POET Design & Construction, Inc. v. Andritz Inc

CourtDistrict Court, D. South Dakota
DecidedMay 14, 2019
Docket4:19-cv-04070
StatusUnknown

This text of POET Design & Construction, Inc. v. Andritz Inc (POET Design & Construction, Inc. v. Andritz Inc) is published on Counsel Stack Legal Research, covering District Court, D. South Dakota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
POET Design & Construction, Inc. v. Andritz Inc, (D.S.D. 2019).

Opinion

UNITED STATES DISTRICT COURT DISTRICT OF SOUTH DAKOTA SOUTHERN DIVISION In the matter of American Arbitration 19-4070 Association Arbitration No. 02-16-0001-3705: POET DESIGN & CONSTRUCTION, INC., ORDER CONFIRMING ARBITRATION AWARD Claimant, Vs. ANDRITZ INC., Respondent.

This is a diversity case in which Claimant, POET Design & Construction, Inc. (“POET”) commenced this action on April 2, 2019, by filing its Application to Confirm Arbitration Award (“Application”). Doc. 1. Filed under seal concurrent with the Application are copies of: 1) the Final Award of Arbitrators dated April 1, 2019, Doc. 1, Ex. A; 2) the Short Form of Agreement Between Design Builder and Engineer for Professional Services entered into by and between POET and Andritz, Inc. (“the Engineering Contract”), Doc. 1, Ex. B; and 3) the Standard Form of Agreement Between Design Builder and Contractor entered into by and between POET and Andritz, Inc. (“the Performance Contract”), Doc. 1, Ex. C. For the following reasons, the Application to Confirm Arbitration Award, Doc. 1, is granted. I. Summary of Undisputed Material Facts This dispute arises from POET’s construction of a state-of-the art cellulosic ethanol facility in Emmetsburg, Iowa, known as “Project Liberty” (“the Project”). Doc. 1, 9 3. POET began working with Andritz, Inc. (“Andritz”) in or around 2009 for the purpose of developing a pre- treatment system (“the System”’) for the Project, to be designed and supplied by Andritz. Doc. 1, q 4.

On or about July 12, 2010, POET and Andritz entered into an Engineering Contract to provide certain design and engineering services in furtherance of providing POET the System. Doc. 1, 5. Subsequently, on or about August 29, 2012, POET and Andritz entered into the

Performance Contract for the System. Doc. 1, § 6. The Performance Contract contains an arbitration provision which provides in pertinent part that: Claims... for which initial decisions have not become final and binding, and which have not been resolved by negotiation or mediation, but which are subject to arbitration pursuant to Section 6.2 and 6.3 of the Agreement .. . may at the option of either party, be submitted to, and shall finally be decided by, arbitration which, unless the parties mutually agree otherwise, shall be in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association currently in effect at the time of the arbitration . . . Any arbitration under this provision will be held in Minnehaha County, South Dakota by a panel of three arbitrators unless otherwise agreed by the parties.

The award rendered by the arbitrator or arbitrators shall be final, and judgment may be entered upon it in accordance with applicable law in any court having jurisdiction thereof. Doc. 1, Ex. C, §§ A.4.4.1 and A.4.4.4. Certain disputes arose between POET and Andritz regarding Andritz’s performance and provision of the System under the Performance Contract. Doc. 1, § 8. As a result of the parties’ disputes, pursuant to the Performance Contract, on or about April 18, 2016, POET commenced an arbitration against Andritz with the American Arbitration Association (“the AAA”) pursuant to the Construction Industry Arbitration Rules then in effect (“the Arbitration”). Doc. 1,99. A panel of three arbitrators was subsequently appointed by the AAA: Adrian L. Bastianelli, Stephen K. Yungblut and H. Bruce Shreves (collectively, “the Panel”). Doc. 1,9] 10. Andritz denied POET’s claim and alleged certain counterclaims against POET relating to the Project and POET denied Andritz’s counterclaims. Doc. 1,411. The parties subsequently amended their claims, and all claims arising under the Engineering Contract were consolidated in the Arbitration. Doc. 1, § 12. For the convenience of the parties, witnesses, and counsel, by mutual agreement, the Arbitration hearing was held at the AAA offices located in Chicago, Illinois. Doc. 1,913. On December 3-7, 2018, December 10-14, 2018, and January 7-9, 2019, the Panel held a hearing at which POET and Andritz appeared and offered evidence through live testimony and exhibits □□□□□ Hearing”). Subsequent to the Hearing, by further agreement of the Panel and the parties, the parties submitted post-Hearing briefing to the Panel. Doc. 1, Following the post-Hearing briefing,

the Arbitration was closed on March 1, 2019, from which time the Panel had thirty (30) days to issue its reasoned award. Doc. 1, 16. On April 1, 2019, the Panel issued its reasoned award (“the Award’). In the Award, the Panel unanimously awarded POET the principal amount of $7,533,815.00 in damages against Andritz to be paid “[wl]ithin thirty (30) calendar days from the transmittal of [the Award] to the parties,” along with “interest at the judgment rate in South Dakota accruing on any amounts remaining unpaid thirty days after receipt of [the Award].” The Award is “in full settlement of all claims and counterclaims submitted to this Arbitration. All claims and counterclaims not expressly addressed in or excluded from [the Award] are hereby denied.” Doc. 1, Ex. A at 3. On April 2, 2019, POET filed with the Court its Application to Confirm Arbitration Award (“Application”). Doc. 1. Andritz filed a response and joined in POET’s Application. Doc. 12. In its response, Andritz disputes only two of the allegations detailed by POET in its Application. First, Andritz denies POET’s characterization of the Award’s language to the extent it states that only claims “under” the Engineering Contract and Performance Contracts were resolved by the Award. Andritz stated that “the Award clearly states that it fully settles all of POET’s professional negligence, and alleged tortious conduct, as follows: ‘This award is in full settlement of all claims and counterclaims submitted to this Arbitration. All claims and counterclaims not expressly addressed in or excluded from this Final Award are hereby denied.” Doc. 12, | 19. Second, although Andritz admits and joins in POET’s request that this Court issue an order confirming the Award, Andritz argues that no monetary judgment should be entered against Andritz because all amounts due were paid by the deadline set forth in the Award. Doc. 12, 26. Andritz further states that POET’s Application was unnecessary because it was filed without any consultation with Andritz and because Andritz did not intend to move to vacate the Award and that as a result, “Andritz should not be responsible for any costs of this action.” Doc. 12, J 26. On May 13, 2019, POET filed its Reply brief in support of its Application. Il. Discussion _ Section 9 of the Federal Arbitration Act (“FAA”) provides that “if the parties in their “agreement have agreed that a judgment of the court shall be entered upon the award made pursuant to the arbitration,” then any party may apply, within one year after an arbitration award is made, to the district court for an order confirming the award. 9 U.S.C. § 9. Section 9 of the FAA provides

that federal courts “must. grant” an order confirming an arbitration award “unless the' award is vacated, modified, or corrected as prescribed in section 10 and 11 of [the FAA].” Jd. A district court “affords the arbitrator’s decisions an extraordinary level of deference and confirms so long as the arbitrator is even arguably construing or applying the contract and acting within the scope of his authority.” Wells Fargo Bank, N.A. v. WMN e-PIN, LLC, 653 F.3d 702, 710 (8th Cir. 2001) (quoting Crawford Group, Inc. v. Holekamp, 543 F.3d 971, 976 (8th Cir. 2008)). A motion to vacate, modify, or correct and arbitration award must be filed within 90 days of the initial arbitration award.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wells Fargo Bank, N.A. v. WMR E-Pin, LLC
653 F.3d 702 (Eighth Circuit, 2011)
Crawford Group, Inc. v. Holekamp
543 F.3d 971 (Eighth Circuit, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
POET Design & Construction, Inc. v. Andritz Inc, Counsel Stack Legal Research, https://law.counselstack.com/opinion/poet-design-construction-inc-v-andritz-inc-sdd-2019.