Dorsey Bros., Inc. v. Anderson

287 A.2d 270, 264 Md. 446, 1972 Md. LEXIS 1160
CourtCourt of Appeals of Maryland
DecidedFebruary 10, 1972
Docket[No. 198, September Term, 1971.]
StatusPublished
Cited by14 cases

This text of 287 A.2d 270 (Dorsey Bros., Inc. v. Anderson) is published on Counsel Stack Legal Research, covering Court of Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dorsey Bros., Inc. v. Anderson, 287 A.2d 270, 264 Md. 446, 1972 Md. LEXIS 1160 (Md. 1972).

Opinion

Digges, J.,

delivered the opinion of the Court.

This dispute is almost identical to the controversy in another case decided this week and both revolve around the weather conditions during the summer of 1969 in which extreme drought and then almost continuous rainfall played havoc with Maryland’s farm community. The other appeal, Friel v. Handley, 264 Md. 433, 287 A. 2d 23 (1972), concerned itself with the problem of harvesting corn during the rainy days of late July and early August. The case now before us, removed from Somerset County to the Circuit Court for Wicomico County (Travers, J.), presents the alternate problem of the drought and its effect on a snap bean crop in June and July of 1969.

The appellee, Howard Anderson, orally contracted to plant and cultivate three separate fields of beans totaling about 28 acres, located in Somerset County, for the appellant, Dorsey Brothers, Inc. Under the terms of this verbal agreement, Dorsey was to determine when the beans were ripe for harvest and then send machinery to pick them at its own expense. It was anticipated that Anderson’s crop would be ready to gather in very early July. However, during the latter part of June there was a serious drought condition throughout much of this area which affected the beans in two ways: not only did *448 it speed up the maturing process but it also dehydrated them. Anderson became apprehensive about the effects of this weather on his crop and notified appellant that it should be picked on Tuesday, July 1, because in his opinion the beans would mature by then. He was told by Mrs. Elizabeth Dorsey, an owner of appellant, that the pickers would be there on that date. Anderson’s fields had also been inspected by Paul Lynch, Dorsey’s coordinator of harvesting, and he indicated on June 30 that he would first pick Carroll Ennis’ crop, which had been planted earlier, and then return to get appellee’s beans. It took until July 2 to harvest at Ennis’ farm but rather than proceed to Anderson’s immediately, Lynch had the crew go elsewhere because he felt that other fields were of better quality. Finally, on July 4 Lynch brought the equipment to appellee’s farm and began the picking. However, after covering less than four acres of the first field the crew was instructed to cease its labor and begin instead on the second. Once there, Lynch had the pickers only harvest certain areas and after a short time he had them discontinue this work also. While on the second tract, the machinery was driven in such a way as to destroy much of the unpicked crop. Lynch did not even attempt to harvest the beans on the third field but informed appellee that the remainder of the crop was not acceptable. Of the two loads already picked, one was subsequently rejected in New York by the processor because it contained excess “cull” material. 1 Based on Dorsey’s failure to harvest the beans, Anderson filed this suit claiming damages for breach of contract. At a jury trial appellee was awarded $4,500 and from the ensuing judgment this appeal is taken. 2

*449 Dorsey first argues that since the ascertainment of the optimum time for harvesting was in its sole judgment, this discretionary matter can only be challenged upon a showing of bad faith or fraud. It then claims that since this was not indicated, no issue was presented for the jury’s determination. In support of its position appellant quotes from Stamatiades v. Merit Music, 210 Md. 597, 614, 124 A. 2d 829 (1956) :

“Though much is left to the discretion of the party to whom the thing or service must be satisfactory, and the judgment of a court is not to be substituted for the honest, even though misguided, judgment of the party, his judgment must be exercised honestly and in good faith. His dissatisfaction ‘must be real and not pretended, capricious, mercenary, or the result of a dishonest design.’ ”

We concur with this statement but find it is not completely determinative of the issue here. The decision of when to pick Anderson’s snap beans, by the terms of the contract, was in the discretion of Dorsey alone and we agree that in the absence of bad faith or fraudulent design its judgment cannot be disturbed. However, in the case before us there was evidence offered which, if believed, could demonstrate that appellant’s failure to harvest the crop was unreasonable and not made in good faith.

To begin with there was testimony that the effect of hot temperatures and drought on any snap beans is not only to accelerate the maturing process but also to dehydrate the crop. But in spite of this appellant’s field manager, Lynch, elected not to pick the beans on July 1. Since this type of crop, even under normal weather conditions, must be harvested within a few days of when it ripens, a three day delay during a drought is evidence from which a jury may conclude bad faith was exhibited. Lynch’s testimony that the picking was additionally put off from July 3 to July 4 so another farmer’s beans of *450 better quality could be harvested, may similarly be an arbitrary decision and evidence of bad faith. Indeed, if Anderson’s crop on Thursday July 3 was not in the best condition, another day’s postponement, when time was so crucial, certainly did not benefit the beans. There was also the testimony of two impartial witnesses whose cumulative experience in farming, including the cultivation of snap beans, was eighty years. Both these gentlemen had inspected appellee’s fields on July 6 and it was their opinion that this was still a good crop; one of the men even said he considered this a “wonderful yield” of beans.

This evidence, though not conclusive of a capricious or mercenary design by appellant, does present an issue to be submitted to the jury for its determination. While the jury may not substitute its own judgment for that which Dorsey honestly made, it surely can conclude from the evidence presented that appellant’s decision not to harvest the-beans was unreasonable and manifested bad faith. Friel v. Handley, 264 Md. 433, 287 A. 2d 23 (1972) ; Volos, Ltd. v. Sotera, 264 Md. 155, 286 A. 2d 101 (1972) ; First National v. Warren-Ehret, 247 Md. 652, 657-61, 233 A. 2d 811 (1967) ; Ferris v. Polansky, 191 Md. 79, 59 A. 2d 749 (1948) ; Distilleries v. Machine Works, 174 Md. 12, 197 A. 599 (1938) ; Devoine Co. v. International Co., 151 Md. 690, 136 A. 37 (1927) ; B. & O. R. R. Co. v. Brydon, 65 Md. 198, 3 A. 306 (1886) ; Lynn v. B. & O. R. R. Co., 60 Md. 404 (1883).

The same conclusion would be reached if we decided this case were governed by Art. 95B of the Maryland Code (Uniform Commercial Code — Sales). However, since the applicability of that statute to the type of transaction involved here was not considered by appellant in its brief and not fully discussed at oral argument, we will await another opportunity before considering this question.

Dorsey next contends that Judge Travers erroneously instructed the jury as to what circumstances must be found to exist before Anderson would be entitled to recover. The disputed statement was:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rainey v. State
280 A.3d 697 (Court of Appeals of Maryland, 2022)
In Re National Energy & Gas Transmission, Inc.
351 B.R. 323 (D. Maryland, 2006)
CSX Transportation, Inc. v. Haischer
824 A.2d 966 (Court of Special Appeals of Maryland, 2003)
Germain v. State
769 A.2d 931 (Court of Appeals of Maryland, 2001)
Thorne v. Contee
565 A.2d 102 (Court of Special Appeals of Maryland, 1989)
Hairston v. State
511 A.2d 73 (Court of Special Appeals of Maryland, 1986)
Paige v. Manuzak
471 A.2d 758 (Court of Special Appeals of Maryland, 1984)
Griffith v. Montgomery County
470 A.2d 840 (Court of Special Appeals of Maryland, 1984)
Hawkins v. State
436 A.2d 900 (Court of Appeals of Maryland, 1981)
Thimatariga v. Chambers
416 A.2d 1326 (Court of Special Appeals of Maryland, 1980)
Feeney v. Dolan
371 A.2d 679 (Court of Special Appeals of Maryland, 1977)
Modular Technology Corp., Metal Board Division v. City of Lubbock
529 S.W.2d 273 (Court of Appeals of Texas, 1975)
A. S. Abell Co. v. Skeen
288 A.2d 596 (Court of Appeals of Maryland, 1972)

Cite This Page — Counsel Stack

Bluebook (online)
287 A.2d 270, 264 Md. 446, 1972 Md. LEXIS 1160, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dorsey-bros-inc-v-anderson-md-1972.