 388 F.3d 30, 2004 U.S. App. LEXIS 21248 (2d Cir. 2004).

Opinion

388 F.3d 30

ELGARD CORPORATION, Plaintiff-Appellant-Cross-Appellee,
v.
BRENNAN CONSTRUCTION COMPANY and American Insurance Company, Defendants-Third-Party-Plaintiffs-Appellees-Cross-Appellants,
Robert C. Adams, Debra E. Adams and R.C. Adco Inc., Third-Party-Defendants.

Docket No. 00-9326.

Docket No. 00-9388.

United States Court of Appeals, Second Circuit.

Argued: May 3, 2004.

Decided: October 13, 2004.

Appeal from the United States District Court for the District of Connecticut, Donna F. Martinez, United States Magistrate Judge. COPYRIGHT MATERIAL OMITTED William J. Egan (Barbara E. Crowley, on the brief), Egan & Crowley, P.C., New Haven, CT for Appellant.

Daniel J. Klau (Richard F. Wareing, on the brief), Pepe & Hazard LLP, Hartford, CT for Appellee.

Before: CARDAMONE and JACOBS, Circuit Judges, KORMAN,* District Judge.

JACOBS, Circuit Judge.

Following a bench trial in this diversity action, the United States District Court for the District of Connecticut (Martinez, Magistrate Judge) awarded contract damages and statutory interest in favor of Appellant-Cross-Appellee Elgard Corporation ("Elgard") in connection with a 1992 construction project. Elgard challenges the district court's exclusion of certain contract and offer-of-judgment interest from the award in its favor, and the denial of attorney's fees. Appellees-cross-appellants Brennan Construction Company ("Brennan") and American Insurance Company ("American") (collectively, "defendants") cross-appeal the award of statutory interest pursuant to Conn. Gen.Stat. § 49-42 and the rejection of Brennan's equitable estoppel defense. For the reasons set forth below, we (i) affirm the judgment as to liability but (ii) reverse the denial of attorney's fees and (iii) vacate the damage award and remand for recalculation in a manner consistent with this opinion.

BACKGROUND

Brennan, a Connecticut-based general contractor, entered an agreement in April 1992 with the State of Connecticut ("the State") to rehabilitate a bridge over the West River in New Haven. The project called for the installation of an anti-corrosive cathodic protection system, which Brennan subcontracted to R.C. Adco, Inc. ("Adco"). Adco in turn subcontracted with Elgard to manufacture the necessary equipment. The Elgard/Adco subcontract became effective on or about April 29, 1992. For $110,200, Elgard was to produce and deliver the protection system to Adco, which would install it. The Elgard/Adco contract further provided that "[a]ny balance remaining due after thirty (30) days of delivery shall accrue interest at the rate of one and one-half percent (1 1/2%) per month." As of September 9, 1992, Elgard delivered to Adco all materials called for under the contract, and has been seeking collection ever since.

* As a sub-subcontractor, Elgard was required to submit invoices to Adco, which would submit them to Brennan, which would seek payment from the State. Upon receipt of state funds, Brennan was to send payment back down the chain, through Adco to Elgard. The cause of the various controversies is that Adco used fraud to induce payment by the State to Brennan, and by Brennan to Adco for Elgard's account, and then misappropriated Elgard's money en route.

On June 30, 1992, Adco submitted to Brennan a requisition for payment in the amount of $107,445.1 By regulation, Connecticut will reimburse a contractor for so-called "unincorporated" materials mid-construction if "such materials have been paid for by the Contractor as shown by receipted bills, or in lieu of such receipted bill or bills, a duly executed Certification of Title executed by the Contractor and the Vendor in the form approved by the Department [of Transportation]." Conn. Dept. of Transp., Standard Specifications for Roads, Bridges and Incidental Construction § 1.09.06(B). Thus, Adco was entitled to payment if it had paid Elgard for the materials, or if it provided Brennan with a Certification of Title to a presently-existing cathodic protection system. Adco furnished a Certification of Title, but the certificate was deficient in two critical and undisputed respects: (i) partial delivery had been made to Adco's West Haven storage facility as of the date it sought payment, but the balance of the system was not scheduled to arrive until early September 1992; and (ii) without Elgard's knowledge or consent, Adco's president, Robert Adams, forged Elgard's signature on the Certification of Title. The forgery that Adams submitted to Brennan was accompanied by two Elgard invoices, seemingly in an effort to suggest that the equipment had been delivered. Adco had asked Elgard in late May 1992 to invoice for the cathodic protection system, notwithstanding that no equipment had yet been delivered. Elgard sent Adco two invoices dated May 29 and June 4, 1992, but each invoice reflected that no materials had been shipped as of those dates.

In reliance on Adco's forgery, Brennan signed the title certification and requested payment from the State. Before paying Brennan, the State sent an inspector to Adco's West Haven storage facility to verify the presence of the cathodic protection system. By that time, all but two rectifiers (a $10,000 value) had arrived, and Adams—perhaps expecting the audit—had planted among the West River bridge materials a single rectifier meant for another job. The ruse succeeded; the inspector noted that some equipment appeared to be missing, but allowed himself to be persuaded that the project specifications called for a single rectifier and (thus satisfied) was sent on his way.

On August 14, 1992, the State issued a check to the order of Brennan in the amount of $107,445. Two weeks later, Adams came to Brennan's offices looking for payment. He received a check in the amount of $107,445 payable to "R.C. Adco, Inc./Elgard Corporation." Adams knew the funds were meant for Elgard, and indicated to Brennan that he would send the check to the company. Instead he deposited the funds in an Adco account. Brennan was unaware that Adco had filed for bankruptcy eleven days before this misappropriation.

In the meantime, Elgard completed manufacture of the cathodic protection equipment, all of which was delivered to Adco as of September 9, 1992. Elgard awaited payment. The underlying litigation started when Elgard ran out of patience.

II

The procedural posture of this 12-year litigation is complicated by Adco's bankruptcy and by Connecticut law, which affords subcontractors like Elgard specific remedies for nonpayment.

Brennan undertook the West River bridge rehabilitation pursuant to a bonded construction contract that was subject to Conn. Gen.Stat. § 49-42. As a condition precedent to signing the contract, Elgard and its surety, American, executed a $1.4 million payment bond in favor of the State. Under § 49-42, a subcontractor can enforce its right to payment under such a bond by serving a notice of claim on the surety "within one hundred eighty days after the date [bonded] materials were supplied." Conn. Gen.Stat. § 49-42(a).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Salve Regina College v. Russell
499 U.S. 225 (Supreme Court, 1991)
State v. Schroff
503 A.2d 167 (Supreme Court of Connecticut, 1986)
Civiello v. Owens-Corning Fiberglass Corp.
544 A.2d 158 (Supreme Court of Connecticut, 1988)
Blakeslee Arpaia Chapman, Inc. v. EI Constructors, Inc.
687 A.2d 506 (Supreme Court of Connecticut, 1997)
Wallerstein v. Stew Leonard's Dairy
780 A.2d 916 (Supreme Court of Connecticut, 2001)
Cardenas v. Mixcus
823 A.2d 321 (Supreme Court of Connecticut, 2003)
Ernst Steel Corp. v. Reliance Insurance
536 A.2d 969 (Connecticut Appellate Court, 1988)
State v. Polanco
597 A.2d 830 (Connecticut Appellate Court, 1991)
Yale University School of Medicine v. McCarthy
602 A.2d 1040 (Connecticut Appellate Court, 1992)
State v. Arbour
618 A.2d 60 (Connecticut Appellate Court, 1992)
Thames River Recycling, Inc. v. Gallo
720 A.2d 242 (Connecticut Appellate Court, 1998)
Elgard Corp. v. Brennan Construction Co.
388 F.3d 30 (Second Circuit, 2004)
Elgard Corp. v. Brennan Construction Co.
157 F.R.D. 1 (D. Connecticut, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
388 F.3d 30, 2004 U.S. App. LEXIS 21248, Counsel Stack Legal Research, https://law.counselstack.com/opinion/elgard-corporation-v-brennan-construction-company-ca2-2004.