Eastern Seaboard Construction Co. v. Gray Construction, Inc.

553 F.3d 1, 2008 U.S. App. LEXIS 26803, 2008 WL 5428159
CourtCourt of Appeals for the First Circuit
DecidedDecember 31, 2008
Docket08-1679
StatusPublished
Cited by28 cases

This text of 553 F.3d 1 (Eastern Seaboard Construction Co. v. Gray Construction, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Eastern Seaboard Construction Co. v. Gray Construction, Inc., 553 F.3d 1, 2008 U.S. App. LEXIS 26803, 2008 WL 5428159 (1st Cir. 2008).

Opinion

STAHL, Circuit Judge.

Eastern Seaboard Concrete Construction Company (“Eastern”) appeals the district court decision vacating an amended arbitration award and denying Eastern prejudgment interest on its award.

I.

The background facts of this case are thoroughly discussed in the magistrate judge’s Recommended Decision, see E. Seaboard Concrete Constr. Co. v. Gray Constr. Inc., 2008 WL 1803781 (D.Me. 2008). For our purposes, Gray Construction (“Gray”), the prime contractor on a construction project at the Portsmouth Naval Shipyard in Kittery, Maine, contracted with Eastern to perform the site work at the project. A dispute arose when Eastern encountered unexpected conditions that increased the project’s scope and as a result, put the job behind schedule. When the Navy refused to pay Gray for the extra work and Gray in turn refused to pay Eastern, Eastern left the job, returned briefly, and ultimately was terminated by Gray. Gray then hired replacement subcontractors and suppliers to complete Eastern’s scope of the work.

Eastern filed a complaint premised on the Miller Act, 40 U.S.C. § 3131 et seq., which requires surety bonds on federal construction projects, against Gray in federal district court in Maine. Gray counterclaimed and simultaneously motioned to stay the proceedings because Eastern had not exhausted the parties’ contractual and administrative remedies pursuant to the parties’ subcontract. The parties then agreed to submit the case to arbitration pursuant to the arbitration clause in their contract and later voluntarily dismissed the court action to permit the arbitration to proceed on a more extended basis. Eastern and Gray agreed that the American Arbitration Association’s Construction Industry Arbitration Rules and Mediation Procedures (“AAA Rules”) would apply to the proceeding.

Following the arbitration proceedings in May 2007, the arbitrator issued a nine-page arbitration award on September 21, 2007. Noting that “[t]o the extent that an issue or claim is not explicitly discussed and resolved, it is denied,” the arbitrator awarded Eastern recovery on all but one of its claims, and he also determined that Eastern breached its contract by abandoning its work and awarded Gray $77,000 for the completion of the contract, “to be deducted from the award paid to Eastern Seaboard.” The arbitrator rejected Eastern’s contention that it was entitled to interest under a Federal Prompt Payment Act interest penalty, 31 U.S.C. §§ 3901-3907, or its implementing regulations.

Eastern then filed an Application for Clarification of the Arbitration Award and sought to have the $77,000 award to Gray reduced by $66,613.89, the amount remaining on the parties’ subcontract. Eastern previously had alerted the arbitrator to this amount in its Posh-Trial Brief in which it observed, “The Parties do not dispute that there was $66,613.89 remaining under the base contract.”

Gray, in its Post-Hearing Arbitration Brief, had contended that it was not in breach of contract for non-payment. Gray made three independent arguments in its defense. First, it noted the pay-when-paid clause of the contract. Second, it stated that Eastern “had effectively already been paid the sums in question by virtue of *3 Gray’s overpayment on the base contract.” Finally, Gray suggested that even if Eastern had not been paid for the work, the contract permitted Gray to withhold payment “when there is reasonable doubt that [Eastern] could complete the Work on time, was satisfactorily prosecuting the Work, or that the Work could be completed for the unpaid balance of the subcontract price.” While the arbitrator’s initial award disposed of Gray’s first defense, finding that the pay-when-paid clause was unenforceable under the Miller Act, it did not address Gray’s other arguments.

On November 4, 2007, acknowledging that “[t]he award could have been clearer,” the arbitrator issued an amended arbitration award and adopted Eastern’s request, noting that “Gray does not seriously dispute the $66,613.89 figure.” He also cited Section 11.2 of the contract which required that any unpaid contract balance owed to the subcontractor be offset by the cost of completing the subcontractor’s work, “which is precisely what is being awarded here.”

Gray moved to vacate the award, and Eastern filed a cross-motion to confirm the award and requested the court award prejudgment interest. On April 18, 2008, the magistrate judge recommended a decision granting Gray’s motion to vacate, finding that AAA Rule R-47 (“Rule 47”) prohibited the substantive modifications in the amended award. She also determined that Eastern was not entitled to interest before the date of the award. On May 23, 2008, the district court affirmed the magistrate’s decision after de novo review. Eastern now appeals the decision.

II.

We review the district court’s decision to vacate the arbitral award de novo. UMass Mem’l Med. Ctr., Inc. v. United Food & Commercial Workers Union, 527 F.3d 1, 5 (1st Cir.2008). Our consideration of the award is “extremely narrow and exceedingly deferential,” Wheelabrator Envirotech Operating Servs. Inc. v. Mass. Laborers Dist. Council Local 1144, 88 F.3d 40, 43 (1st Cir.1996) (citations omitted), such that our de novo review is “among the narrowest known in the law,” Me. Cent. R. Co. v. Bhd. of Maint. of Way Employees, 873 F.2d 425, 428 (1st Cir.1989) (citations omitted). Indeed, we have recognized that “[arbitral awards are nearly impervious to judicial oversight.” Teamsters Local Union No. 42 v. Supervalu, Inc., 212 F.3d 59, 61 (1st Cir.2000) (citations omitted). Thus, “[a] court’s review of an arbitration award is highly deferential because the parties ‘have contracted to have disputes settled by an arbitrator’ and thus, ‘it is the arbitrator’s view of the facts and of the meaning of the contract that they have agreed to accept.’ ” Bull HN Info. Sys., Inc. v. Hutson, 229 F.3d 321, 330 (1st Cir.2000) (quoting United Paperworkers Int’l Union v. Misco, Inc., 484 U.S. 29, 37-38, 108 S.Ct. 364, 98 L.Ed.2d 286 (1987)).

“Courts must accord substantial deference to the decisions of arbitrators. Nevertheless, there are limits to that deference.” Kashner Davidson Sec. Corp. v. Mscisz, 531 F.3d 68, 70 (1st Cir.2008). Section 10 of the Federal Arbitration Act (“FAA”) permits courts to vacate arbitrators’ awards “[w]here the arbitrators exceeded their powers.” 9 U.S.C. § 10(a)(4).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

McCuistion v. Kijakazi
E.D. Washington, 2023
Wickstrum v. FCA US LLC
S.D. California, 2021
Axia Netmedia Corp. v. Mass. Tech. Park Corp.
381 F. Supp. 3d 128 (District of Columbia, 2019)
Ameriprise Fin. Servs., Inc. v. Brady
325 F. Supp. 3d 219 (District of Columbia, 2018)
Bank of America, N.A. v. Casey
52 N.E.3d 1030 (Massachusetts Supreme Judicial Court, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
553 F.3d 1, 2008 U.S. App. LEXIS 26803, 2008 WL 5428159, Counsel Stack Legal Research, https://law.counselstack.com/opinion/eastern-seaboard-construction-co-v-gray-construction-inc-ca1-2008.