Bollinger MacHine Shop & Shipyard, Inc. v. United States

594 F. Supp. 903, 1984 U.S. Dist. LEXIS 14942
CourtDistrict Court, District of Columbia
DecidedJuly 13, 1984
DocketCiv. A. 84-1763
StatusPublished
Cited by5 cases

This text of 594 F. Supp. 903 (Bollinger MacHine Shop & Shipyard, Inc. v. United States) is published on Counsel Stack Legal Research, covering District Court, District of Columbia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bollinger MacHine Shop & Shipyard, Inc. v. United States, 594 F. Supp. 903, 1984 U.S. Dist. LEXIS 14942 (D.D.C. 1984).

Opinion

MEMORANDUM

FLANNERY, District Judge.

Plaintiff in this case was an unsuccessful bidder in a United States Coast Guard procurement in which the Coast Guard sought sixteen Patrol Boats (“WPB’s”) on an expedited basis to combat drug smuggling in the Gulf Coast area. The contract award was given to Marine Power & Equipment *905 Company (“MPE”), and plaintiff here complains that the successful bid was not responsive. Plaintiff requests the court to order that the Coast Guard terminate its contract with MPE and award it to plaintiff. Based on the facts adduced at a trial on the merits, and for the reasons stated herein, the court will grant plaintiffs request to set aside the Coast Guard’s award to MPE, but will deny plaintiff’s request for an order awarding plaintiff the contract. Instead, the case will tie remanded to the Coast Guard for appropriate action not inconsistent with this opinion. BACKGROUND

On May 11, 1984, the Coast Guard awarded MPE the contract at issue in this case. Plaintiff soon discovered certain information which led it to believe that the award was improper because MPE’s proposal could not have met the WPB specifications established by the Circular of Requirements (“COR”) governing this procurement. On June 8, 1984, plaintiff-filed the instant complaint, and simultaneously moved for a temporary restraining order and/or a preliminary injunction to stop performance of the Coast Guard/MPE contract. The court set the matter down for a hearing on the TRO, and notified counsel for plaintiff, the Coast Guard, and MPE, a potential intervenor. 1 After the hearing, the court denied plaintiff’s motion for a TRO after balancing the equities. After consultation with counsel, however, the court determined that the dispute should be decided expeditiously on the merits. Without objection, an expedited discovery schedule was established, and the case was set down for a trial on the merits on July 9, 1984. The parties were able to work out discovery disputes with minimal intervention by the court, and depositions were taken of the witnesses who would appear at trial. Defendant submitted certain information to the court in camera which contained apparently proprietary information that defendant considered necessary for the court’s review of the agency’s action. On July 9, 1984, the casé was tried by the court sitting without a jury. The court, having considered the pleadings filed in this case, the testimony of the witnesses, the documents in evidence and the stipulations of the parties, the defendant’s in camera submissions, 2 and the arguments of counsel, hereby makes the following findings of fact and conclusions of law as required by Rule 52(a) of the Federal Rules of Civil Procedure.

FINDINGS OF FACT

A. General Description of WPB Procurement

1. In late 1982, the Coast Guard determined that there was an urgent need for patrol boats to be used for alien and drug interdiction on the gulf and southeast coasts of the United States. In order to ensure that it could expeditiously obtain reliable and proven crafts that could meet the requirements necessary for this urgent mission, the Coast Guard developed the “Parent Craft” concept, and explicitly incorporated that concept into its Request for Proposals (RFP) and Circular of Requirements (COR) for RFP DTCG23-83-R30024.

' 2. The Parent Craft concept utilized for this WPB procurement represented a departure from normal procurement procedures. As Commander Tozzi, a member of the Source Evaluation Board and Engineering Evaluation Team for this procurement *906 testified, a normal procurement involves thorough and time consuming design development, engineering studies, and testing to work out design difficulties that can be expected with a new craft. For the WPB procurement at issue, the Coast Guard determined that use of the “Parent Craft” concept would result in much faster procurement and construction of a tested, reliable boat which greatly reduced risk to the Coast Guard. The “Parent Craft” concept was very simple — each offeror was required to designate a “Parent Craft” from among existing, fully proven patrol boats, and the “daughter craft” proposed to be constructed would be required to be identical or similar to the Parent Craft in critical areas set forth in the COR. By making use of this. concept, the Coast Guard believed it could avoid the need for the normally required extensive engineering studies and testing, and could obtain proven WPB’s quickly and with minimal risk that they would fail to perform as required. In a Coast Guard announcement in the March, 1983, Commerce Business Daily, it was emphasized that the proven Parent Graft concept was being utilized “to minimize Coast Guard technical risk.”

3. The requirements for the Parent Craft and the WPB (the “daughter craft” to be constructed) were set out in some detail in the COR for this procurement. In July, 1983, approximately eleven proposals were received. Throughout the procurement process, the “Parent Craft” concept was stressed, and when bidders requested clarification on critical issues such as Parent Craft/WPB similarity requirements, the Coast Guard routinely replied that the COR was clear, and referred bidders to specific provisions in the COR without comment. Through a gradual process of eliminating bidders who could not correct disqualifying deficiencies, the field was narrowed to two — MPE and plaintiff Bollinger Machine Shop. A third bidder, Eastern Marine, Inc., challenged the Coast Guard’s decision to eliminate it for proposing a WPB that was “dissimilar” from its Parent Craft, but the Coast Guard’s decision was upheld by the United States Court of Claims in Eastern Marine, Inc. v. United States, 5 Cl.Ct. 34 (1984). In that action, plaintiff Bollinger intervened along with MPE to defend the Coast Guard’s decision to eliminate Eastern Marine from the competition.

4. Plaintiff submitted its “best and final offer,” and MPE submitted at least two “best and final offers,” one with WPB’s containing 12-cylinder engines and another with 16-eylinder engines. On May 11,1984, the Coast Guard awarded the contract to MPE for production of up to 16 WPB’s with 12-cylinder engines, for an approximate price of $76 million. Shortly thereafter, plaintiff initiated this lawsuit, alleging that the Coast Guard’s selection of MPE’s 12-cylinder craft was not permissible under the COR, primarily because the MPE Parent Craft was believed to contain a 20-cylin-der engine, making substitution of the 12-eylinder engine “dissimilar” and inconsistent with the Parent Craft concept.

B. Specific Requirements of the' COR

5. The Coast Guard’s requirements for each competitor’s Parent Craft and WPB’s were set forth in the COR. Section 042b, “Parent Craft”, states that the “Parent Craft shall have been previously designed, built, and operated,’ as a patrol craft.” Among other requirements, § 042b states that

The Parent Craft shall meet the requirements of COR 100b (Structure), 200a (Propulsion Plant), and 200b (Propulsion Plant Rating).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Yash Raj Films v. Ahmed (In Re Ahmed)
359 B.R. 34 (E.D. New York, 2005)
Capital Engineering & Manufacturing Co. v. Weinberger
695 F. Supp. 36 (District of Columbia, 1988)
Eastern Marine, Inc. v. United States
33 Cont. Cas. Fed. 74,491 (Court of Claims, 1986)
Marine Power & Equipment Co. v. United States
594 F. Supp. 997 (District of Columbia, 1984)
Marine Power & Equipment Co. v. United States
32 Cont. Cas. Fed. 72,721 (Court of Claims, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
594 F. Supp. 903, 1984 U.S. Dist. LEXIS 14942, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bollinger-machine-shop-shipyard-inc-v-united-states-dcd-1984.