DURR MECHANICAL CONSTRUCTION, INC. v. PSEG FOSSIL, LLC

District Court, D. New Jersey·Decided March 18, 2021·No. 2:18-cv-10675·Unknown

Opinion

UNITED STATES DISTRICT COURT FOR THE DISTRICT OF NEW JERSEY

DURR MECHANICAL CONSTRUCTION, INC., Plaintiff, Civ. No. 18-10675 (KM) (CLW) v. OPINION AND ORDER PSEG FOSSIL, LLC, Defendant.

KEVIN MCNULTY, U.S.D.J.: Durr Mechanical Construction, Inc., and PSEG Fossil, LLC, are involved in litigation after a construction project went awry. I previously dismissed Durr’s claim under the cardinal change doctrine, finding that that doctrine was not recognized under New Jersey law. (DE 75, 76;1 see also Durr Mech. Constr., Inc. v. PSEG Fossil, LLC, Civ. No. 18-10675, 2021 WL 303030, at *3–5 (D.N.J. Jan. 29, 2021).) Now Durr moves, pursuant to 28 U.S.C. § 1292(b), to certify an interlocutory appeal on the question of whether New Jersey recognizes the cardinal change doctrine. (DE 79.) For the following reasons, the motion is DENIED. I. BACKGROUND I assume familiarity with the facts as set forth in my prior opinion. Durr, 2021 WL 303030, at *1–2. As relevant here, Durr worked as a contractor for PSEG on a power plant project. Id. at *1. The contract provided that PSEG had the right to change the scope of work. Id. PSEG constantly and drastically changed the work required of Durr in a manner Durr considered excessive. Id. at *2. At the end of the project, PSEG avoided its payment obligations. Id.

1 Certain citations to the record are abbreviated as follows: DE = docket entry Durr Ltr. = Durr’s Letter (DE 79) Durr sued PSEG, asserting contract, quasi-contract, and tort claims. Id. PSEG moved to dismiss most of those claims, although not the marquee breach of contract claim. Id. I dismissed, among others, Durr’s “cardinal change” claim (Count 3). Id. at *3. The cardinal change doctrine comes from federal government contracts law. It holds that “when the government effects an alteration in the work so drastic that it effectively requires the contractor to perform duties materially different from those originally bargained for,” then the government has effected a “cardinal change” and is in breach. Rumsfeld v. Freedom NY, Inc., 329 F.3d 1320, 1332 (Fed. Cir. 2003) (citation omitted). The doctrine arose because government contracts often grant the government significant leeway to modify the contract. The doctrine acts as an equitable check on the extent of modifications. Green Mgmt. Corp. v. United States, 42 Fed. Cl. 411, 429 (1998); Exec. Bus. Media, Inc. v. U.S. Dep’t of Def., 3 F.3d 759, 763 n.3 (4th Cir. 1993). I dismissed the cardinal change claim because there were insufficient indicia that New Jersey would recognize such a claim: (1) No New Jersey court had precedentially adopted it; (2) the unpublished Appellate Division opinions which Durr cited were distinguishable; (3) there was not a majority view from other jurisdictions; and (4) the doctrine was in some tension with New Jersey contract law, which disfavors implied limits to express provisions in a contract. Durr, 2021 WL 303030, at *3–5. After my dismissal, Durr moved via letter brief to certify for interlocutory appeal the question of whether New Jersey recognizes the cardinal change doctrine. (Durr Ltr. at 1.) What Durr really wants is to have the New Jersey Supreme Court consider the question (id. at 4), but there is no procedure for this district court to certify a question of law to the state Supreme Court. See Cohen v. Chase Bank, N.A., 679 F. Supp. 2d 582, 590 n.6 (D.N.J. 2010) (the New Jersey Supreme Court does not accept questions from the district court). Thus, what Durr proposes is a bank shot. If allowed to appeal, Durr would immediately ask the Third Circuit in turn to certify the question to the New Jersey Supreme Court. (Durr Ltr. at 4.) See generally N.J. Ct. R. 2:12A-1 (permitting the New Jersey Supreme Court to answer questions of New Jersey law from the Third Circuit). PSEG opposes the motion. (DE 81.) II. DISCUSSION Generally, a litigant may appeal only final decisions of federal district courts. Def. Distrib. v. Att’y Gen. of N.J., 972 F.3d 193, 198 (3d Cir. 2020). Interlocutory orders, like a partial dismissal, merge with the final judgment, and so an appeal encompasses review of such orders. See Verma v. 3001 Castor, Inc., 937 F.3d 221, 228 (3d Cir. 2019) (stating general merger rule); Head v. Chi. Sch. Reform. Bd. of Trs., 225 F.3d 794, 800 (7th Cir. 2000) (appeal of summary judgment order brought up earlier order dismissing some, but not all, claims without prejudice). The final judgment rule, however, is “subject to limited exceptions.” Def. Distrib., 972 F.3d at 198. One exception is for certified questions. A non-final order may be certified for appeal if the court determines that it (1) involves a “controlling question of law,” (2) for which there is “substantial ground for difference of opinion,” and (3) which may “materially advance the ultimate termination of the litigation” if appealed immediately. 28 U.S.C. § 1292(b). But even if these criteria are met, certification is discretionary. ADP, LLC v. Ultimate Software Grp., Inc., Civ. No. 16-8664, 2018 WL 1838003, at *3 (D.N.J. Apr. 17, 2018). Moreover, there is a strong policy against departing from the final judgment rule, Def. Distrib., 972 F.3d at 198, so courts require the movant to show “exceptional circumstances” warranting application of § 1292(b), Karagjozi v. Bruck, Civ. No. 17-63, 2017 WL 3528002, at *2 (D.N.J. Aug. 16, 2017) (citation omitted). I address each prong in turn. A. Controlling Question of Law A controlling question of law is one which, if answered erroneously, “would be reversible error on final appeal.” Katz v. Carte Blanche Corp., 496 F.2d 747, 755 (3d Cir. 1974) (en banc). “Controlling” also means “serious to the conduct of the litigation, either practically or legally.” Id. The question of whether New Jersey recognizes a cardinal change claim is not controlling. Durr’s cardinal change claim is essentially a specific type of breach of contract claim, and Durr already has a live breach of contract claim. That breach claim will require the same factual development as any cardinal change claim. Perhaps Durr will prevail on it, rendering the cardinal change issue unimportant. But even if I were to eventually grant summary judgment to PSEG, Durr were to appeal, and the Third Circuit were to hold that the cardinal change claim was cognizable, that holding would not necessarily result in reversal. The factual record would look much the same, and either the appellate court or this court might well be in a position simply to apply the correct legal standard to it. See Blackledge v. Blackledge, 866 F.3d 169, 182 (3d Cir. 2017) (the court of appeals may affirm on any ground supported by the record); Tri-M Grp., LLC v. Sharp, 638 F.3d 406, 417–18 (3d Cir. 2011) (remand unnecessary when record is complete and question is one of law).

Free access — add to your briefcase to read the full text and ask questions with AI

DURR MECHANICAL CONSTRUCTION, INC. v. PSEG FOSSIL, LLC, (D.N.J. 2021).

DURR MECHANICAL CONSTRUCTION, INC. v. PSEG FOSSIL, LLC (DURR MECHANICAL CONSTRUCTION, INC. v. PSEG FOSSIL, LLC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

TRI-M GROUP, LLC v. Sharp
638 F.3d 406 (Third Circuit, 2011)
Reese v. BP Exploration (Alaska) Inc.
643 F.3d 681 (Ninth Circuit, 2011)
Cohen v. Chase Bank, N.A.
679 F. Supp. 2d 582 (D. New Jersey, 2010)
Charles Blackledge v. Olga Blackledge
866 F.3d 169 (Third Circuit, 2017)
Adrian Lupu v. Loan City LLC
903 F.3d 382 (Third Circuit, 2018)
Priya Verma v. 3001 Castor Inc
937 F.3d 221 (Third Circuit, 2019)
Green Management Corp. v. United States
42 Cont. Cas. Fed. 77,412 (Federal Claims, 1998)
Federal Trade Commission v. Wyndham Worldwide Corp.
10 F. Supp. 3d 602 (D. New Jersey, 2014)