Dynalectric Co. of Nevada, Inc. v. Clark & Sullivan Constructors, Inc.

255 P.3d 286, 127 Nev. 480, 127 Nev. Adv. Rep. 41, 2011 Nev. LEXIS 43
CourtNevada Supreme Court
DecidedJuly 14, 2011
Docket51758
StatusPublished
Cited by13 cases

This text of 255 P.3d 286 (Dynalectric Co. of Nevada, Inc. v. Clark & Sullivan Constructors, Inc.) is published on Counsel Stack Legal Research, covering Nevada Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dynalectric Co. of Nevada, Inc. v. Clark & Sullivan Constructors, Inc., 255 P.3d 286, 127 Nev. 480, 127 Nev. Adv. Rep. 41, 2011 Nev. LEXIS 43 (Neb. 2011).

Opinion

OPINION

Per Curiam:

In this appeal, we address the measure of damages applicable to promissory estoppel claims. We adopt a flexible approach as suggested in the Restatement (Second) of Contracts and apply the same factors that bear on promissory estoppel relief to the remedy afforded by the breach. The determination of the appropriate measure of damages in any given case turns on considerations of what justice requires and the foreseeability and certainty of the particular damages award sought. We further conclude that the presumptive measure of damages for a general contractor that reasonably relies upon a subcontractor’s unfulfilled promise is the difference between the nonperforming subcontractor’s original bid and the cost of the replacement subcontractor’s performance.

FACTS AND PROCEDURAL HISTORY

This appeal arises from a dispute between appellant Dynalectric Company of Nevada, Inc., a subcontractor, and respondent Clark and Sullivan Constructors, Inc. (C&S), a general contactor, concerning a public works project (the Project). The Project involved the expansion of the University Medical Center (UMC) in Las Vegas. In 2004, UMC solicited bids for the Project. C&S, interested in serving as the general contractor for the Project, sought bids from subcontractors. Dynalectric submitted a bid to C&S to perform the electrical work for the Project and repeatedly assured C&S of the accuracy of its bid. C&S incorporated Dynalectric’s bid into its bid to UMC for the general contract (Prime Contract). C&S was the low bidder, and UMC awarded it the Prime Contract. C&S notified Dynalectric. Subsequently, Dynalectric repudiated its obligations to C&S and refused to negotiate with C&S. C&S therefore contracted with three replacement subcontractors to complete the electrical work for the Project.

C&S then sued Dynalectric in district court under various theories of liability, including breach of contract, promissory estoppel, and breach of the covenant of good faith and fair dealing. Dy- *483 nalectric countersued for, among other theories, breach of an implied contract, fraud, and violation of NRS 338.141. 2

Following a 12-day bench trial, the district court entered a judgment for C&S on its promissory estoppel claim and rejected each of Dynalectric’s counterclaims. The district court awarded C&S $2,501,615 in damages, which represents the difference between Dynalectric’s bid ($7,808,983) and the amount C&S paid the three replacement contractors to complete the work ($10,310,598). Dynalectric appealed.

DISCUSSION

Dynalectric contends that the district court applied the incorrect measure of damages. 3 Specifically, it asserts that the district court should not have awarded C&S expectation damages. We disagree.

Standard of review

Whether a party is “entitled to a particular measure of damages is a question of law” reviewed de novo. Toscano v. Greene Music, 21 Cal. Rptr. 3d 732, 736 (Ct. App. 2004).

Measure of damages for promissory estoppel claims

Broadly speaking, Nevada follows the doctrine of promissory estoppel articulated in the Restatement (Second) of Contracts. See *484 Vancheri v. GNLV Corp., 105 Nev. 417, 421, 111 P.2d 366, 369 (1989).

The Restatement describes promissory estoppel as follows:

A promise which the promisor should reasonably expect to induce action or forbearance on the part of the promisee or a third person and which does induce such action or forbearance is binding if injustice can be avoided only by enforcement of the promise. The remedy granted for breach may be limited as justice requires.

Restatement (Second) of Contracts § 90(1) (1981).

Comment d elaborates further upon the remedies available for promissory estoppel:

A promise binding under this section is a contract, and full-scale enforcement by normal remedies is often appropriate. But the same factors which bear on whether any relief should be granted also bear on the character and extent of the remedy. In particular, relief may sometimes be limited to restitution or to damages or specific relief measured by the extent of the promisee’s reliance rather than by the terms of the promise.

Id. § 90 cmt. d (emphasis added).

Thus, under the Restatement, an award of expectation damages 4 is often an appropriate remedy for promissory estoppel claims. But, in other instances, reliance damages 5 or restitutionary damages 6 may be more suitable.

Following the lead of the Restatement, we hold that the district court may award expectation, reliance, or restitutionary damages for promissory estoppel claims. 7 Although the doctrine of promis *485 sory estoppel is conceptually distinct from traditional contract principles, there is no rational reason ‘“for distinguishing the two situations in terms of the damages that may be recovered.’ ’ ’ Toscano, 21 Cal. Rptr. 3d at 737 (quoting Signal Hill Aviation Co., Inc. v. Stroppe, 158 Cal. Rptr. 178, 185 (Ct. App. 1979)). In sum, no single measure of damages will apply to each and every promissory estoppel claim; instead, to determine the appropriate measure of damages for promissory estoppel claims, the district court should consider the measure of damages that justice requires and that comports with the Restatement’s general requirements that damages be foreseeable and reasonably certain. 8 See Restatement (Second) of Contracts §§ 351, 352 (1981).

Whether the district court used the appropriate measure of damages

We now consider whether the district court used the appropriate measure of damages when it awarded C&S promissory estoppel damages representing the difference between Dynalectric’s bid and the amount that the three replacement contractors charged C&S to complete the same work.

Drennan v. Star Paving Company, 333 P.2d 757, 761 (Cal. 1958), the seminal promissory estoppel case in the subcontract bidding context, illustrates how damages should typically be computed in this situation. In Drennan, a general contractor was preparing a bid for a construction project. Id. at 758.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mitchell v. Nype
Nevada Supreme Court, 2022
In re: DRAFT BARS LLC
Ninth Circuit, 2021
Weitz Co. v. Hands, Inc.
882 N.W.2d 659 (Nebraska Supreme Court, 2016)
Crowley, Esq. v. Burke
Nevada Supreme Court, 2015
Richard Bell v. Recontrust Company
587 F. App'x 402 (Ninth Circuit, 2014)
Khan v. Bakhsh
306 P.3d 411 (Nevada Supreme Court, 2013)
Davis v. Beling
278 P.3d 501 (Nevada Supreme Court, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
255 P.3d 286, 127 Nev. 480, 127 Nev. Adv. Rep. 41, 2011 Nev. LEXIS 43, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dynalectric-co-of-nevada-inc-v-clark-sullivan-constructors-inc-nev-2011.