Ernst Steel Corp. v. Reliance Insurance

536 A.2d 969, 13 Conn. App. 253, 1988 Conn. App. LEXIS 21
Connecticut Appellate Court·Decided January 19, 1988·No. (4803)·Published·Cited by 19 cases

Opinions

Spallone, J.

The defendants are appealing from the judgment rendered for the plaintiff in an action on a construction contract. The plaintiff has cross appealed from the denial of counsel fees on the defendant’s counterclaim. We find no error.

The plaintiff, Ernst Steel Corporation (Ernst) commenced this action against the defendants Reliance Insurance Company (Reliance) and General Reinsurance Corporation (General) in their capacities as sureties for the defendant, Yonkers Contracting Company, Inc. (Yonkers). Ernst sought to recover $410,472.80, plus interest and attorney’s fees, against Yonkers’ sureties, due in connection with its performance under a subcontract with Yonkers for the fabrication and erection of steel structures required in the construction of certain bridges. Yonkers was under a general contract with the Connecticut department of transportation for the construction of a portion of Interstate Route 84. Ernst claimed payments and interest due under its contract with Yonkers as damages and also claimed counsel fees by application of General Statutes § 49-41a.1 [255]*255Although Yonkers was not named as a party in the initial complaint, the general contractor moved to be added as a defendant and filed a counterclaim against Ernst for damages allegedly caused by Ernst’s delays in performing its contractual duties.

The trial judge presiding over this action endeavored to simplify the proceedings by bifurcating the trial into the issues of liability and damages. In a memorandum of decision dated February 15, 1985, the trial court found that the parties had not agreed upon a firm delivery schedule, that the plaintiff had satisfactorily performed its contractual obligations within a reasonable period of time and, therefore, Yonkers was not justified in withholding the sums owed to the plaintiff. Additional testimony was heard by the court on June 25, 1985, and a second memorandum of decision followed on October 13, wherein the court discussed its determination of damages. Ernst was awarded $343,387.15 plus interest at 1.5 percent per month for the work done under the contract2 and $10,394.88 plus interest at

[256]*2561 percent per month3 for work performed by Ernst outside of the contract. ■

The court also found that, pursuant to General Statutes § 49-41a, Ernst was entitled to collect attorney’s fees, and therefore awarded Ernst an amount equal to 20 percent of the sums found to be due as of December 13,1985. The plaintiff was not awarded, however, additional attorney’s fees which it claimed it incurred as a result of defending against Yonkers’ counterclaim. After the rendition of judgment, the defendants filed this appeal, and the plaintiff filed a cross appeal alleging error in the court’s denial of its claim for additional counsel fees.

In January of 1986, the defendants filed a motion for rectification with the trial court. One month later, the plaintiff filed a motion for further articulation, largely in response to the defendants’ motion, which set out in detail the necessary underlying facts to support the court’s factual conclusions. Oral argument was held on both motions and the court issued an articulation which, for the most part, adopted verbatim the proposed findings filed by the plaintiff.4

I

In its statement of issues, the defendants initially claimed that the trial court’s articulation should be reviewed by a standard more strict than clear error because of the court’s wholesale adoption of the plain[257]*257tiff’s proposed articulation. The defendants abandoned this claim at oral argument in light of the recent disposition by our Supreme Court of a similar claim. See Grayson v. Grayson, 202 Conn. 221, 520 A.2d 225 (1987) (appeal dismissed on the ground that certification was improvidently granted).5

The defendants’ remaining claims are that the court erred: (1) in finding that there was no agreement as to a specific delivery date; (2) in finding that the time within which the subcontract was to be performed was not of the essence; (3) in finding that the plaintiff performed within a reasonable time; (4) in awarding the plaintiff interest and attorney’s fees under General Statutes § 49-41a; (5) in its computation of the damages awarded under the contract; and (6) in holding for the plaintiff on the counterclaim.

The first three of the defendants’ claims of error, no matter how couched, presented or obfuscated, are merely attacks on the factual findings of the trial court. In essence, the defendant is asking us to retry these issues. We cannot. On appeal, the function of this court is limited solely to the determination of whether the decision of the trial court is clearly erroneous. Practice Book § 4061; Damora v. Christ-Janer, 184 Conn. 109, 113, 441 A.2d 61 (1981); Ram Roofing & Sheet Metal Co. v. A.B.C. Plumbing & Heating, Inc., 2 Conn. [258]*258App. 54, 56, 475 A.2d 341 (1984). It is the province of the trial court to “pass upon the credibility of witnesses and the weight to be accorded the evidence.” Edgewood Construction Co. v. West Haven Redevelopment Agency, 170 Conn. 271, 272, 365 A.2d 819 (1976); Essex Savings Bank v. Leeker, 2 Conn. App. 98, 102, 476 A.2d 1071 (1984). It is not within this court’s power to find facts or draw conclusions therefrom. As an appellate body, we review the factual findings below to ensure that they could have been legally, logically and reasonably found, thereby establishing that the trial court could reasonably conclude as it did. Appliances, Inc. v. Yost, 186 Conn. 673, 676-77, 443 A.2d 486 (1982); Hallmark of Farmington v. Roy, 1 Conn. App. 278, 280-81, 471 A.2d 651 (1984). Our review of the record and transcripts discloses ample support for the court’s findings and conclusions that the contract between Ernst and Yonkers contained no agreement which evinced a specific delivery date, that the time within which the contract was to be performed was not of the essence, and that the plaintiff performed its contractual obligations within a reasonable time. There is no merit to the defendants’ assertion to the contrary.

Free access — add to your briefcase to read the full text and ask questions with AI

Ernst Steel Corp. v. Reliance Insurance, 536 A.2d 969, 13 Conn. App. 253, 1988 Conn. App. LEXIS 21 (Colo. Ct. App. 1988).

536 A.2d 969 (Ernst Steel Corp. v. Reliance Insurance) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

In re Halle T.
902 A.2d 670 (Connecticut Appellate Court, 2006)
Elgard Corporation v. Brennan Construction Company
388 F.3d 30 (Second Circuit, 2004)
Elgard Corp. v. Brennan Construction Co.
388 F.3d 30 (Second Circuit, 2004)
Maris v. McGrath
850 A.2d 133 (Supreme Court of Connecticut, 2004)
TDS Painting & Restoration, Inc. v. Copper Beech Farm, Inc.
808 A.2d 726 (Connecticut Appellate Court, 2002)
Cloutier v. Liberty Mutual Insurance, No. Cv90 027 81 84 S (Aug. 13, 2001)
2001 Conn. Super. Ct. 10959 (Connecticut Superior Court, 2001)
Pryce v. Keane Thummel Trucking, No. Cv 00-0800961 (Jul. 20, 2001)
2001 Conn. Super. Ct. 9941 (Connecticut Superior Court, 2001)
Colandro v. Allstate Insurance Company, No. Cv 92-0337064 (Dec. 19, 1996)
1996 Conn. Super. Ct. 6762 (Connecticut Superior Court, 1996)
CFM of Connecticut, Inc. v. Chowdhury
685 A.2d 1108 (Supreme Court of Connecticut, 1996)
Saturn Construction Co. v. Premier Roofing Co.
680 A.2d 1274 (Supreme Court of Connecticut, 1996)
Jones v. Forst
675 A.2d 922 (Connecticut Appellate Court, 1996)
Quoka v. Drapko, No. Cv91 0036714s (Nov. 25, 1992)
1992 Conn. Super. Ct. 10613 (Connecticut Superior Court, 1992)
Rosie's Repair Remod. v. Smp Devel., No. Cv91 0117846 (Apr. 13, 1992)
1992 Conn. Super. Ct. 3505 (Connecticut Superior Court, 1992)
Sippin v. Ellam
588 A.2d 660 (Connecticut Appellate Court, 1991)
In re Noel M.
580 A.2d 996 (Connecticut Appellate Court, 1990)
Bucy v. Bucy
579 A.2d 117 (Connecticut Appellate Court, 1990)
Fattibene v. Kealey
558 A.2d 677 (Connecticut Appellate Court, 1989)
Seery v. Yale-New Haven Hospital
554 A.2d 757 (Connecticut Appellate Court, 1989)
Ruwet-Sibley Equipment Corp. v. Stebbins
542 A.2d 1171 (Connecticut Appellate Court, 1988)