DURR MECHANICAL CONSTRUCTION, INC. v. PSEG FOSSIL, LLC

CourtDistrict Court, D. New Jersey
DecidedJanuary 29, 2021
Docket2:18-cv-10675
StatusUnknown

This text of DURR MECHANICAL CONSTRUCTION, INC. v. PSEG FOSSIL, LLC (DURR MECHANICAL CONSTRUCTION, INC. v. PSEG FOSSIL, LLC) is published on Counsel Stack Legal Research, covering District Court, D. New Jersey primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
DURR MECHANICAL CONSTRUCTION, INC. v. PSEG FOSSIL, LLC, (D.N.J. 2021).

Opinion

UNITED STATES DISTRICT COURT FOR THE DISTRICT OF NEW JERSEY

DURR MECHANICAL CONSTRUCTION, INC., Plaintiff, Civ. No. 18-10675 (KM) (CLW) v. OPINION PSEG FOSSIL, LLC, Defendant.

KEVIN MCNULTY, U.S.D.J.: PSEG Fossil, LLC, an energy company, hired Durr Mechanical Construction, Inc., a contractor, to construct a power plant. The project and their relationship went awry, so Durr sued PSEG, asserting contract, quasi- contract, and tort claims. PSEG moves to dismiss most of those claims. (DE 62.)1 For the following reasons, PSEG’s motion to dismiss is GRANTED IN PART and DENIED IN PART. I. BACKGROUND A. Facts PSEG sought to build a power plant (the “Project”). (Am. Compl. ¶ 13.) Instead of providing drawings of the plant to potential contractors to estimate their bids for the Project, PSEG provided a Bill of Quantity (“BOQ”) that “set out the type and amount of materials to be used to construct the Project.” (Id. ¶ 19.) In effect, the BOQ “quantif[ied] the extent of the Project scope.” (Id.)

1 Certain citations to the record are abbreviated as follows: DE = docket entry Am. Compl. = Amended Complaint (DE 59) Mot. = PSEG’s Brief in Support of its Motion to Dismiss (DE 62-1) Opp. = Durr’s Opposition to PSEG’s Motion to Dismiss (DE 67) Reply = PSEG’s Reply Brief in Support of its Motion to Dismiss (DE 68) Relying on the BOQ, Durr bid on portions of the project, which PSEG accepted, and began work. (Id.) It became clear that “the BOQ wildly understated the critical elements of the Project.” (Id.) Although PSEG had drawings available at bidding time, PSEG chose to send bidders the inaccurate BOQ in order to receive lower quotes for a Project for which PSEG had not properly budgeted. (Id. ¶¶ 20–22.) Unbeknownst to Durr when it began work, the Project was already behind schedule and over-budget. (Id. ¶ 34.) As the Project moved forward, PSEG asked Durr for a proposal to perform all mechanical work for the Project, instead of just the components it originally bid on. (Id. ¶ 28.) Durr did so, and since there were no drawings, “Durr proposed, and PSEG accepted, that Durr would be paid for work it performed on a cost reimbursable basis.” (Id. ¶ 31.) “To establish an initial monetary value for Durr’s work, subject to future adjustments based on the final design, Durr and PSEG negotiated and established a target price, i.e., a price goal assuming the final design matched the BOQ.” (Id. ¶ 32.) The Project continued, and new drawings kept arriving. (Id. ¶ 41.) These drawings “substantially revised the BOQ” and changed all types of specifications. (Id. ¶ 42.) Such changes caused Durr to spend more manpower and money. (Id. ¶ 43.) Nonetheless, PSEG assured Durr “that at the end of the Project there would be a ‘true-up’ between what was originally called for in the BOQ and what was required pursuant to the final version of the design.” (Id. ¶ 40.) At one point, however, PSEG purported to draw “a line in the sand.” (Id. ¶ 45.) When Durr submitted its final bid documents, PSEG’s Project director, Kevin Reimer, told Durr that it should not consider any documents after September 2016 for purpose of developing its price. (Id. ¶¶ 44–45.) So PSEG and Durr finalized a contract in November 2016 that limited the scope of work based on documents received as of September 2016. (Id. ¶ 47.) Nonetheless, the contract provided that PSEG had the right to change the scope of work. (DE 62-3 at 43–44.)2 Despite the “line in the sand,” PSEG continued to authorize design changes and send drawings. (Id. ¶¶ 49, 54.) Indeed, it became clear that numerous aspects of the mechanical design had been incomplete, requiring costly, mid-Project changes. (Id. ¶ 61.) Further complicating the Project, PSEG failed to manage the other contractors or provide necessary, promised supplies. (Id. ¶¶ 63, 69, 73.) Not only that, PSEG had Durr perform additional work at another site. (Id. ¶¶ 81–82.) All the while, Durr submitted progress payment applications to PSEG for the work it had performed, which PSEG failed to pay. (Id. ¶¶ 77–78) When the Project was finally completed, “PSEG began a concerted effort to avoid its payment obligations” entirely. (Id. ¶ 87.) PSEG hoped that Durr would “accept an amount less than it had earned for its work on the Project, or to abandon its claims.” (Id. ¶ 101.) As part of this effort, PSEG informed Durr’s surety that PSEG was considering declaring Durr to be in default—even though PSEG owed Durr money under the contract. (Id. ¶¶ 102–04.) As a result of actions like these, PSEG “has effectively destroyed Durr” and allegedly owes Durr tens of millions of dollars. (Id. ¶¶ 111, 114.) B. Procedural History Durr filed this action against PSEG. (DE 1.) The currently operative Amended Complaint asserts eight claims: (1) breach of contract (Am. Compl. ¶¶ 113–15); (2) violation of New Jersey Prompt Payment Act, N.J. Stat. Ann. § 2A:30A-1, et seq. (Am. Compl. ¶¶ 116–24); (3) cardinal change (id. ¶¶ 125–28);

2 The Amended Complaint relied on and attached as exhibits certain excerpts of the contract. (DE 48-8) PSEG submitted the entire contract with its motion to dismiss (DE 62-3, 62-4). Because the contract is “integral to or explicitly relied upon in the complaint,” and its authenticity is not disputed, I may consider it on a motion to dismiss. Doe v. Univ. of Scis., 961 F.3d 203, 208 (3d Cir. 2020) (citation omitted). (4) quantum meruit and unjust enrichment (id. ¶¶ 129–32); (5) breach of the covenant of good faith and fair dealing (id. ¶¶ 133–44); (6) misrepresentation (id. ¶¶ 145–55); (7) tortious interference with contract (id. ¶¶ 156–63); and (8) tortious interference with prospective advantage (id. ¶¶ 164–68). PSEG moves to dismiss Counts 3 through 8. (Mot.) II. STANDARD OF REVIEW Federal Rule of Civil Procedure 8(a) does not require that a pleading contain detailed factual allegations. Still, the pleading must contain “more than labels and conclusions.” Bell Atl. Corp. v. Twombly, 550 U.S. 544, 555 (2007). The allegations must raise a claimant’s right to relief above a speculative level, so that a claim is “plausible on its face.” Id. at 570. That standard is met “when the plaintiff pleads factual content that allows the court to draw the reasonable inference that the defendant is liable for the misconduct alleged.” Ashcroft v. Iqbal, 556 U.S. 662, 678 (2009). Rule 12(b)(6) provides for the dismissal of a complaint if it fails to state a claim upon which relief can be granted. The moving party bears the burden of showing that no claim has been stated. See Animal Sci. Prods., Inc. v. China Minmetals Corp., 654 F.3d 462, 469 n.9 (3d Cir. 2011). The facts in the complaint are accepted as true, and all reasonable inferences are drawn in favor of the plaintiff. N.J. Carpenters & Trs. Thereof v. Tishman Constr. Corp. of N.J., 760 F.3d 297, 302 (3d Cir. 2014). III. DISCUSSION I apply the foregoing motion-to-dismiss standards to each claim. In sum, I hold that the claims of cardinal change (Count 3) and tortious interference with contract (Count 7) require dismissal, while the rest survive. A. Cardinal Change Claim Count 3 is a claim under the “cardinal change” doctrine. (Am. Compl. ¶¶ 125–28.) This doctrine, derived from federal government contracts law, holds that “when the government effects an alteration in the work so drastic that it effectively requires the contractor to perform duties materially different from those originally bargained for,” then the government has effected a “cardinal change” and is in breach. Rumsfeld v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
Cristen M. Gleason v. Norwest Mortgage, Inc
243 F.3d 130 (Third Circuit, 2001)
LK Comstock & Co., Inc. v. Becon Const. Co., Inc.
932 F. Supp. 906 (E.D. Kentucky, 1993)
Frederico v. Home Depot
507 F.3d 188 (Third Circuit, 2007)
Bak-A-Lum Corp. of America v. Alcoa Building Products, Inc.
351 A.2d 349 (Supreme Court of New Jersey, 1976)
Jewish Center of Sussex Cty. v. Whale
432 A.2d 521 (Supreme Court of New Jersey, 1981)
Fuller Co. v. Brown Minneapolis Tank & Fabricating Co.
678 F. Supp. 506 (E.D. Pennsylvania, 1987)
Kas Oriental Rugs, Inc. v. Ellman
926 A.2d 387 (New Jersey Superior Court App Division, 2007)
Kaufman v. I-Stat Corp.
754 A.2d 1188 (Supreme Court of New Jersey, 2000)
Wade v. Kessler Institute
798 A.2d 1251 (Supreme Court of New Jersey, 2002)
Singer v. Beach Trading Co., Inc.
876 A.2d 885 (New Jersey Superior Court App Division, 2005)
Saltiel v. GSI Consultants, Inc.
788 A.2d 268 (Supreme Court of New Jersey, 2002)
Wilson v. Amerada Hess Corp.
773 A.2d 1121 (Supreme Court of New Jersey, 2001)
Tessler and Son, Inc. v. Sonitrol SEC. Systems of Northern New Jersey, Inc.
497 A.2d 530 (New Jersey Superior Court App Division, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
DURR MECHANICAL CONSTRUCTION, INC. v. PSEG FOSSIL, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/durr-mechanical-construction-inc-v-pseg-fossil-llc-njd-2021.