Domino Group, Inc. v. Charlie Parker Memorial Foundation

985 F.2d 417, 1993 U.S. App. LEXIS 1804, 1993 WL 23772
CourtCourt of Appeals for the Eighth Circuit
DecidedFebruary 5, 1993
Docket91-3588
StatusPublished
Cited by66 cases

This text of 985 F.2d 417 (Domino Group, Inc. v. Charlie Parker Memorial Foundation) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Domino Group, Inc. v. Charlie Parker Memorial Foundation, 985 F.2d 417, 1993 U.S. App. LEXIS 1804, 1993 WL 23772 (8th Cir. 1993).

Opinion

LOKEN, Circuit Judge.

Domino Group, Inc. (“Domino”), appeals a district court order vacating a confirmed arbitration award, denying Domino alternative damage relief, and setting the case for trial. Although we otherwise agree with the district court’s analysis, we conclude that it erred in vacating its prior confirmation of the award. Accordingly, we modify the district court’s order and remand the case for further proceedings.

I.

The Charlie Parker Memorial Foundation (“Foundation”) owns the International Jazz Hall of Fame. On April 24, 1985, the Foundation entered into a written Production Contract with Domino relating to “International Jazz Hall of Fame induction ceremonies.” Paragraph 3 of the contract provided that Domino “Agrees to produce the ceremonies, specifically on the evening of August 21, 1985.” Article J of the contract’s preamble provided that, “Acceptance of this contract gives [Domino] the sole option to produce the next ten (10) ceremonies.”

Domino produced the 1985 awards ceremony, which was a money-losing failure. When the Foundation refused to allow Domino (or any other producer) to produce additional ceremonies, Domino filed a claim for arbitration under the arbitration clause in the contract, asking that it “be allowed to exercise [its] rights to produce the ceremonies under said contract, or to be compensated therefor.” On August 15, 1986, following a hearing, the arbitrator issued a final award granting Domino’s request for specific performance of the “on-going continuing and subsisting contract.” The arbitrator denied Domino’s alternative request for “substantial monetary damages” as moot.

The Foundation did not timely move to vacate, modify, or correct the arbitrator’s award. See § 12 of the Federal Arbitration Act, 9 U.S.C. § 12. On August 11, 1987, Domino commenced this action by moving to confirm the award under § 9 of the Act. The district court initially denied Domino’s motion for summary judgment because it was unable “to determine what it is the award directs the parties to do.” Then, on May 15, 1989, the court granted Domino’s motion to remand to the arbitrator for clarification of the award. The court explained:

The arbitrator is instructed to clarify what is meant by “Claimant’s request ... for injunctive relief and specific per- *419 formanee is granted.” Namely, the arbitrator should delineate all actions which the parties are to perform “specifically,” including all duties found to be arising from the contract at issue. The object and extent of injunctive relief should be similarly identified.

On April 5, 1990, Domino sent a letter to the arbitrator constituting “claimant’s position on clarification of the Award.” Domino attached an exhibit enumerating “Producer’s Rights” under the contract and urged the arbitrator to “specifically direct the Foundation to permit Domino Group to exercise these enumerated rights.” Domino also argued that “[t]he Foundation’s actions make necessary a consideration of alternative relief,” and urged the arbitrator to award $450,000 damages “as alternative relief.” Domino justified its request for damages by submitting six pages of transcript from the original arbitration hearing that recorded a discussion between Domino’s counsel and the arbitrator concerning the appropriateness of a $450,000 damage award.

On June 6, 1990, without holding a further hearing, the arbitrator issued a Clarification of Award. In a cryptic, nearly unintelligible decision, the arbitrator adopted the list of specific Producer’s Rights submitted by Domino, commenting that “[c]o-operation should and ought remove any doubt as to just how to undertake performance” of the contract. The arbitrator further agreed that Domino’s suggested $450,000 damage award “does provide a good basis of alternative relief.” The decision concluded, “All that need be added is that these suggested and proposed courses for relief are adopted as the resolution of this arbitration.”

On September 28, 1990, the district court granted Domino’s uncontested motion to confirm the clarified award. The court’s order directed entry of judgment in favor of Domino for specific performance, incorporating the list of Producer’s Rights adopted in the Clarification of Award. The order further stated that, if the Foundation refused to permit Domino to exercise these rights, “plaintiff may seek damages.”

On July 8, 1991, Domino moved the court to enter judgment for $450,000 damages “in addition to the award for specific performance.” Domino submitted a short affidavit by Domino’s president stating that the Foundation had continued to refuse to permit Domino to perform under the contract. In response, the district court ruled that the award of damages in the Clarification of Award was “in manifest disregard of the law and evidential record in these proceedings.” The court concluded that a further remand to the arbitrator would be futile. It therefore vacated the arbitrator’s award and clarification and ordered that the case be “returned to the docket of this court for trial.”

This appeal followed. We have jurisdiction to review a district court order vacating an award. 9 U.S.C. § 16(a)(1)(E). On appeal, Domino argues that the district court erred in vacating the arbitrator’s award and that Domino is entitled to a judgment for $450,000 damages based upon the arbitrator’s Clarification of Award. The Foundation argues that the district court properly vacated the arbitrator’s awards but erred in setting the case for trial. The Foundation argues that the case be referred to a new arbitration panel for “full arbitration proceedings.”

II.

We have recited the procedural history of this case in detail because in our view it is critical to a proper resolution of the issues raised on appeal. The answer to most of these issues becomes readily apparent when put in the context of the limited nature of judicial review of arbitration awards under the Federal Arbitration Act:

First, the Foundation’s failure to file a motion to vacate, modify, or correct within three months of either the initial award or the Clarification of Award waived any defenses to confirmation that might be asserted in a timely motion to vacate. See, e.g., Local Union No. 36, Sheet Metal Workers’ Int’l Assn. v. Atlas Air Conditioning Co., 926 F.2d 770, 772 (8th Cir.1991); Sanders-Midwest, Inc. v. Midwest *420 Pipe Fabricators, Inc., 857 F.2d 1235, 1237-38 (8th Cir. 1988); Piccolo v. Dain, Kalman & Quail, Inc., 641 F.2d 598, 600 (8th Cir.1981). Absent a timely motion to vacate, in most cases “the confirmation of an arbitration award is a summary proceeding that makes what is already a final arbitration award a judgment of the court.” Florasynth, Inc. v. Pickholz, 750 F.2d 171, 176 (2d Cir.1984).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Signal 88 v. Lyconic
310 Neb. 824 (Nebraska Supreme Court, 2022)
J.B. Hunt Transport, Inc. v. BNSF Railway Company
9 F.4th 663 (Eighth Circuit, 2021)
Signal 88 v. Lyconic
29 Neb. Ct. App. 533 (Nebraska Court of Appeals, 2021)
Saltzman v. Russell
D. Nebraska, 2019
Glaser v. Legg
928 F. Supp. 2d 236 (District of Columbia, 2013)
Turner v. UNITED STEELWORKERS OF AMER., LOCAL 812
581 F.3d 672 (Eighth Circuit, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
985 F.2d 417, 1993 U.S. App. LEXIS 1804, 1993 WL 23772, Counsel Stack Legal Research, https://law.counselstack.com/opinion/domino-group-inc-v-charlie-parker-memorial-foundation-ca8-1993.