Eastern Marine, Inc. v. United States

33 Cont. Cas. Fed. 74,491, 10 Cl. Ct. 184, 1986 U.S. Claims LEXIS 857
CourtUnited States Court of Claims
DecidedJune 18, 1986
DocketNo. 105-84C
StatusPublished
Cited by8 cases

This text of 33 Cont. Cas. Fed. 74,491 (Eastern Marine, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Eastern Marine, Inc. v. United States, 33 Cont. Cas. Fed. 74,491, 10 Cl. Ct. 184, 1986 U.S. Claims LEXIS 857 (cc 1986).

Opinion

OPINION

MARGOLIS, Judge.

Pursuant to the Equal Access to Justice Act, 28 U.S.C. § 2412(d)(1)(A) (West Supp. 1986), the plaintiff, Eastern Marine, Inc. [EMI], seeks attorneys fees and costs incurred in bringing an action against the United States resulting in a judgment for $223,430. EMI alleges that it is a “prevailing party” as defined by the Act and that the position of the defendant United States was not substantially justified. It seeks an award of $100,169.05 in attorneys fees and $16,268.55 in costs.

The defendant asserts that EMI was not a prevailing party; that the government’s position was substantially justified; that in the alternative, if fees are awarded, only attorneys fees relating to the theory on which EMI eventually prevailed should be recovered; and that EMI’s recovery should be limited to the statutory rate of $75 per hour.

FACTS

A full discussion of the dispute that gave rise to this claim for attorneys fees and costs is set forth in Eastern Marine, Inc. v. United States, 5 Cl.Ct. 34 (1984). In short, these are the facts:

Through the unauthorized encouragement of a Coast Guard officer, EMI was induced to participate in a procurement for high speed Coast Guard boats modeled after parent crafts that were proven to be fast, reliable, and seaworthy. That same officer assured EMI that certain variations it hoped to propose would not disqualify it from the bid competition. Relying on his assurances, EMI incurred substantial costs in preparing a bid.

Despite the Coast Guard officer’s assurances to the contrary, EMI’s proposal was eliminated from the competition because the craft EMI proposed differed substantially from the parent craft. Before being eliminated, however, the Coast Guard advised EMI of several technical deficiencies in its bid, and EMI spent additional monies correcting these deficiencies only to be told later that it was being eliminated from the competition.

EMI filed a protest with the Government Accounting Office [GAO] and subsequently filed a complaint in this court when the Coast Guard refused to stipulate that it would postpone award of the contract until GAO ruled on the protest. This court was asked to enjoin the Coast Guard from awarding the contract or, alternatively, to award EMI its bid preparation costs. The court denied both requests, finding that an injunction was inappropriate since there was a rational basis for the Coast Guard’s action and that EMI should not have relied on the officer’s verbal assurances.

On appeal, the U.S. Court of Appeals for the Federal Circuit [CAFC] affirmed this court’s finding with respect to the injunction, but reversed the court’s determination that bid preparation expenses should not be awarded. Eastern Marine, Inc. v. United States, No. 84-1444 (Fed.Cir. Jan. 31, 1985) (unpublished slip opinion, disposition only reported at 765 F.2d 158). The Court of Appeals found that the Coast Guard had acted in an arbitrary and capricious manner in failing to advise EMI earlier that its proposal was non-competitive and unacceptable. The CAFC stated:

The record clearly demonstrates that EMI would not have been in the [patrol boat] competition if it had not been for the encouragement of [the Coast Guard officer] and should have been eliminated at an earlier stage if the contracting personnel had clearly informed it of the disqualifying condition relating to the two engine design. Since the [Coast Guard’s] conduct was not honest and fair, it was arbitrary and capricious. The award of bid preparation costs is appropriate under the circumstances.

Slip op. at 5.

After the CAFC ruled that EMI was entitled to relief, the Government filed a Motion for Reconsideration which was denied on March 4,1985. On March 26, 1985, the CAFC issued a one sentence order stat[186]*186ing, “The court having considered the submissions of the parties, IT IS ORDERED THAT the parties shall bear their own costs in this appeal.” Eastern Marine, Inc. v. United States, No. 84-1444, Order of March 26 (Fed.Cir.1985). The Government insists the March 26, 1985 order establishes that EMI was not a prevailing party and that this court is bound by the CAFC’s determination as the law of the case.

EMI disagrees and also points out that during the course of litigation in the U.S. Claims Court, the Government’s position was not substantially justified because the Government resisted discovery and interposed questionable defenses. For example, EMI asserts that the Government defended against the request for an injunction by asserting that immediate award of the contract was a matter of national security. However, the Coast Guard waited nearly five weeks after the injunction was denied to award the contract, and that award was later set aside as illegal because of significant variations between the parent craft and the craft proposed. See Bollinger Machine Shop & Shipyard, Inc. v. United States, 594 F.Supp. 903 (D.D.C.1984). EMI also alleges that a further example of the Government’s lack of good faith in resolving EMI’s claim is the Coast Guard’s initial refusal to stipulate to postponement of the contract award.

DISCUSSION

The Equal Access to Justice Act [EAJA] was first enacted in 1980 with a sunset date of October 1, 1984. The purpose of the Act was to ensure that certain individuals and small businesses would not be deterred from seeking review of, or defending against, unjustified governmental action because of the expense involved in securing the vindication of their rights. The Act expired as scheduled, but was retroactively revived, modified, re-enacted and made permanent by the passage of H.R. 2378 signed by the President on August 5, 1985. The standard for recovery under the Act is that a qualified “prevailing party” can recover attorneys fees and costs unless the United States can show its position was “substantially justified.”

EMI is a “prevailing party” as defined by the Act since it is a small business and was successful in obtaining at least one significant form of requested relief, i.e., its bid preparation costs. See Environmental Defense Fund, Inc. v. Watt, 554 F.Supp. 36, 39 (E.D.N.Y.1982), aff'd, 722 F.2d 1081 (2d Cir.1983). The Government’s contention that the law of the case precludes a finding that EMI was a “prevailing party” is without merit. The CAFC’s one sentence order of March 26, 1985 that each party bear its own costs does not necessarily imply that EMI did not prevail. Moreover, the costs at issue in the CAFC were appeal costs, not attorneys fees and costs in this court.

Having found that EMI is a prevailing party, the next relevant inquiry is whether or not the Government has met its burden of proving that its position was “substantially justified.” To this end, a brief discussion of the legislative history of the Act is necessary.

Subsequent to the passage of the EAJA, the House Committee on the Judiciary conducted oversight hearings on its implementation. The Congress eventually passed H.R. 2378, an amended version of the Act, to overcome certain Presidential objections to earlier versions and to remedy ambiguities and inconsistent holdings in the courts. One such ambiguity was the meaning of the term “substantially justified”; another was whether or not the underlying agency action was part of the determination of whether the Government’s position was substantially justified.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Q Integrated Companies, LLC v. United States
132 Fed. Cl. 638 (Federal Claims, 2017)
Coflexip & Services, Inc. v. United States
36 Cont. Cas. Fed. 75,867 (Court of Claims, 1990)
Vanguard Security Inc. v. United States
20 Cl. Ct. 90 (Court of Claims, 1990)
Doe v. United States
16 Cl. Ct. 412 (Court of Claims, 1989)
Babenco Development Co. v. United States
15 Cl. Ct. 637 (Court of Claims, 1988)
Esprit Corp. v. United States
35 Cont. Cas. Fed. 75,551 (Court of Claims, 1988)
Tax Analysts v. United States
11 Cl. Ct. 802 (Court of Claims, 1987)
Oliveira v. United States
11 Cl. Ct. 101 (Court of Claims, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
33 Cont. Cas. Fed. 74,491, 10 Cl. Ct. 184, 1986 U.S. Claims LEXIS 857, Counsel Stack Legal Research, https://law.counselstack.com/opinion/eastern-marine-inc-v-united-states-cc-1986.